American Yacht Harbor
American Yacht Harbor
Facility Condition Status Report
September 2015
Addressing specific issues raised July 2015
-- I GY MARINAS
EFTA01084560
Hurricane Shutters - Completed
Original pictures of the hurricane
shutters outside upper level office Pictures of same, repaired and painted
in July/August 2015
,„--
EFTA01084561
Wall Paint - Completed
Original Pictures of exterior walls
around upper level office
6MINIIMMIONO -01,001°6.Pictures of same, repaired and painted
in July/August 2015
EFTA01084562
Dock beam repairs - Completed
Original picture of dock area near slip Picture of same repaired September
B-26 2015
EFTA01084563
Main Flag - Completed
Original picture of flag with tattered
edge Picture of same, replaced July 2015
EFTA01084564
Parking deck walls - Completed
Original pictures of lower parking deck Pictures of same, repaired and painted
walls July/August 2015
EFTA01084565
Parking Deck Columns - Completed
Original picture of column needing
paint
GARAGE PARKING
BEFORE 9AM WITi.
CURRENT PASS ON
LC)ITERIN
OLICITIK 9 Picture of same painted July 2015 — other
columns were painted as needed.
GARAGE PARKING
BEFORE 9AM WITH
CURRENT PASS ONLY
EFTA01084566
Dock planking — In-Progress
Original pictures (4 samples of many)
of various dock planking trouble spots Sample pictures of recent and in-progress
dock repairs — September 2015
EFTA01084567
Security Fencing — In Progress
Original pictures showing fence
transition Picture of same. As vegetation in this area
regrows, the fencing choice is more
understandable.
EFTA01084568
Piling wrap — In Progress
Original picture of pile with failing
wood wrap Sample of a pile with completed wood
wrap. A project is underway to replace
failed wrapping on 24 concrete piles.
Expected completion in October 2015
EFTA01084569
Support columns — In Progress
Original pictures of support column
bases lifted off brick deck Action Plan:
• Bases will be split open, lowered, and
reinstalled to be flush with brick deck
• Contractor quoted price approx. $75 per
columns
• 133 columns on B & C (Main) Building, for
total price of about $10,000
• Contractor is currently lowering 5 bases to
test feasibility
• If solution is workable, we will move forward
strategically to address most visible columns
first, and continue until aesthetics are
satisfactory
EFTA01084570
Parking Deck Ceiling — In Progress
Original pictures of damaged drop
ceiling in the lower parking deck Action Plan:
• Materials are on order to begin replacement
of damaged ceiling tiles, support structure
and light fixtures.
• Drop ceiling near parking deck entrance is
being cut back to be flush and neat with
entranceway (areas shown in bottom to
picture on the left)
• The above efforts will lift aesthetics to
acceptable levels while we plan long term
solution
• Long term replacement or refurbishment
options are being explored and quoted for
completion in 2016
EFTA01084571
Elevator — In Progress
Original pictures of scraped paint on
the elevator doors Action Plan:
• Doors have been repainted, but elevator use
for freight will continually scrape paint
• Elevator doors and trim areas are being fitted
with stainless steel rub rails/guards to protect
paint while remaining aesthetical ly pleasing
• Interior of elevator cab is also being
refurbished, including polishing of stainless
steel, new paint and new flooring.
• Completion expected in Q4 2015
EFTA01084572
Brick Pavers — In Progress
Original pictures of various areas of the
brick paver deck needing attention Action Plan:
• Brick paint is being color custom color
matched to better blend repair areas with
original brick.
• Patch and replacement bricks are installed
where need.
• Long term resurfacing or repainting option
are being explored by local contractors. Two
primary options are 1) Coating with a heavy
duty masonry paint or 2) removal and
replacement of entire system of brick pavers
• Either option above will be a significant
undertaking, expected to start and complete
project in 2016
EFTA01084573
Stairways — In Progress
Original pictures of stairways Action Plan:
• Local structural engineer Paul Ferreras, PE has
inspected the property's stairways and written a
letter recommending refurbishment over
replacement
• Two local welding contractors are producing job
quotes to address all structural steel issues with
stairways
• Concrete stair treads will be painted to match
paver bricks on surrounding decks
• Steel will be repainted black after above repairs
are complete
• All repairs expected to be completed in Q4 2015
EFTA01084574
P Dock — In Progress
Original pictures of areas around
P-Dock Action plan:
• P-Dock is owned by 3rd party and slips are
managed by AYH
• Dock owner is refurbishing entire dock
structure and utilities starting October 2015
• AYH/IGY management team working with P-
Dock owner to ensure rebuilt dock meets
safety and aesthetics standard.
• Expected completion January 2016.
EFTA01084575
📷 Images in this document (16 detected; 6 largest described)
AI-generated factual descriptions of embedded images (llava:13b). These are searchable across the corpus.
[Image 1] The image is a collage of photographs showing the progress of a dock planking project. The top left photo shows the original condition of the dock with visible damage. The top right photo shows the dock after the planking process has been completed. The bottom left photo shows the dock in the middle of the planking process, with some planks already installed. The bottom right photo shows the dock
[Image 2] The image shows a before-and-after comparison of a security fence installation. On the left, there is a photograph of a fence with vegetation growing through it, indicating that the fence is not fully effective in preventing plant growth. On the right, there is a photograph of the same area after the installation of a new security fence, which is now fully enclosed and free of vegetation, demonstr
[Image 3] The image shows a series of photographs depicting a building's exterior after a hurricane. The top photo shows the building's facade with visible damage, including missing siding and a boarded-up window. The subsequent photos show the progress of repairs, with the bottom photo showing the completed repair work, including the installation of new siding and the repair of the window. There are no vis
[Image 4] The image shows a before-and-after comparison of a dock repair. On the left, there is a photograph labeled "Original picture of dock area near slip" showing a wooden dock with visible damage and water damage. On the right, there is a photograph labeled "Picture of same repaired dock area September 2021" showing the same dock area after repairs, with the dock appearing to be in good condition and f
[Image 5] The image is a collage of four photographs showing a wall paint project. The top left photo shows a wall with a visible crack and a patch of missing paint. The top right photo shows the same wall after it has been repaired and painted. The bottom left photo shows the wall with a fresh coat of paint. The bottom right photo shows the wall with a new coat of paint and a visible improvement in its con
[Image 6] The image is a collage of photographs showing the process of painting parking deck walls. The top photo shows the walls before painting, the middle photo shows the walls during the painting process, and the bottom photo shows the completed painted walls. The photos are taken from the same angle and show the same area of the parking deck walls. There are no visible texts, logos, or people in the im