Transportation System Plan 2018-2038
Medford · Page 346 of 398 · Adopted 2018-12-06
Planned Non-Vehicular Improvements
Planned bicycle and pedestrian im provem ents as shown in the RTP are listed in Table F-5. As with the
planned roadway improvem ents, Table F-5 separat es non-vehicular planned im provem ents into short-
range, m edium -range and long-range co rresponding to the sam e tim efram e as in Tables F-2, F-3 and F-4.
Over $7 m illion in im provem ents are planned over the com ing 20 y ears. Planned and program med
bicycle facility improvem ents are depicted in Figure F-1.
Table F-5
Planned Bicycle/Pedestrian Improvements
Medford UGB
Funding Agency
Project Location Project Description Medford Other Project Cost
Medford Tier 1 – Short-Range (2001-2005)
Miscellaneous locations City-wide sidew alk improvements $1,000,000
Black O ak, Hillcr est to Acor n Widen to tw o lanes w ith curb, gutter and
sidew alks $325,000
Hillcr est Rd, Valley View Dr to
Black O ak Rd Add sidew alks and re-stripe w ith bike
lanes $165,000
Medford Short Ra nge Cos ts - $1,490,000
Jackson County Tier 1 – Short-Range (2001-2005)
Oak Grove Rd, Stew art Ave to
Medford UGB Limits Widen to rural tw o-lane cross-section w ith
shoulder bikew ay $250,000
Jackson County Short Range Costs - $250,000
Medford Tier 1 – Medium -Range (2006-2010)
Garfield, Columbus to Keny on Widen to provide curb, gutter, bike lanes
and sidew alks $1,000,000
Sunset, South Stage Rd to
Orchard Home Dr Widen to provide curb, gutter, bike lanes
and sidew alks $780,000
Pierce Rd, Hillcr est Rd to Spr ing Widen to provide curb, gutter, bike lanes
and sidew alks $650,000
Diamond, Peach to Kings Hw y Widen to provide curb, gutter, bike lanes
and sidew alks $520,000
Highland, Keene Way to Main St Widen to provide curb, gutter, bike lanes
and sidew alks $390,000
12th St, Central Ave (Hw y 99) to
Cottage Widen to provide curb, gutter, bike lanes
and sidew alks $390,000
Barneburg Rd, Keene Drive to
Main St Widen to provide curb, gutter, bike lanes
and sidew alks $390,000
Edwards, Niantic to Riverside Widen to provide curb, gutter, bike lanes
and sidew alks $130,000
Hillcrest Rd, Phoenix to Highcrest Add sidew alks $120,000
Cottage, 12th St to Main Remove parking, re-stripe w ith bike lanes $5,000
Medford Me dium Ra nge Cos ts - $4,372,000
Medford Tier 1 – Long-Range (2011-2023)
Coker Butte Rd, Crater Lake Hw y
to Foothill Realign and w iden to rural tw o-lane w ith
shoulder bikew ay $1,500,000
Medford Long Ra nge Cos ts - $1,500,000