Zorro Projects - 6/15/13
Zorro Projects - 6/15/13
Landscaping (22) -
Rear Planter Bed
Front & Rear Parking Beds
Bowel Garden
Aspen Grove
Pinion Screen Start End Total Est. Cost
575,000.00 3/28/13 - Refurbishment & Maintenance proposals from 3
companies forwarded to RK & DI
4/27/13 - JE approved Aspen Landscaping for Refurbishment
5/9/13 - New proposal forwarded to JE & RK, awaiting direction
5/16/13 - Final proposal forwarded to RK, will discuss with JE
5/24/13 - Aspen agreed to $75,000
5/31/13 - $44,383.08 Deposit issued to Aspen
6/1/13 - Project Started
6/8/13 - Work continues, soil preparation in progress
6/14/13 - Plant material starting to arrive, more due next week -
!attached photos Notes
6/1/13
landscape Lighting Timers Replacement - Start
Landscaping - In House
-
Ponderosa Pines & Landscape Light:, at
Front Entrance End Total Est. Cost
$5,000.00 4/27/13 - JE approved
5/1/13 - Unable to move forward until Project 22 - Landscaping
has been resolved
6/1/13 - Brice to review with Aspen about location etc.
6/7/13 - Awaiting electrical proposal from RMC Electric
Notes
Start End Total Est. Cost
OS/1S Notes
4/27/13 - JE approved the removal of-dad pine in courtyard &
Ponderosa Pines, Landscape Lights & relocate Pinions to the area.
6/3/13 - Project Started
6/7/13 - Removal of Ponderosa Pines complete
6/18/13 - Removal of courtyard Pine scheduled Photo X
Photo Photo
EFTA01124639
Zorro Projects - 6/15/13
Terraces (27) - Start End Total En. Cost Notes Photo
Terraces - $52,000.00
Stucco/Gutters/Painting - $4,200.00 4/7/13 $56,200.00 12/12/12 - Bid Received
3/20/13 - JE approved
4/7/13 - Project Started
4/20/13 - Library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
i5/31/13 - There was a fault in one of the rolls of material, vendor
has reordered, will recover area once on site.
6/7/13 - Material on site, will continue 6/10/13
6/14/13 - Membranes & Gutters Complete - attached photos
6/18/13 - Stucco & Painting scheduled to start X
Photo
Front Gates Openers Call Boxes (30) - Start End Total Est. Cost Notes
4/20/13 - Bid received, requested vendor to make adjustments
5/9/13 - Received revised bid. Options & Equipment reviewed
5/12/13 - Options & Equipment selected, final bid due 5/21/13
5/21/13 - Final bid received via fax, unable to read, vendor will
resend. 6/8/13 - Final bid attached, also forwarded separately to RK.
6/11/13 - RK requested material breakdown
6/14/13 - Material breakdown forwarded to RK
Cooling Tower - (36) Start End Total Est. Cost Notes Photo
4/24/13 - RK approved bid from SPX & JBH. RK has all cost details
5/3/13 - Deposit was to be forwarded, awaiting confirmation
6/25/13 - Unit due on site
EFTA01124640
Zorro Projects - 6/15/13
Replacement of Pool Pac (33) - Start End Total Est. Cost Notes Photo
Engineering Inspection - $9,100.00
Unit Cost - $43,170.00
Camera Ducting Inspection - $1,214.91
Ducting - TBA 9/11/12 4/29/13 - Quote forwarded to RK, who requested more detail
5/8/13 - Revised quote forwarded to RK, awaiting direction
5/22/13 - Beaudin Ganze on site to review project
5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 - JE approved investigation via camera.
6/3/13 -JBH forwarded estimate
6/4/13 -JE approved moving ahead
6/11/13 - JBH due on site
6/12/13 - JBH on site, completed camera inspection, awaiting
report
Repair Pool/spa (29) - Start End Total Est. Cost Notes Photo
$12,600.00 5/9/13 - Vendor on site
5/16/13 - Bid breakdown forwarded to RK
IF requested work.be completed an Sept
REQUIRE CONFIRMATION THAT BID IS ACCEPTED, SO VENDOR
CAN BE PLACED INTO SCHEDULE
Water Sample of Tap Water - Start End Total Est. Cost Notes Photo
6/12/13 4/27/13 - JE requested water samples be taken.
ads will be completed once water system is balanced
5/10/13 - Dakota RO Is down, pressure issues
6/2/13 -All Wells up and running
6/12/13 - Water samples taken. Results due back 6/24/13
Exterior Doors Main House - Start End Total Est. Cost Notes Photo
4/27/13 - JE requested that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once
Terraces etc. complete
EFTA01124641
Zorro Projects - 6/15/13
Audio Upgrade - Start End Total Est. Cost Notes Photo
New N's 6/3/13 Installed - final programming required
DVD Players/Theater Upgrade Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before moving
forward 5/24/13 - Receiver on site
6/3/13 - Work to begin
6/7/13 - Work 80% complete in Gym, Breakfast Rm, Lodge & BH
6/12/13 - Gym, Lodge & BH Systems Complete
6/14/13 - Will exchange the Samsung DVD for a Marantz DVD in
Breakfast Rm
End Total Est. Cost Photo
Kitchen Table Electrical - (35) Start Notes
Electrical & Data Cut In - $2,160.00 6/3/13 6/13/13 3/1/13 - Bid received Lead Time 1 Week
6/3/13 - Project Started
6/7/13 - Under floor conduit due to be completed 6/12/13
. . .
6/13/13 - Conduit installed, tiles replaced & grouted. Cat 5 still to
be pulled and punched down
Start End Total Est. Cost Photo
Media Room Curtains (24) - Notes & RK
Blackout & Rings 2/24/13 4/27/13 - JE selected fabric
5/10/13 - Project Request forwarded to JE
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
$6,262.08
Sarah's Office Curtains (25) -
Lined & Rings Start End Total Est. Cost
2/24/13 $2,527.01 Notes
4/27/13 - JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enough yardage
of selected fabric
5/9/13 - Another fabric option forwarded to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION Photo
EFTA01124642
Zorro Projects - 6/15/13
Gym - Mirrored Doors - Backed/Framed Start End Total Est. Cost 1 Notes Photo
2/24/13 3/4/13 - Project Complete. JE requested further work, which will
begin once Project 27 - Terraces complete
Phones Main House (31) - Start End Total Est. Cost Notes Photo
4/27/13 - JE approved installation of new phones at MH
Awaiting for service provision & estimated cost of delivery of
services - Project 21 Microwave & IT
Microwave & IT - (21)- Start End Total Est. Cost Notes Photo
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE, RK & JR,
awaiting direction
5/16/13 - JE requested contacting Dava Baumann reference
delivery of service from Sandia Crest verses D Mark
5/17/13 - Dava Baumannhas forwarded detailsof RSM Craig
Franck. Brice has been in contact with Craig will forward details
5/24/13 - Received bid from Southwestern Wireless, have call set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to JE, RK & JR
6/8/13 - Forwarded TW Telecom Proposal for Delivery of Services
to JE & RK. Firm Bids due by 6/14/13
6/14/13 - Received bid from Southwestern Wireless, confirming
details before forwarding
6/15/13 - Informed JE, will forward once all details confirmed
Cell Repeaters & WI-Fl Start End Total Est. Cost Notes Photo
Cell Repeater - Library Will have installed 6/21/13
Cell Repeater - Gym Will have installed 6/21/13
Computers - Start End Total St. Cost Notes Photo
Lap Top - Lodge Requesting Approval to Purchase
Desk Top - RC Office Requesting Approval to Purchase
EFTA01124643
Zorro Projects - 6/15/13
Well K (37) - Start End Total Est. Cost Notes Photo Plugging First Hole $15,000.00 Estimate to plug 1st hole
Lodge Roof Start End Total Est. Cost Notes Photo Repair/Replace Broken Sections Three B's will complete while on site for upcoming projects
i
Tort - (23) - Start End ! Total Est. Cost Notes Photo Replacement Walls/Roof/Door/Windows 5/9/13 $6,355.00
plus shipping
charges of
approx.
$480.00
I
_
End Total Est. Cost 4/27/13 -JE approved Investigating options
5/9/13 - Project Request forwarded to RK & A
5/9/13 -JE approved Project, awaiting direction on deposit
payment from RK
5/13/13 - Deposit forwarded to vendor $3,177.50
6/24/13 - Removal of fumiture, deconstruction of existing
walls/roof/windows & door to begin. Then reconstruction of base,
resanding/sealing floor required - in house
7/3/13 - Scheduled Ship Date
Start Repair/Painting Work - ion Notes Photo
5/7/13 - E Mailed Photos to JE showing work required
5/23/13 - Forwarded all work details to Ion, including work that
will be required after MBR Terrace is completed
EFTA01124644
Zorro Projects - 6/15/13
Painting/Staining/Sealing - In House Start End Total Est. Cost Notes Photo Hay Barn 5/13/13 6/14/13 5/13/13 - Project Started
5/24/13 - 90% - Staining of trim to be completed
5/30/13 - Work to start, due to high winds & stormy weather
work to continue 6/10/13
6/14/13 - Project Complete - attached photo X
Bunkhouse 4/14/13 6/14/13 4/14/13 - Project Started
5/3/13 - 80% - Staining of trim & deck to be completed
5/30/13 - Work to start, due to high winds & stormy weather
work to continue 6/10/13
6/14/14 - Project Complete - attached photo X
Bay Garages - including outside lights 5/13/13 6/14/13 5/13/13 - Project Started
5/24/13 - 90% - Staining of trim to be completed
5/30/13 - Work to start, due to high winds & stormy weather
work to continue 6/10/13
6/14/13 - Project Complete - attached X
photo Fire House - including outside lights 5/13/13 6/14/13 5/13/13 - Project Started
5/24/13 - 80% complete
5/30/13 - Work to begin, due to high winds & stormy weather
work to continue 6/11/13
6/14/13 - Project Complete - attached photo X
Stables - including outside/Inside lights 5/29/13 - Work to begin, due to high winds & stormy weather
work to begin 6/17/13
Yellow House Garage 6/12/13 6/14/13 6/12/13 - Project Started
6/14/13 - Project Complete
Log Cabin Work to begin once all painting/staining projects complete at RC
Lodge Work to begin once all painting/staining projects complete at RC
Reservoir Work be begin once all painting/staining/sealing projects complete
Fuel Storage Tanks Work to begin once all painting/staining/sealing projects complete
EFTA01124645
Zorro Projects - 6/15/13
RC Office Interior Work scheduled for Winter
Fuel Storage Tank Area - In House Start End Total Est. Cost Notes Photo
Removal of grass. Matting & edging to be
installed Gravel/Edge Work RC Paths - In House Start End Total Est. Cost Notes Photo
All paths to be dug out, edged and gravel
to be installed
Log Cabin - In House Start End Total Est. Cost Notes Photo
Step Outside - Repair/Replace Broken
Section Caboose - In House Start End Total Est. Cost Notes Photo
Installation of Retaining Wall
4 Bay Garages - In House StS End Total Est. Cost Notes Photo
Repair Leaking Roof
Repair Damaged Wall Start End Total Est. Cost
Pole Barn Water Truck Parking Notes Photo
Installation of a Retaining Wall To begin late Fall, Early winter
Start End
Cactus Removal - In House Total Est. Cost Notes Photo
Removal of Cactus to begin late Fall, early Winter
r
Vehicles Start I End Total Est. Cost Notes Photo
2013 Ford Expedition - review Captain
Seats to be Installed3/27/13 / 5/2/13 - Estimate received - $11,528.74
5/31/13 - as of date unable to get a 2nd estimate,
I End t Total Est. Cost]
Dogs Start Notes Photo
4/27/13 - JE approved Investigating purchase of 2 dogs.
Researching
EFTA01124646
Zorro Projects - 6/15/13
Inventory/dean Work Shops - In House Start End Total Est. Cost Notes Photo
6/6/13 Work continues as time allows - complete clean up & Inventory of
all work shops at RC & MH
Purchases Start End Total Est. Cost Notes Photo White Rug & Pad (26) - Gym (10 x 12) 5/16/13 6/14/13
$862.55 4/27/13 -JE Robert's to manufacture a rug using carpet
used in M Office. Vendor no longer stocks this brand, will add
10% for spedal order.
5/15/13 - 2 Estimates received
5/16/13 - Estimate forwarded to JE - Enchantment Carpet
5/16/13 - Project approved
6/8/13 - Rug on site
6/14/13 - Project Complete - attached photo X
Big Urns-Outside MH 4/27/13 -JE approved Terre Cotto constructed Urns Outside Pool Furniture 6/22/13 - Will forward possible options Pool Pace Clock 4/25/13 - Ordered, lead time 4 to 5 weeks Large Chrome Pool Clock Investigating Options
Facial Machine to purchase
Wells- Dakota & K
Combined Usage as of date 6/14/13 6.33 afa
2014 Budget
Bunkhouse Start End Total Est. Cost Notes Photo Window/Doors - Total Replacement
EFTA01124647
📷 Images in this document (9 detected; 6 largest described)
AI-generated factual descriptions of embedded images (llava:13b). These are searchable across the corpus.
[Image 1] The image shows a document with a table that appears to be a form or a checklist. The table has several columns with headings such as "Date," "Time," "Name," "Title," "Status," and "Comments." There are rows filled out with various details, including names, titles, statuses, and comments. The document is a scan or a photograph of a printed form, and the text is legible. The visible names, dates, a
[Image 2] The image shows a table with various columns and rows of text. The text appears to be a list of items or tasks, with each row containing a description followed by a numerical value. The numerical values are likely to represent quantities or scores. The text is too small to read in detail, but it seems to be a structured document, possibly a spreadsheet or a table from a report or a survey. There a
[Image 3] The image shows a document with a table that appears to be a form or a list with various columns and rows. The visible columns include "Date," "Time," "Name," "Title," "Status," and "Comments." There are entries filled out in the form, with names, titles, and statuses such as "Completed," "In Progress," and "Not Started." The document is a scan, and the text is legible, but the image is rotated, m
[Image 4] The image shows a document with a table that appears to be a survey or questionnaire. The table has rows with headings such as "Question," "Answer," and "Score," indicating that it is a form for collecting responses to a series of questions. The questions are not fully visible, but they seem to be related to some sort of evaluation or assessment. The document is a scan or photograph of a physical
[Image 5] The image shows a document with a table of figures. The table appears to be a financial statement or report, with columns for figures such as "Amount," "Date," and "Description." There are numerical values listed under each column, indicating financial transactions or figures for a specific period. The document is a scan, and the text is not entirely clear due to the resolution and angle of the sc
[Image 6] The image shows a document with a table that appears to be a form or a checklist. The table has several columns with headings such as "Date," "Time," "Task," "Status," and "Notes." There are rows filled out with various tasks, dates, and statuses, indicating that this is a record of tasks completed or to be completed. The document is a scan, and the text is not entirely clear due to the resolution