Zorro Ranch Projects / Tasks List
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
JE 3/13 Zorro Ranch water status Memo 3/12/01
3/7 MBI is pressure testing the lines they
should be complete 4/7. Once pressure
testing is complete, MBI will the us a
quote to put well 3&4 on line. to
meet with MBI the week of 4/1 to go over
money saving ideas.
JE Mike Jeff 3/8 Hang the cross in the upper library 3/22 Mike is going to look for the studs to
see if the cross can be centered.
3/28 E-Mail with hanging options will be
sent
3/28 We would like to wait for JE arrival
before we hang the cross it is more involved
than originally thought.
.. 1 WINDOWS \DesktoplCamera
pics.)1cross.JPG
JE Mike 2/27 sketch shelves for the massage room and send to
JE
JE Jeff Mike 2/27 The screw that is on the exercise room door
knobs should be filed down Jeff to replace door handle 3/15
3/22 Jeff has put the handle on the door for
JE approval 3/23
complete
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues FT- Future Construction Issues HM- House Manual
EFTA00578197
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
JE Jeff 2/27 The lights on the LR mantel are too tall find low
profile lights Purchased 3/9. The new lights are not
strong enough to light up the painting. Need
more instructions.
JE Jeff 2/27 The LR gallery painting should have two lights
mounted on the table that will shine on the painting.
The lights should be similar to the ones on the LR
mantel. Sendpictures fora roval Jeff said that he could not find lights that
would mount on the table. Please advise if a
cord across the floor is acceptable.
JE Jeff Landscape lights for Main House All lights have been ordered. They will take
approximately 20 days from order date to
arrive. Expected April 4. left
message for electrician to call 3/19
Message left 3/26
3/28 Scheduled for April 5th
JE Jeff 2/27 When the painting of the Spanish nude with
black hair arrives it is to be hung in front of the
telesco Sendpicture to JE first Picture sent to JE 3/21 per his request
3/22
Com lete
JE Jeff 2/27 Purchase light fixture in UL ceiling to tilt and
shine on easel Jeff purchased 3/10. Jeff is going to see if
he can install himself 3/15
3/29 Jeff is going to purchase 3 fixtures for
JE approval
JE Jeff 2/27 Purchase flood lights over terrace, MB balcony,
back wall at library Purchased 3/9. Will be installed with
landscape lights
3/26 =. Called Service Electric to get
installation date —waiting for call back
Service Electric will be out 3/28
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues IT- Future Construction Issues HM- House Manual 2
EFTA00578198
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
Service Electric is here 3/29
The installation will be very involved, JE to
approve. Jeff has details.
JE Where should the telescope be located? JE to decide location.
JE Lean too and water troft should be painted Token
brown Sample on lean too for JE approval
JE
JE 2/27 Mechanical room door is warped 3/23 Mike is repairing the door front 3/20
3/23
complete
Construct North Terrace at Main House Monarch is tiLgi 1 out the wa11s3/14
Memo from = sent to JE 3/19 re: paving
3/22 waiting for instructions
2/23 JE approved the $5,183.00 quote for
concrete. We are waiting for the 200 pieces
of stone to arrive before they can lay the
concrete. Stone should arrive in 2 weeks
April 7?
JE 3/24 Paint the balustrade the same color as the main
house 3/26 Painters are on site
3/27 Painting on a time and materials basis.
Estimate $5,000.00.
JE to approve
3/27 Painters have put the first coat of paint
to make it look presentable. They will
return after visit if anproved
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SDI- DI- Decorating Issues Fe- Future Construction Issues House Manual 3
EFTA00578199
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
JE 3/29 Finish the Bowl Garden planting 3/29 Eden would like to plant the remainder
of plants in the bowl garden. The cost will
be $564.00 JE to approve.
3/21 Quote to repaint the gray garage doors in shop
area at ranch central 3/23 Will cost $875.00
JE to approve
JE Loggia spot lights not the correct size they need to be
replaced with lower profile lights called Service Electric on 3/12 and
3/15
Purchased new lights 3/24 Called Service
Electric 3/26 waiting for return call
Service Electric is coming out 3/28
Service Electric is here
3/29.AWIND0WS 1 DesktoplCamera 3/29
complete
pics.)11ozzia light.JPCi
JE 3/29 Eden to give quote to seed the remainder of
areas at Main House 3/29 Seeding can begin after May 15th.
Should have quote 3/30
GM Jeff 2/27Research auto pool vac Requesting your approval to purchase pool
vac for $549.00
GM Jeff 2/27 Purchase brown utility shed for MH 3/12 has brochures, Jeff to stake
out proposed area.
3/22 has been staked for approval
GM Deidre 3/12 Train Wolfhounds and Duke???? 3/28 The cost is 63.50 for each dog. The
classes are for 8 weeks, once a week.
Waiting for GM approval. Does Duke need
to go?
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues IT- Future Construction Issues HM- House Manual 4
EFTA00578200
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
GM 2/27 Ask Pinto about the painting design for the
balustrade has sent a memo to Pinto 2/27
Memo 3/5
left message 3/7 for GM to talk to
Pinto in Europe
Memo to GM 3/19
Memo sent from GM 3/21
3/23 JE has approved same color as the
house. 3/28 Requested quote from Bobs.
See painting status page 3
GM
GM 2/27 There should be something that sits on the top of
the heads in the hall near GM office GM to buy candles or something
appropriate
2/27 Purchase two more carpets for the main hall
downstairs they should duplicate the one that is
existing but with brighter colors 3/17 We have placed 3 rugs in this area.
3/17 Pictures have been sent for GM
approval.
Approved and in place 3/20 3/20
complete
GM 2/27 The guest hall needs more photographs
GM 2/27Talk to Ricardo about the roof tile designs for
landscape beds GM sent Ricardo fax.
JE discontinued the services of Ricardo
JE meeting with new designer
GM 2/27 Purchase 70 inch picture light is needed for the
painting of the girl in the main stair hall. Order 4 30
inch lights per GM 3/23 Mike and Jeff ling lights 4-30
inch lights. Spoke to 3/23 and will
send pictures.
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues FT- Future Construction Issues Int- House Manual 5
EFTA00578201
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
3/20 Installed one set of 30 inch lights.
Waiting for GM/JE approval
GM 2/27 Purchase 52 inch picture light of the girl in the
princess staircase
GM 2/27 Purchase light for the painting in the LR gallery
should be 80 inches 3/23 Mike and Jeff hanging lights 2-40inch.
Spoke to 3/23 and wills send p ictures
GM 2/27 Purchase rug for library bathroom 7ft 45inches Arrived and placed 3/15 pictures sent 3/15 3/15
complete
GM 2/27 Purchase rug for basement (end of the main stair
hall)
GM 2/27 Purchase 15x15 rug for exercise room Arrived and placed 3/15 3/15
complete
GM 2/27 Purchase rugs for the east corridor 4 Y2 ft wide x
? The rugs should follow down the hallway upstairs
GM 2/27 Purchase new rug for pool gym hallway 41 x 6 3/22 GM Ordered Zebra Rug 3 weeks ago
from ABC
3/23 should arrive 3/30 per
GM 2/27 Purchase Estancia furniture
GM Zorro pottery
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues FC- Future Construction Issues HM- House Manual 6
EFTA00578202
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
GM GM to send black and white pictures for frames in
upper library Photo dimensions 22 x 15' inches
GM 2/27 Larger photos are need for the garage
GM 2/27 Replace all globe light fixtures
GM 2/27 Take digital photos of the furniture shipment
that arrives from Leah's Shipment arrived 3/7
Digital photos sent to GM 3/7 to ask for
placement instructions
Photos send 3/17
GM Need extra sheets for the guest bedrooms at the main
house (yellow and blue rooms)
GM 3/21 Three rugs have arrived for the main house
Need to know location 3/21 pictures sent to 3/21 3/22
complete 3/22 Have been placed in basement near
elevator..\WINDOWS\DesktopCamera
pics.riruu in elevator areal.JPG
GM Make new easel crank that is larger GM to try to locate original crank
GM 3/23 Mangel ironer training at the MH 3/23 The company does not give training
because it is meant for table linens not
sheets. The girls will practice.
Does GM want us to pursue further?
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues FC- Future Construction Issues HM- House Manual 7
EFTA00578203
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
DI Pinto Replacement plate for estancia wall
DI Pinto Light fixture to replace 2 in JE and GM master bdrm
hall
DI Pinto Sheer curtains for the arches in the hallway in front
of the living room Dimensions sent to Pinto 3/21
HM Advise Tamera that there needs to be water and food
for Max at all times. Add details to house hold
manual 3/15
complete
HM 3/12 Advised Jeff not to take dogs during a visit
Add to household manual 3/15/
complete
2/28 Fix the crumbling column in the estancia arranged for Les Files to come out in 3/29
complete April — it needs to warm up.
Adrian is repairing 3/28
2/27 Give Jeff note book for JE walk throughs 3/15
complete
2/27 Frame the island pictures Pictures taken to Absolute Framing on 3/8
Expect completion 3/29 3/29
2/27 Have someone repair green fountain tiles Vernon tiles will come out in April to repair
tiles. It needs to warm up
Have Western Systems come out to install sound
system when it arrives for Breakfast rm Sound system arrived 3/22
3/23 Western Systems will be out Friday 3/28
complete
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues IT- Future Construction Issues HM- House Manual 8
EFTA00578204
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
3/30 to install
Has been installed but the remote is not
working so Western Systems is trying to
troubleshoot 3/28
3/28 New Remote has arrived Mike is
ro min
2/27 Purchase alarm clocks for guest bedrooms MH
and guest lodge Total of 6 4 have been purchased still need 2 more
(Blue rm and 1 for guest lodge) 3/22
Complete
Blue Mobile home to be moved to gravel pit Electric disconnected 3/13
Phone disconnected 3/13 3/14
Complete
2/27 Have the courtyard tree lights repaired Fixed 3/10 — Transformer was out 3/10
complete
2/26 Get a price on the butternut carpet sample for
the bunkhouse will be out to measure bunkhouse to
give an estimate2/26
Will have prices 3/27 for GM approval
has prices for GM 3/29
2/25 Get estimate to repair roads Estimate sent to GM and Eric 3/13
E-mail from 3/21 not doing the roads
per JE
GM has asked us to explore other options.
Call Larry to investigate road equipment
options to maintain roads in usable
condition.
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues FC- Future Construction Issues HM- House Manual 9
EFTA00578205
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
3/15 Repair stone diamonds in front motor court at
MH Masons are working on the repairs 3/15
Pictures sent to JE, GM, SM
3/28..1 WINDOWS 1 DesktoplCamera 3/22
complete
ics. \motor court stoneworkl.JPG
Repair transmitting station for wells. (controls the
water level in the tank) 3/20 Val Comm to give a proposal to repair
or replace transmitters
3/23 Desert Scene painting from Leah's 3/26 Mike to
Hang.AWINDOWS1DesktoplCamera 3/20
complete
pics.)1desert paintink.JPG
Hook up voice mail to GM line 832 1746 3/23 Val Comm is going to hook up the
voice mail because it is on a microwave line
3/28 should be on by Monday 4/1
3/28 Shana to purchase answering machine
for GM to use until voice mail is hooked up
Main House phone lines have interference and poor
reception Val Comm and Sawyers are trouble
shooting problems. 3/28 Sawyers is Fed
Exing a new CPU card.
3/28 Val-com and Sawyers are
reprogramming the system
3/29 Complete. They had to reprogram the
entire system Tom said there may be a few
"bugs" over the next few days. The phone
lines seem clear. 3/29/01
complete
Mike Mike to make bases for library vestibule tables
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues EC- Future Construction Issues House Manual I0
EFTA00578206
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
Mike 2/27 make 2 10 ft benches out of the timbers for the
loggia
Mike 2/27 Change cords on the light in the library
vestibule to a black one 3/5 Service Electric changed one cord Mike
to change the second
Mike Order steam room door sweeps Mike has installed the sat but the still
are not the correct size. is working on
locating sweeps 3/19
3/21 Piece being shipped from Denver
3/28 Digital pictures sent to
Mike Build Motor court gates at MH Gates have been built will be hung 3/20
Mike is working on the pole barn — weather
is good so gates on
hold.WINDOWS DesktoplCamera 3/20
complete
pies.Mate.JPG
Mike Red doors into tables
Mike Sand and seal tables and benches for the main house
Mike Guest lodge — repair crawl space enclosure
Mike Chicken coop to be moved to area near stabels
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues FC- Future Construction Issues HM- House Manual 11
EFTA00578207
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
7 Mike Screen doors to be repaired at bunkhouse, Shannons
house and office
Mike Ventilation at pump pit for ranch central
Mike Repair French doors at Bunkhouse
Mike 2/27 Cover hole in wall under the yellow bedroom
sink at MH 3/20
complete
Mike Estancia pews Mike received JE instructions 3/14
Mike Close in Sterilizer
Mike Pole barn enclosure We can only work on the pole barn in the
mornings because the wind picks up in the
afternoon. Mike has 'A the siding on 3/21
3/30 Mike has Y4 of the siding
up.AWINDOWS\DesktoplCamera
pics.11pole bam.JPG
Mike The guest lodge sliding glass door does not lock
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues FC- Future Construction Issues HM- House Manual 12
EFTA00578208
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
Manoltio
Larry 2/28 Lany to purchase John Deer Gator for the ranch 3/28 to see if we can purchase one
in N.M.
3/14 Take down the TV screen in the bunkhouse
living nn and put into storage
3/14 Hang ranch blueprints in garage
Clutch on the water truck is broken Truck taken to be repaired should return
3/23 3/17
complete
Lany Larry is ordering TV for breakfast room TV arrived 3/7 3/8
complete
Jeff Jeff to measure the pool doors at the main house for
Gary Measured and faxed to Gary 3/13 3/13
Complete
Jeff CD player is being repaired Picked up 3/13 3/13
complete
Jeff The stakes for the MH drive should be 24 inches and
have flat tops. Around the curves they should get
closer together. They should have whiter square
reflectors
Jeff 3/28 Jeff to power wash the diamonds in the front
motor court
Jeff 3/28The stack of wood near the microwave dish
needs to be relocated for the visit Advised Jeff 3/27 3/28
3/29
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues IT- Future Construction Issues House Manual 13
EFTA00578209
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
7 complete
Deidre 3/15 Purchase emergency kits for each vehicle ordering 3/28
David 3/15 Remove remainder of the cactus on the ranch 3/30 David will begin mid April 6/1
Build 3 17x 20 frames and 3 17x22 inch frames made
out of dark wood 3/30 advised that GM wants
to locate a photo shop to make frames
2/27 When the large chess set arrives it belongs in the
north garden Arrived 3/8 will be placed 3/16 3/16
complete
2/27 Check telephone in exercise room The house is not wired for a telephone in
the massage room - plate to be installed
over circuit and Bobs paint to touch up 3/9
complete
Shana Find snow melt that contains OJ 3/30 advised high priority Shana will
begin April 1
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues Fe- Future Construction Issues House Manual 14
EFTA00578210
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
7 urns to be sent back to NY when delivered to Shipped 3/6 to 71st street 3/6
complete the ranch
Assemble balustrade at main house They are caulking the balustrade 3/14 will
take 2 weeks to finish weather permitting 3/27
complete
Paint large ranch house 3/15 the house is half painted weather
permitting should be complete 3/20 3/20
complete
Ranch Central - the stables should be painted the
same color as the inside As soon as it warms up Bobs paint can
begin
3/22 Sam les on barn
2/27 Paint he shelves in the garage the same color as
the walls Bobs paint will be out the week of the 19th
of March. 3/26/
Complete
3/27 Elevator lights are not working 3/29 Service Electric has repaired 3/29/01
complete
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues Fe- Future Construction Issues HM- House Manual 15
EFTA00578211
Zorro Ranch Projects / Tasks List
PROJ.
SORT ASSIGN. DATE & DESCRIPTION STATUS COMP.
TO DATE
7
SORT KEY
JE- Mr. Epstein GM- Ms. Maxwell SM- DI- Decorating Issues FC- Future Construction Issues HM- House Manual 16
EFTA00578212
📷 Images in this document (16 detected; 6 largest described)
AI-generated factual descriptions of embedded images (llava:13b). These are searchable across the corpus.
[Image 1] The image is a document scan, specifically a task list or project management document. It contains a table with columns labeled "Task," "Description," "Date," and "Status." The visible tasks include items such as "ZRR Ranch Projects," "ZRR Ranch Projects," and "ZRR Ranch Projects," with corresponding descriptions, dates, and statuses. The document appears to be related to project management or a t
[Image 2] The image shows a document titled "Zorro Ranch Projects / Tasks List." It appears to be a list of tasks or projects with associated dates, descriptions, and status indicators. The document includes columns for "Task ID," "Task Description," "Date Due," and "Status." There are several tasks listed, each with a unique identifier and a brief description. The status column indicates whether the task h
[Image 3] The image shows a document titled "Zorro Ranch Projects / Tasks List." It appears to be a list of tasks or projects with columns for "Task," "Date," and "Status." The tasks are listed in a table format, with some tasks marked as "Completed" and others as "In Progress." The document includes a date at the top, which is not fully visible, and there are names and other details that are not fully legi
[Image 4] The image shows a document titled "Zorro Ranch Projects / Tasks List." It appears to be a list of tasks or projects with associated dates and descriptions. The document includes a header with the title, a table with columns for "Task ID," "Task Description," "Start Date," "End Date," and "Status." There are several rows of text, each detailing a specific task or project, including dates and descri
[Image 5] The image shows a document titled "Zorro Ranch Projects / Tasks List." It appears to be a list of tasks or projects with columns for "Task," "Date," "Time," "Priority," "Status," and "Notes." The tasks are listed in a table format, with some tasks having notes or comments. The document includes dates and times, but no specific names or identifying details are visible. The content of the document s
[Image 6] The image shows a document titled "Zorro Ranch Projects / Tasks List." It appears to be a table or a list with columns for "SHORT TITLE," "DESCRIPTION," "DATE," and "NOTES." The document contains various entries with descriptions, dates, and notes, which seem to be related to project tasks or events. The visible text includes phrases such as "Zorro Ranch," "tasks," "projects," "date," and "notes,"