American Yacht Harbor

EFTA01084560 Dataset 9 16 pages Download original PDF Download as text
American Yacht Harbor Facility Condition Status Report September 2015 Addressing specific issues raised July 2015 -- I GY MARINAS EFTA01084560 Hurricane Shutters - Completed Original pictures of the hurricane shutters outside upper level office Pictures of same, repaired and painted in July/August 2015 ,„-- EFTA01084561 Wall Paint - Completed Original Pictures of exterior walls around upper level office 6MINIIMMIONO -01,001°6.Pictures of same, repaired and painted in July/August 2015 EFTA01084562 Dock beam repairs - Completed Original picture of dock area near slip Picture of same repaired September B-26 2015 EFTA01084563 Main Flag - Completed Original picture of flag with tattered edge Picture of same, replaced July 2015 EFTA01084564 Parking deck walls - Completed Original pictures of lower parking deck Pictures of same, repaired and painted walls July/August 2015 EFTA01084565 Parking Deck Columns - Completed Original picture of column needing paint GARAGE PARKING BEFORE 9AM WITi. CURRENT PASS ON LC)ITERIN OLICITIK 9 Picture of same painted July 2015 — other columns were painted as needed. GARAGE PARKING BEFORE 9AM WITH CURRENT PASS ONLY EFTA01084566 Dock planking — In-Progress Original pictures (4 samples of many) of various dock planking trouble spots Sample pictures of recent and in-progress dock repairs — September 2015 EFTA01084567 Security Fencing — In Progress Original pictures showing fence transition Picture of same. As vegetation in this area regrows, the fencing choice is more understandable. EFTA01084568 Piling wrap — In Progress Original picture of pile with failing wood wrap Sample of a pile with completed wood wrap. A project is underway to replace failed wrapping on 24 concrete piles. Expected completion in October 2015 EFTA01084569 Support columns — In Progress Original pictures of support column bases lifted off brick deck Action Plan: • Bases will be split open, lowered, and reinstalled to be flush with brick deck • Contractor quoted price approx. $75 per columns • 133 columns on B & C (Main) Building, for total price of about $10,000 • Contractor is currently lowering 5 bases to test feasibility • If solution is workable, we will move forward strategically to address most visible columns first, and continue until aesthetics are satisfactory EFTA01084570 Parking Deck Ceiling — In Progress Original pictures of damaged drop ceiling in the lower parking deck Action Plan: • Materials are on order to begin replacement of damaged ceiling tiles, support structure and light fixtures. • Drop ceiling near parking deck entrance is being cut back to be flush and neat with entranceway (areas shown in bottom to picture on the left) • The above efforts will lift aesthetics to acceptable levels while we plan long term solution • Long term replacement or refurbishment options are being explored and quoted for completion in 2016 EFTA01084571 Elevator — In Progress Original pictures of scraped paint on the elevator doors Action Plan: • Doors have been repainted, but elevator use for freight will continually scrape paint • Elevator doors and trim areas are being fitted with stainless steel rub rails/guards to protect paint while remaining aesthetical ly pleasing • Interior of elevator cab is also being refurbished, including polishing of stainless steel, new paint and new flooring. • Completion expected in Q4 2015 EFTA01084572 Brick Pavers — In Progress Original pictures of various areas of the brick paver deck needing attention Action Plan: • Brick paint is being color custom color matched to better blend repair areas with original brick. • Patch and replacement bricks are installed where need. • Long term resurfacing or repainting option are being explored by local contractors. Two primary options are 1) Coating with a heavy duty masonry paint or 2) removal and replacement of entire system of brick pavers • Either option above will be a significant undertaking, expected to start and complete project in 2016 EFTA01084573 Stairways — In Progress Original pictures of stairways Action Plan: • Local structural engineer Paul Ferreras, PE has inspected the property's stairways and written a letter recommending refurbishment over replacement • Two local welding contractors are producing job quotes to address all structural steel issues with stairways • Concrete stair treads will be painted to match paver bricks on surrounding decks • Steel will be repainted black after above repairs are complete • All repairs expected to be completed in Q4 2015 EFTA01084574 P Dock — In Progress Original pictures of areas around P-Dock Action plan: • P-Dock is owned by 3rd party and slips are managed by AYH • Dock owner is refurbishing entire dock structure and utilities starting October 2015 • AYH/IGY management team working with P- Dock owner to ensure rebuilt dock meets safety and aesthetics standard. • Expected completion January 2016. EFTA01084575

📷 Images in this document (16 detected; 6 largest described)

AI-generated factual descriptions of embedded images (llava:13b). These are searchable across the corpus.

[Image 1] The image is a collage of photographs showing the progress of a dock planking project. The top left photo shows the original condition of the dock with visible damage. The top right photo shows the dock after the planking process has been completed. The bottom left photo shows the dock in the middle of the planking process, with some planks already installed. The bottom right photo shows the dock [Image 2] The image shows a before-and-after comparison of a security fence installation. On the left, there is a photograph of a fence with vegetation growing through it, indicating that the fence is not fully effective in preventing plant growth. On the right, there is a photograph of the same area after the installation of a new security fence, which is now fully enclosed and free of vegetation, demonstr [Image 3] The image shows a series of photographs depicting a building's exterior after a hurricane. The top photo shows the building's facade with visible damage, including missing siding and a boarded-up window. The subsequent photos show the progress of repairs, with the bottom photo showing the completed repair work, including the installation of new siding and the repair of the window. There are no vis [Image 4] The image shows a before-and-after comparison of a dock repair. On the left, there is a photograph labeled "Original picture of dock area near slip" showing a wooden dock with visible damage and water damage. On the right, there is a photograph labeled "Picture of same repaired dock area September 2021" showing the same dock area after repairs, with the dock appearing to be in good condition and f [Image 5] The image is a collage of four photographs showing a wall paint project. The top left photo shows a wall with a visible crack and a patch of missing paint. The top right photo shows the same wall after it has been repaired and painted. The bottom left photo shows the wall with a fresh coat of paint. The bottom right photo shows the wall with a new coat of paint and a visible improvement in its con [Image 6] The image is a collage of photographs showing the process of painting parking deck walls. The top photo shows the walls before painting, the middle photo shows the walls during the painting process, and the bottom photo shows the completed painted walls. The photos are taken from the same angle and show the same area of the parking deck walls. There are no visible texts, logos, or people in the im