Zorro Projects - 5/31/13
Zorro Projects - 5/31/13
Landscaping (22) - Start End Total Est. Cost Notes Photo Rear Planter Bed
Front & Rear Parking Beds
Bowel Garden
Aspen Grove
Pinion Screen
Landscape Lighting Timers Replacement - 6/1/13
Start $75,000.00 3/28/13 - Refurbishment & Maintenance proposals from 3
companies forwarded to RK & DI
4/27/13 - JE approved Aspen Landscaping for Refurbishment
5/9/13 - New proposal forwarded to JE & RK, awaiting direction
5/16/13 - Final proposal forwarded to RK, will discuss with JE
5/24/13 - Aspen agreed to $75,000
'5/31/13 - $44,383.08 Deposit issued to Aspen
Photo End Total Est. Cost Notes
$5,000.00 4/27/13 - JE approved
5/1/13 - Unable to move forward until Project 22 - Landscaping
has been resolved
6/1/13 - Brice to review with Aspen about location etc.
Landscaping - In House -
Ponderosa Pines & Landscape Lights at
Front Entrance Start End Total Est. Cost Notes
4/27/13 - JE approved the removal of existing Ponderosa Pines,
'Landscape Lights & to relocate Pinions to the area.
Removal of Dead Pine in Front Courtyard.
REQUIRE APPROVAL TO PROCEED WITH REMOVAL Photo
Terraces (27) - Start End Total Est. Cost Notes Photo Terraces - $52,000.00
Stucco/Gutters/Painting - $4,200.00 4/7/13 $56,200.00 12/12/12 - Bid Received
3/20/13 - JE approved
4/20/13 - Library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
5/31/13 - There was a fault in one of the rolls of material, vendor
has reordered, will recover area once on site.
6/3/13 - Start gutter & stucco work
6/10/13 - Project completion expected
EFTA01124605
Zorro Projects - 5/31/13
Front Gates Openers Call Boxes (30) - Start End Total Est. Cost Notes
4/20/13 - Bid received, have requested vendor to make
adjustments
5/9/13 - Received revised bid. Options & Equipment reviewed
5/12/13 - Options & Equipment selected, final bid due 5/21/13
5/21/13 - Final bid received via fax, unable to read, vendor will
resend.
Cooling Tower - 6/1/13 - Final bid expected
Start End Total Est. Cost Notes
4/24/13 - RK approved bid from SPX & JBH. RK has all cost details
5/3/13 - Deposit was to be forwarded, awaiting confirmation
6/17/13 - Due to ship to ZDC
Replacement of Pool Pae (33) -
Engineering Inspection - $9,100.00
Unit Cost - $43,170.00
Ducting - TBA
Repair Pool/Spa (29) -
Water Sample of Tap Water - Start End Total Est. Cost
9/11/12 Notes
4/29/13 - Quote forwarded to RK, who requested more detail
5/8/13 - Revised quote forwarded to RK, awaiting direction
5/22/13 - Beaudin Ganze on site to review project
5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 - JE approved investigation via camera. JBH have been
approached for estimate
Start End Total Est. Cost Notes
$12,600.00 15/9/13 - Vendor on site
5/16/13 - Bid breakdown forwarded to RK
JE requested work be completed in Sept
REQUIRE CONFIRMATION THAT BID IS ACCEPTED, SO VENDOR
CAN BE PLACED INTO SCHEDULE
Start End Total Est. Cost Notes
4/27/13 - JE requested water samples be taken.
will be completed once water system is balanced
5/10/13 - Dakota RO is down, pressure issues
6/5/13 - Water samples to be taken This Photo
Photo
Photo
Photo
Photo
EFTA01124606
Zorro Projects - 5/31/13
Exterior Doors Main House - Start End Total Est. Cost , Notes Photo
Total Est. Cost 4/27/13 - JE requested that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once il
.Terraces etc. complete
Audio Upgrade - Start End Notes Photo New N's
DVD Players/Theater Upgrade Installed - final programming required
Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before moving
forward
5/24/13 - Receiver on site
- Work to begin _16/3/13
I Kitchen Table Electrical - Start End Total Est. Cost Notes Photo Electrical & Data Cut In - $2,160.00 3/1/13 - Bid received Lead Time 1 Week
Need to review design and floor
End Media Room Curtains (24) - Start Total Est. Cost Notes Photo Blackout & Rings 2/24/13
$6,262.08 4/27/13 - JE selected fabric
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Sarah's Office Curtains (25) - Start End Total Est. Cost Notes Photo Lined & Rings 2/24/13
$2,527.01 4/27/13 - JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enough yardage
of selected fabric
5/9/13 - Another fabric option forwarded to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Gym - Mirrored Doors - Backed/Framed Start End Total Est. Cost Notes Photo
2/24/13 3 B's completed, JE requested further work, will review with
vendor
EFTA01124607
Zorro Projects - 5/31/13
Phones Main House (31) - Start End Total Est. Cost Notes Photo
534,295.00 4/27/13 -JE approved installation of new phones at MH
5/14/13 - Awaiting engineered solution for delivery of services
(phone/data) before proceeding
Start End Microwave & IT- (21)- Total Est. Cost Notes Photo
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE, RK & JR,
awaiting direction
5/16/13 -JE requested contacting Dava Baumann reference
delivery of service from Sandia Crest verses D Mark
5/17/13 - Dava Baumannhas forwarded details of RSM Craig
Franck. Brice has been in contact with Craig will forward details
5/24/13 - Received bid from Southwestern Wireless, have call set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to JE, RK & JR
Cell Repeaters & Wi-Fl Start End Total Est. Cost Notes Photo
Cell Repeater - Library Will have installed by 5/17/13
Cell Repeater - Gym Will be completed with Audio install
Computers,- Start End Total Est. Cost Notes Photo
Lap Top - Lodge Requesting Approval to Purchase
Desk Top - RC Office Requesting Approval to Purchase
Well K (20) - Start End Total Est. Cost Notes Photo
Plugging First Hole
Multi Media Filters & Install
Mis Pipe & Fittings 4/27/13 5/31/13 $15,000.00
$5,844.57
$822.20 4/27/13 -JE approved
5/3/13 - Multi Media Filters ordered
5/17/17 - Pipe & Fitting due on site
5/28/13 - Multi Media Fitters to installed
5/31/13 - Project Complete
EFTA01124608
Zorro Projects - 5/31/13
Dakota RO Water Softener Start End Total Est. Cost Notes Photo 2/18/13 5/31/13 $3,045.45 5/3/13 - Well & RO on line
5/10/13 - Dakota RO off Line, pressure issues - recalibration due
5/20/13 - Water Softener Installed
5/24/13 - Clock on Water Softener, needs to be replaced. Dakota
on line but requires manual operation, requiring 2 hours.
5/28/13 - Clock replaced
5/31/13 - Project Complete
Lo_til Start End Total Est. Cost Notes
Roof - Repair/Replace Broken Sections
Start Three 8% will complete while on site for upcoming projects
Log Cabin End Total Est. Cost Notes Photo Step Outside - Repair/Replace 2/24/13
Start NA
End Caboose Total Est. Cost Photo Outside Wall - Installation of Retaining Wall
End NA
Yurt (23) - Start Total Est. Cost Notes Photo Replacement Walls/Roof/Door/Windows 5/9/13 $6,355.00
plus shipping
charges of
approx.
$480.00 4/27/13 - JE approved Investigating options
5/9/13 - Project Request forwarded to RK & JE
5/9/13 - JE approved Project, awaiting direction on deposit
payment from RK
5/13/13 - Deposit forwarded to vendor $3,177.50
6/24/13 - Removal of furniture, deconstruction of existing
walls/roof/windows & door to begin. Then reconstruction of base, j
resanding/sealing floor required - in house
7/3/13 - Scheduled Ship Date
End Refurbishment Yards/Grass Areas RC (32) Start Total Est. Cost Notes Photo Due to poor preparation & selection of soil
In 2012 all yards/grass areas need to be
refurbished 5/16/13 5/31/13 5/16/13 - Tilling & Manure/Soil installation started in Red &
Yellow yards
5/24/13 - Seed on site, work continues
5/30/13 - All seed installed, irrigation installation complete
5/31/13 - Project Complete
EFTA01124609
Zorro Projects - 5/31/13
Painting/Staining/sealing - Start EndTotal Est. Cost Notes Photo
Hay Barn 5/13/13 90%- Staining of trim to be completed
5/30/13 - Work to start, due to high winds work to begin 6/10/13
Bunkhouse 4/14/13 80% - Staining of trim & deck to be completed
5/30/13 - Work to start, due to high winds work to begin 6/10/13
Bay Garages 5/13/13 90% - Staining of trim to be completed
5/30/13 - Work to start, due to high winds work to begin 6/10/13
Fire House - including outside lights 5/28/13 - Work to begin, due to high winds work to begin 6/6/13
Stables 5/29/13 - Work to begin, due to high winds work to begin 6/6/13
Log Cabin Work to begin once all painting/staining projects complete at RC
Lodge Work to begin once all painting/staining projects complete at RC
Reservoir Work be begin once all painting/staining/sealing projects complete
Repair/Painting Work - Ion (34)- Start End Total Est. Cost Notes
Start 5/17/13 - E Mail/Photos forwarded to JE showing work
5/23/13 - Forwarded details to Ion, including work that will be
required after Master Terrace ceiling is repaired
Bunkhouse End Total Est. Cost Notes
Window/Doors - Total Replacement 2/6/121— Will Budget for 2014
End Cactus Removal Start Total Est. Cost Notes
Removal of Cactus to begin late Fall, early Winter
End Total Est. Cost Vehicles Start Notes
2013 Ford Expedition - review Captain
Seats to be installed 3/27/13 5/2/13 - Estimate received - $11,528.74
5/31/13 - as of date unable to get a 2nd estimate,
EFTA01124610
Zorro Projects - 5/31/13
Start End Total Est. Cost Notes
14/27/13 -JE approved investigating purchase of 2 dogs.
Researching
Purchases White Rug & Pad (26) - Gym (10 x 12) Start End
4/27/13 Total Est. Cost 4/27/13 - JE approved Robert's to manufacture a rug using carpet
used in IM Office. Vendor no longer stocks this brand, will add
10% for special order.
5/15/13 - 2 Estimates received
5/16/13 - Estimate forwarded to JE - Enchantment Carpet
5/16/13 - Project approved
$862.55 6/5/13 - Rug due on site
Big Urns - Outside MH
Outside Pool Furniture
Pool Pace Clock
Large Chrome Pool Clock
Facial Machine 4/27/13 -JE approved Terre Cotto constructed Urns
6/5/13 - Will forward possible options
4/25/13 - Ordered, lead time 4 to 5 weeks
Invest' ati Options to purchase
EFTA01124611
📷 Images in this document (7 detected; 6 largest described)
AI-generated factual descriptions of embedded images (llava:13b). These are searchable across the corpus.
[Image 1] The image shows a document with a table of information. The table has several columns with headings such as "Date," "Time," "Name," "Title," "Status," and "Comments." There are rows filled with text, which likely contains details about events, meetings, or tasks. The text is too small to read clearly, and the document appears to be a form or a report of some sort. The document is scanned and has a
[Image 2] The image appears to be a scanned document, possibly a financial statement or a report, with a table of figures and text. The visible text includes numbers and possibly some descriptions or headings, but the specific content is not clear due to the resolution and angle of the scan. The document is structured with columns and rows, typical of a spreadsheet or a financial report.
[Image 3] The image shows a document with a table of text. The table has columns with headings such as "Date," "Time," "Name," "Title," "Location," and "Notes." There are rows of text under each heading, indicating a schedule or list of events or tasks. The text is too small to read in detail, but it appears to be a list of items or activities with associated dates and times. The document is a scan or a pho
[Image 4] The image shows a document with a table of information. The table has columns with headings such as "Date," "Time," "Name," "Title," "Type," "Amount," and "Comments." There are entries filled out in the table, including dates, times, names, titles, types, amounts, and comments. The document appears to be a financial or transactional record, possibly a receipt or an invoice. The text is too small t
[Image 5] The image shows a document with a table of information. The table has several columns with headings such as "Date," "Time," "Activity," "Status," and "Notes." There are rows filled with text, indicating tasks or events with dates and times, activities, statuses, and notes. The document appears to be a schedule or a log of some sort, possibly related to work or project management. The text is too s
[Image 6] The image shows a document that appears to be a project status report or a project summary. It includes a table with columns such as "Project Name," "Start Date," "End Date," "Total Hours," "Total Cost," and "Status." There are entries in the table with dates ranging from 5/1/2013 to 12/31/2013, and various project names are listed along with the corresponding figures for hours and costs. The docu