Zorro Projects - 6/8/13
Zorro Projects - 6/8/13
Landscaping (22) -
Rear Planter Bed
Front & Rear Parking Beds
Bowel Garden
Aspen Grove
Pinion Screen Start 6/1/13
Landscape Lighting Timers Replacement - Start
Landscaping - In House -
Ponderosa Pines & Landscape Lights at 6/3/13
Front Entrance
Terraces (27) -
Terraces - $52,000.00
Stucco/Gutters/Painting - $4,200.00 End Total Est. Cost
$75,000.00 Notes
3/28/13 - Refurbishment & Maintenance proposals from 3
companies forwarded to RK & DI
4/27/13 - JE approved Aspen landscaping for Refurbishment
5/9/13 - New proposal forwarded to JE & RK, awaiting direction
5/16/13 - Final proposal forwarded to RK, will discuss with JE
5/24/13 - Aspen agreed to $75,000
5/31/13 - $44,383.08 Deposit issued to Aspen
6/1/13 - Project Started
6/8/13 - Work continues, soil preparation in progress Photo X
End Total Est. Cost Notes
$5,000.00 4/27/13 -JE approved
5/1/13 - Unable to move forward until Project 22 - Landscaping
has been resolved
6/1/13 - Brice to review with Aspen about location etc.
6/7/13 - Awaiting electrical proposal from RMC Electric
Start End
Start I End
4/7/13 Photo
Total Est. Cost Notes
4/27/13 - JE approved the removal of dead pine in courtyard &
Ponderosa Pines, Landscape Lights & relocate Pinions to the area.
6/3/13 - Project Started
6/7/13 - Removal of Ponderosa Pines complete
6/12/13 - Removal of courtyard Pine scheduled Photo
Total Est. Cost Notes
$56,200.00 12/12/12 - Bid Received
3/20/13 - JE approved
4/7/13 - Project Started
4/20/13 - Library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
5/31/13 - There was a fault in one of the rolls of material, vendor
has reordered, will recover area once on site.
6/7/13 - Material on site, will continue 6/10/13 'Photo
EFTA01124632
Zorro Projects - 6/8/13
Front Gates Openers Call Boxes (30) - Start End Total Est. Cost Notes Photo
4/20/13 - Bid received, have requested vendor to make
adjustments 5/9/13 - Received revised bid. Options & Equipment reviewed
5/12/13 - Options & Equipment selected, final bid due 5/21/13
5/21/13 - Final bid received via fax, unable to read, vendor will I
resend. 6/8/13 - Final bid attached, also forwarded separately to RK.
direction Notes Photo
IAwaiting
Coolln: Tower - (36) ' Start End Total Est. Cost 4/24/13 - RK approved bid from SPX & JBH. RK has all cost details
5/3/13 - Deposit was to be forwarded, awaiting confirmation
6/25/13 - Unit due on site Photo
Notes
Replacement of Pool Pac (33) - Start End Total Est. Cost
Engineering Inspection - $9,100.00
Unit Cost - $43,170.00
Ducting - TBA I 9/11/12 , I 4/29/13 - Quote forwarded to RK, who requested more detail
5/8/13 - Revised quote forwarded to RK, awaiting direction
5/22/13 - Beaudin Ganze on site to review project
5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 - JE approved investigation via camera.
6/3/13 - JBH forwarded estimate, JE approved moving ahead
i6/11/13 -1BH due on site Photo
Repair Pool/spa (29) - Start End Total Est. Cost Notes
$12,600.00 5/9/13 - Vendor on site
5/16/13 - Bid breakdown forwarded to RK
JE requested work be completed in Sept
REQUIRE CONFIRMATION THAT BID IS ACCEPTED, SO VENDOR
CAN BE PLACED INTO SCHEDULE
EFTA01124633
Zorro Projects - 6/8/13
Water Sample of Tap Water - Start End Total Est. Cost Notes Photo
4/27/13 - JE requested water samples be taken.
This will be completed once water system is balanced
5/10/13 - Dakota RO is down, pressure issues
6/2/13 - All Wells up and running
6/11/13 - Water samples to be taken
Exterior Doors Main House - Start End Total Est. Cost Notes Photo
4/27/13 -JE requested that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once
Terraces etc. complete
Start End Total Est. Cost
Audio Upgrade - Notes Photo
New TV's
DVD Players/Theater Upgrade 6/3/13 Installed - final programming required
Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before moving
forward 5/24/13 - Receiver on site
6/3/13 - Work to begin
6/7/13 - Work 80% complete in Gym, Lodge & BH
Kitchen Table Electrical - (35) Start End Total Est. Cost Notes Photo
Electrical & Data Cut In - $2,160.00 6/3/13 3/1/13 - Bid received Lead lime 1 Week
6/3/13 - Project Started
6/7/13 - Under floor conduit due to be completed 6/12/13 X
End
Media Room Curtains (24)- Start Total Est. Cost Notes Photo
Blackout & Rings 2/24/13 $6,262.08 4/27/13 -JE selected fabric
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
EFTA01124634
Zorro Projects - 6/8/13
Sarah's Office Curtains (25) -
Lined & Rings Start End Total Est. Cost
2/24/13 Notes
4/27/13 - JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enough yardage
of selected fabric
5/9/13 - Another fabric option forwarded to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
$2,527.01 5/31/13 - AWAITING DIRECTION Photo
Gym - Mirrored Doors - Backed/Framed Start End Total Est. Cost Notes Photo
2/24/13 3 B's completed, JE requested further work
vendor , will review with
Phones Main House (31) Start End ' Total Eft. Cost Notes Photo
Microwave & IT- (21) - Start $34,295.00 14/27/13 - JE approved installation of new phones at MH
5/14/13 - Awaiting engineered solution for delivery of services
(phone/data) before proceeding firm bids end next week
End Total Est. Cost
Cell Repeaters & Wi-Fi
Cell Repeater - Library
Cell Repeater - Gym Notes
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE, RK & JR,
awaiting direction
5/16/13 - JE requested contacting Dava Baumann reference
delivery of service from Sandia Crest verses D Mark
5/17/13 - Dava Baumannhas forwarded details of RSM Craig
Franck. Brice has been in contact with Craig will forward details
5/24/13 - Received bid from Southwestern Wireless, have call set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to 1E, RK & JR
6/8/13 - Firm Bids due by 6/14/13
Attached TW Telcom Proposal for Delivery of Services
Start End Total Est. Cost Notes
Will have installed by 5/17/13
Will be completed with Audio install Photo Photo
EFTA01124635
Zorro Projects - 6/8/13
Corn • uters - Start End Total Est. Cost Notes Photo
Lap Top - Lodge I Requesting Approval to Purchase
Desk Top - RC Office Requesting Approval to Purchase
Well K (37) - Start End Total En. Cost Notes Photo
Plugging First Hole $15,000.00 Estimate to plug 1st hole
wig! Start End Total Est. Cost Notes Photo
Roof - Repair/Replace Broken Sections Three B's will complete while on site for upcoming projects
Log Cabin Start I End Total Est. Cost Notes Photo
Step Outside - Repair/Replace 2/24/13 NA
Caboose Start End Total Est. Cost Notes Photo
Outside Wall - Installation of Retaining Wal NA
Total Est. Cost Photo
Yurt - (23) - Start End Notes
Replacement Walls/Roof/Door/Windows 5/9/13 $6,355.00 plus shipping
charges of
approx. $480.00 4/27/13 -JE approved investigating options
5/9/13 - Project Request forwarded to RK & JE
5/9/13 - JE approved Project, awaiting direction on deposit
payment from RK
5/13/13 - Deposit forwarded to vendor $3,177.50
6/24/13 - Removal of furniture, deconstruction of existing
walls/roof/windows & door to begin. Then reconstruction of base,
resanding/sealing floor required - in house
7/3/13 - Scheduled Ship Date
Repair/Painting Work - ion Start End Total Est Cost Notes Photo
5/7/13 - E Mailed Photos to JE showing work required
5/23/13 - Forwarded all work details to Ion, including work that
will be required after MBR Terrace is completed Photo
Inventory/Clean up all Work Shops Start End Total Est. Cost Notes
6/6/13 Work continues as time allows complete clean up and Inventory x
on all Work Shops
EFTA01124636
Zorro Projects - 6/8/13
Painting/Staining/Sealing - Start End Total Est. Cost Notes Photo
Hay Barn 5/13/13 . 90%- Staining of trim to be completed
5/30/13 - Work to start, due to high winds & stormy weather
work to begin 6/10/13
Bunkhouse 4/14/13 80%- Staining of trim & deck to be completed
5/30/13 - Work to start, due to high winds & stormy weather
work to begin 6/10/13
Bay Garages 5/13/13-90% - Staining of trim to be completed
5/30/13 - Work to start, due to high winds & stormy weather
work to begin 6/10/13
Fire House - including outside lights 5/28/13 - Work to begin, due to high winds & stormy weather
work to begin 6/14/13
Stables 5/29/13 - Work to begin, due to high winds & stormy weather
work to begin 6/14/13
Log Cabin Work to begin once all painting/staining projects complete at RC
Lodge Work to begin once all painting/staining projects complete at RC
Reservoir Work be begin once all painting/staining/sealing projects complete
Bunkhouse Start End Total Est. Cost Notes
Window/Doors - Total Replacement 2/6/12 Will Budget for 2014
Cactus Removal Start End Total Ed. Cost Notes
Removal of Cactus to begin late Fall, early Winter
Vehicles Start End Total Est. Cost Notes
2013 Ford Expedition - review Captain
Seats to be installed 3/27/13 5/2/13 - Estimate received - $11,528.74
5/31/13 - as of date unable to get a 2nd estimate,
Start End Total Est. Cost Notes
4/27/13 - JE approved investigating purchase of 2 dogs.
Researching
EFTA01124637
Zorro Projects - 6/8/13
Purchases Start End Total Est. Cost
White Rug & Pad (26)- Gym (10 x 12) 5/16/13 $862.55 4/27/13 - JE approved Robert's to manufacture a rug using carpet
used inEMOffice. Vendor no longer stocks this brand, will add
10% for special order.
5/15/13 - 2 Estimates received
5/16/13 - Estimate forwarded to JE - Enchantment Carpet
5/16/13- Project approved
6/8/13 - Rug on site, will lay out and forward photos 6/10/13
Big Urns - Outside MH 4/27/13 - JE approved Terre Cotto constructed Urns
Outside Pool Furniture 6/12/13 - Will forward possible options
Pool Pace Clock 4/25/13 - Ordered, lead time 4 to 5 weeks
Large Chrome Pool Clock Investigating Options
Facial Machine to purchase
Wells - Dakota & K
Combined Usage as of date 6/8/13 5.58 afa
EFTA01124638
📷 Images in this document (7 detected; 6 largest described)
AI-generated factual descriptions of embedded images (llava:13b). These are searchable across the corpus.
[Image 1] The image shows a printed document with a table of information. The table has columns with headings such as "Date," "Time," "Name," "Title," "Amount," and "Check No." There are rows filled with text, indicating specific entries with dates, times, names, titles, amounts, and check numbers. The document appears to be a financial record or a list of transactions, possibly related to payments or expen
[Image 2] The image shows a document with a table that appears to be a financial or accounting spreadsheet. The table has columns with headings such as "Date," "Description," "Amount," and "Debit/Credit." There are rows with entries that seem to be related to financial transactions, with descriptions like "Rent," "Utilities," "Food," and "Groceries." The document is a scan, and the text is legible, but the
[Image 3] The image shows a document with a table of text. The table has several columns with headings such as "Date," "Time," "Name," "Title," "Location," and "Notes." There are rows of text under each heading, but the specific content of the text is not clear due to the resolution of the image. The document appears to be a form or a record of some sort, possibly related to an event or meeting, given the s
[Image 4] The image shows a document with a table that appears to be a schedule or a list of tasks or events. The table has columns with headings such as "Date," "Time," "Event," and "Notes." There are entries filled out in the table, indicating specific dates and times for various events or tasks. The document is a scan or a photograph of a printed document, and the text is legible. The style of the docume
[Image 5] The image shows a document with a table and text. The table has columns with headings such as "Date," "Time," "Name," "Title," "Amount," and "Description." There are rows filled with text, which appear to be entries for expenses or transactions, with details such as dates, times, names, titles, amounts, and descriptions. The document is a financial or accounting record, likely used for tracking ex
[Image 6] The image shows a document with a table that appears to be a list of items or tasks, possibly related to a project or inventory. The table has columns with headings such as "Item," "Description," "Quantity," "Unit," "Price," and "Total." There are rows filled with text, indicating specific items or tasks with corresponding details. The document is a scan or a photograph of a printed page, and ther