NASA Technical Reports Server (NTRS) 19790014263: CTS-type variable conductance heat pipes for SEP FM/PPU

Survival, Water, Medical Field Manuals

Military Manuals

Nasa Technical Reports Server (Ntrs)

Document text

General Disclaimer 


One or more of the Following Statements may affect this Document 


• This document has been reproduced from the best copy furnished by the 
organizational source. It is being released in the interest of making available as 
much information as possible. 


• This document may contain data, which exceeds the sheet parameters. It was 
furnished in this condition by the organizational source and is the best copy 
available. 


• This document may contain tone-on-tone or color graphs, charts and/or pictures, 
which have been reproduced in black and white. 


• This document is paginated as submitted by the original source. 


• Portions of this document are not fully legible due to the historical nature of some 
of the material. However, it is the best reproduction available from the original 
submission. 


Produced by the NASA Center for Aerospace Information (CASI) 



TRW 30979-6003-RU-0C 


NASA CR 159550 


CTS-TYPE 

VARIABLE CONDUCTANCE 
HEAT PIPES FOR SEP FM/PPU 

CONTRACT NAS 3-21130 

FINAL REPORT 


DECEMBER, 1978 

Prepared for v 

NASA LEWIS RESEARCH CENTER 
CLEVELAND, OHIO, 44153 

N79-22434 

fjnclas 
25103 

D. ANTONIUK 
E.E. LUEDKE 


(NASA-CR-159550) CTS-TYPF VAPIABLP 

s'l Zl, nnal 
1978 (TPK Defen«;p 

and Space Systens Group) 45 p HC A03/!1F^A01 

CSCL 20D G3/34 


TRW SALES NO. 30979.000 


TRW 

OffftfU AMO SAACt SYSTtMtS OMOUR 

* RCOOP40O SfACM • 



ONC «»»ACf RA«»l 



CONTENTS 


Page 


1. INTRODUCTION 

1 

2. BACKGROUND 

2 

3. PHASE I 

3 

3.1 

Artery Splicing 

3 

3.2 

Arteries 

6 

3.3 

Gas Reservoir 

7 

3.4 

Artery Priming Tests 

7 

3.5 

Liquid Inventory 

8 

3.6 

Performance Tests 

10 

3.7 

Summary 

14 

4. PHASE II DESCRIPTION 

15 

4.1 

Final Heat Pipe Design 

15 

4.2 

Heat Pipe Assembly and Processing 

15 

4.3 

Liquid Inventory 

15 

4.4 

Performance Tests 

16 

4.5 

Individual Heat Pipe Summary 

19 

4.6 

Module Assembly 

19 

4.7 

Module Acceptance Test 

21 

5. SUMMARY AND CONCLUSIONS 

25 

APPENDIX 


A-1 


1. INTRODUCTION 


Under Contract NAS3-21130, TRW Defense and Space Systems Oroup 
has fabricated six variable conductance heat pipes (VCHP's) and 
assembled them into two modules of three heat pipes, soldered into 
a common aluminum saddle. THese heat pipes have individual capacities 
of at least 220 watts at 50°C and are over 310 centimeters long. This 
heat pipe design was evolved from the VCHP design which TRW built for 
NASA Lewis Research Center as a part of the Transmitter Experiment 
Package for the CTS spacecraft. 

This report documents the activities conducted under contract 
including development effort, complete design details and test results. 


1 



2. BACKGROUND 


TRW Defense and Space Systems Group has been active in heat pipe 
development since 1964, and has had considerable experience with flight 
heat pipes on CTS, Viking, OAO-C, sounding rockets and other spacecraft. 

The use of variable conductance arterial heat pipes on CTS represents 
the first time that gas loaded heat pipes have been used in the primary 
thermal control system of a spacecraft. THe heat transport capacity of 
the individual CTS heat pipes is approximately 7500 watt-inches. 

Recognizing the potential application of this technology to 
systems such as SEP FM/PPU which have stringent weight limitations, TRW 
pursued an Independent Research and Development Program in 1974 and in 
1975 to implement improvements in the CTS design aimed at doubling the 
capacity. During the I RAD program, two heat pipes were fabricated, one 
with 0.70-inch-diameter arteries and one with 0.080- inch-diameter arteries, 
both using 0.0027-inch priming foils with a single row of 0.0067-inch- 
diameter venting holes. The arteries were placed low in the pipe cross- 
section such that a 0.020-inch gap was maintained between the artery and 
the tube wall. The lower placement of the arteries was to improve the 
ability of the arteries to prime in earth gravity. In addition, a new 
priming foil design was conceived that did not impede the liquid entering 
it and thus allow priming with a low fluid charge. These changes in the 
CTS design were successful in terms of capacity increases but artery 
priming was unreliable. The capacity was increased to 14,300 watt-inches 
at 0.3-inch evaporator elevation which corresponds to the capacity 
predicted in zero gravity. This increase in capacity resulted from the 
use of larger diameter arteries and smaller venting holes in the priming 
foil. The lower placement of the arteries, however, was believed to be 
responsible for the unreliable artery priming. 

In 1977, TRW was awarded contract NAS3-21130 by NASA Lewis Research 
Center to conduct a two-phase program to develop and test two prototypes 
and subsequently, six flight-type variable conductance CTS-type heat pipes 


2 



each with a 14, 000-watt- inch capacity for SEP application. A two phase 
program was called for to confirm that recommended changes in the heat 
pipe design would successfully resolve the priming problems encountered 
in the IR&D program. During Phase I, two methanol/stainless steel heat 
pipes, one with 0.070-inch-diameter arteries and one with 0.80-inch- 
diameter arteries, were to be developed and tested. In addition, since 
the SEP design calls for an overall heat pipe length of 122.5 inches, the 
activities during this phase were to include the development of a tech- 
nique to splice the arteries. 

Contingent upon successful results from these Phase I development 
activities, a design would then be selected for the fabrication of six 
variable conductance heat pipes during Phase II. The heat pipes were 
to be soldered to aluminum saddles as the final fabrication step. 


3 



3. PHASE I DESCRIPTION 


The objective of this phase of the program was to fabricate and test 
two variable conductance heat pipes which incorporated developments 
expected to lead to the 14,000 watt-inch capacity goal and to reliable 
artery priming. 

3.1 ARTERY SPLICING 

One of the first activities in this program was the development 
of a technique to splice the arteries mandated by the SEP design calling 
for an overall length of over 122 inches. 

The arteries are fabricated from 150 mesh stainless steel screen, 
made using 0. 0026-inch-diameter wire. This material is only available 
in 60-inch width. This fact impacts the fabrication of arteries for the 
SEP application since it is mandatory to cut the screen on a 45-degree 
bias to prevent collapse of the arteries when the 90-degree bend if’ the 
heat pipe is formed between the PPL) and the radiator. The longest 
single piece of material that is obtained with this mesh pattern is 
approximately 80 inches; hence, it was necessary to splice the artery 
at some point in the wick structure. Although the slab wick which 
supports the arteries also required a splice, a technique for that splice 
had already been developed and tested during the CTS program. 

A method for splicing the artery was developed and tested. The 
concept is to seam weld a 0.75-inch-wide strip of 0.0005-inch stainless 
steel foil to the two sides of a butt joint in the mesh screen. The 
spliced screen is then used to form the artery following standard manu- 
facturing techniques. The drawing of a test specimen is shown in 
SK77040 in the Appendix. As shown, the foil in the region of the splices 
is inside the artery. The specimen proved to be sufficiently strong to 
render unnecessary the use of an additional section of foil on the out- 
side of the artery. Photographs of the splice sample are shown in Figure 1. 


4 




A. Splice Region 

i 

f 



B. Overall Sample 
Figure 1. Artery Splice Test Sample 


5 


Concurrent with these development activities, detailed drawings 
for the two heat pipes were prepared. The complete set of drawings is 
included in the Appendix. Certain features of the SEP design are 
discussed below. 

3.2 ARTERIES 

The design uses 0.070-inch-diameter and 0.080-inch-diameter arteries. 
For the same capillary pressure these arteries can be expected to have a 
capacity 1.5 times and 2.5 times respectively larger than the 0.063-inch- 
diameter arteries in the CTS design. Following the recommendation made 
after the 1974 and the 1975 I RAD programs, the arteries are located in 
the tube cross-section such that a 0.040-inch gap exists between the 
arteries and the tube wall. The locations of the SEP arteries are shown 
sthenatlcally in Figure 2 where they can be compared to the CTS design, 
ihis configuration yields essentially the same safety factor for artery 
priming as the CTS design. The safety factor is a measure of the ability 
of the arteries to prime in earth gravity, which is taken as the ratio of 
the capillary pressure of the open artery to the hydrostatic pressure 
based on the distance from the bottom of tube to the center of mass of 
the artery. 



Figure 2. Artery Locations in CTS and SEP Designs 


6 



The capillary pressure of the arteries is established by the 0.0067- 
inch-diameter venting holes in the priming foil. Tiis capillary pressure 
is approximately 50 percent greater than the capillary pressure of the 
CTS arteries. The SEP priming foil design uses a 0,00027-inch-thick 
stainless steel foil section with a single row of venting holes. This 
foil is spot welded on the inside of a short stainless steel tube over 
a window cut in it. 

The inside diameter of the priming tube is 0.001 inch larger than the 
inside diameter of the arteries in order to prevent the foil region from 
filling with liquid by capillary pressure before the artery primes. This 
priming foil design is similar to the one developed during the 1974-1975 
IRAD program. Tests have shown that this design does not impede the liquid 
from entering it, thus requiring in principle a lower fluid inventory for 
artery priming. 

3.3 GAS RESERVOIR 

The volume of the gas reservoir is identical to that of the CTS 
reservoir, which is 8.22 cubic inches. Although the reservoir-to- 
condenser volume ratio is approximately 1, compared to the 1.5 to 2.0 
ratio in the CTS design, a tighter control range is achieved (26°F 
versus 52°F). The improved temperature control range is due to the 
fixed, and low, sink temperature of -102°F. Based on the flat gas front 
theory, a gas inventory of 6 x 10“® lb-moles should provide a control 
range from full off at 91°F to the full on at IH^F. 

3.4 ARTERY PRIMING TESTS 

Before the arteries were attached to the slab wick, bubble point 
tests were performed to establish the integrity of the arteries and the 
priming foil . 

Subsequently, the slab wick/artery assemblies were subjected to 
priming tests in a glass tube containing acetone. Tests results with the 
0.080-inch-diameter arteries using 0.081-inch-I.D. priming tubes were 
satisfactory. However, priming tests with the 0.070-inch-diameter arteries 
using 0.071-inch-I.D. priming tubes showed that priming occurred con- 
sistently through the priming cap region and gas was vented through the 
screen. It is believed that the small difference in radii (0.070 inch 


7 



versus 0.071 inch) was insufficient to allow a safety marqin, and slight 
deformation in either the tube or foil during the priming cap installa- 
tion could have resulted in the priming foil region having a smaller 
effective radius than the artery. As a means of guaranteeing that the 
priming tube would be last to prime, the 0.081-inch-I .0. priming tube 
was also installed on the 0.070-in:h-d1ameter arteries. Subsequent tests 
showed this design change resulteo in reliable priming of the 0.070-inch- 
diameter arteries. 

3.5 LIQUID INVENTORY 

A change in the design of the two heat pipes was made in which the 
last 4 inches of the evaporator, including the priming foil caps, was 
exposed by cutting the tube short. This was done to allow observation 
of priming and depriming during the evaluation tests. One of the heat 
pipes, complete with heater tape and thermocouples, is shown in Figure 3. 
The evaporator end was closed with a glass tube and a Swagelok fitting 
using Teflon ferrules as shown in Figure 4. Figures 5 and 6 show the 
exposed wick and artery in more detail. 



Figure 3. Completed SEP FM/PPU Development Heat Pipe 




9 




Figure 6. Exposed Evaporator End of Heat Pipe 

Preliminary tests were performed on both heat pipes to determine the 
minimum fluid change required for priming. This value was determined by 
level priming tests, observing priming at Increasing Inventories until 
repeatable priming occurred. The required Inventory was 120 cc which, 
correcting for the additional length of the SEP heat pipes. Is approxi- 
mately 20 percent less than the CTS Inventory. 

3.6 PERFORMANCE TESTS ? 

The heat pipes were Instrumented with 18 thermocouples, wrapped 
with an electrical heater over a 38-Inch length and mounted over a 
48-Inch length to a temperature-controlled baseplate using a grooved 
condenser block with aluminum foil In all Interfaces. The test configu- 
ration Is shown In Figure 7. Data were taken In the temperature range of 
8S°F to 120°F. The results of tests with the 0. 070-1 nch-dlameter artery 
heat pipe using 0.081-1nch-I.D. priming tubes are shown In Figure 8. 

The solid points shown In the figure have been corrected using capacity 
versus temperature results from tests on the 0.080-1nch-d1ameter artery 
heat pipe. The dashed line Is the performance predicted by the 
Multiwick program and can be seen to be In good agreement with the 
measured values. The zero gravity prediction from the Hultiwick program 


10 




WATUNCH CAPACITY 



corresponds to the result at 0.3-inch evaporator elevation. The fact 
that the zero gravity prediction is lower than the earth gravity results 
at no evaporator elevation is due in part to the contribution from 
fillets and excess fluid natural reservoirs which aids significantly 
the performance in one-g, but not in zero-g. 

The capacity measured at 0.3-inch evaporator elevation was 245 watts. 
As noted in Figure 8, the effective length of the test heat pipe was 72 
inches which corresponds to 17,640 watt-inches. Sir.ce the effective 
length of the heat pipe for actual SEP application is about 64 inches, 
the capacity of the production SEP heat pipes would therefore be 2/5 
watts. Also shown in the figure is the capacity of a single artery. 

This result was obtained by raising the heat pipe until one artery was 
observed to deprime and then applying a heat load. 

Tests were also performed on the 0.070-inch-diameter artery heat 
pipe containing gas in order to verify the effe-. *: of gas on priming and 
capacity performance. At 0.32-inch and l.?3-incn evaporator elevations, 
the capacity with gas was identical to that without gas. Priming was 
consistent with or without gas. Figure 9 shows the temperature profiles 
in the heat pipe at nearly off and fully on conditions. Data for the 
0.080-inch-diameter artery heat pipe are shown in Figure 10. The capacity 
at 0.30-inch evaporator elevation was 310 watts, which corresponds to 
22,300 watt-inches. This capacity is 15 percent lower than Multi wick 
prediction. The discrepancy is attributed to the impaired function of 
one of the arteries. The fact that one of the arteries did not prime 
reliably during priming tests seems to indicate that this artery sustained 
some damage during heat pipe assembly. This heat pipe underwent X-ray 
inspection but the source of the problem could not be identified. 

A number of data points with one 0.080-inch-diameter artery primed 
showed high capacity (14,000 watt-inches) at burnout. Groove dryout or 
partial slab wick dryout was evident with only one artery primed. For 
example, at 0,25-inch elevation, temperature gradients began to appear 
in the evaporator at 160 watts, yet burnout (depriming of the artery) 
did not occur until 210 watts were applied. 




12 


TEMKtATUK 





The capacity as a function of vapor temperature was measured for 
the 0.080-1nch>d1ameter pipe. The data shown In Figure 11 were used to 
correct data taken at various adiabatic temperatures. Testing Is more 
efficient timewise when the sink temperature Is fixed and power Is 
Increased until burnout occurs. This results In burnout data at tempera 
tures different from the design temperature of 122°F. 



Figure 11. Capacity of 0.080-Inch Artery Heat Pipe as a 
Function of Temperature 


3.7 SUMMARY 

The performance of both heat pipes substantially exceeded the 14,000 
watt-inch capacity goal of this program; however, only the 0.070-1nch- 
dlameter artery heat pipe with 0. 081 -Inch- I. D. priming caps showed 
reliable artery priming. As a result, this design was selected for the 
fabrication of six deliverable heat pipes during Phase II. 


14 



4. PHASE II DESCRIPTION 


The objective of this phase of the program was to fabricate six 
variable conductance heap pipes in a configuration suitable for inclusion 
in a development SEP FM/PPU test article. 

4.1 FINAL HEAT PIPE DESIGN 

As recommended from the development activities in Phase I, a heat 
pipe configuration with the 0.070-inch-diameter arteries and 0.081-inch- 
I.D. priming tubes was selected for the fabrication of six deliverable 
heat pipes. Detail drawings of the final design are shown in the Appendix. 
The drawings include the changes made during Phase I, primarily regarding 
the priming tube. The length of the evaporator was increased by 0.15 
inch to allow the end cap weld to extend just beyond the end of the saddle 
when the modules are assembled. An assembly drawing of the modules is 
shown in SK78006 in the Appendix. 

4.2 HEAT PIPE ASSEMBLY AND PROCESSING 

All parts were cleaned per TRW procedure PR 2-28-1. The arteries 
were subjected to bubble tests to establish the integrity of the mesh 
screen and the priming tubes prior to installation of the arteries on the 
slab wick. Subsequently, the completed slab wick/artery assemblies were 
tested for priming reliability. 

As a check of mechanical integrity and to identify any major leak, 
each heat pipe was pressurized with nitrogen to 50 psig and held for 15 
minutes. In addition, each heat pipe was leak checked with a vacuum leak 
detector. No leaks were detected on any of the six heat pipes. Sub- 
sequently, the heat pipes were vacuum bakeu at 275°F for 2 hours. 
Identification numbers, 1 through 6, were scribed on the end caps of each 
heat pipe. 

4.3 LIQUID INVENTORY 

Heat pipe number 3 (HP3) was selected for preliminary tests intended 
to establish the minimum fluid inventory required for reliable artery 
priming. Tests began with a 120 cc methanol inventory which was the one 
used in the Phase I heat pipes. Reliable priming was found at 138 :c. 


15 



and to allow some tolerance, 140 cc were used for the other heat pipes. 

This inventory is proportionally the same as the CTS heat pipe inventory, 
correcting for increased length and larger artery diameter in the SEP 
design. 

4.4 PERFORMANCE TESTS 

The heat pipes were installed on a temperature-controlled base plate 
using 0.5-inch-thick grooved aluminum blocks with aluminum foil between 
all interfaces to assure good thermal contact. The evaporator heater 
was bonded to a grooved aluminum saddle which was bolted to the evaporator 
section of the heat pipe. A sketch of the test configuration and mounting 
details is shown in Figure 12. In this configuration, the effective length 
of the heat pipes was approximately 66 inches. A minimum of six thermo- 
couples were used; more in some tests. 



Figure 12. Test Configuration 


16 



The general test procedure was to level the heat pipe to +^0.010 
inch using a cathetometer, apply 25 watts, tilt the heat pipe to the 
desired evaporator elevation and raise the power sequentially to 100 
watts, 150 watts and 200 watts allowing 15 minutes to elapse between 
power changes. Thereafter, the power was increased in 20-watt increments 
until burnout occurred. In tests where the heat load exceeded 220 
watts, some nonuniform evaporator temperatures were observed. These 
nonuniformities were indications that part’ll groove dryout was occurring 
in the evaporator without evidence of artery failure. The results of 
tests on all heat pipes at 0.30-inch evaporator elevation and 120° +5°F 
adiabatic temperature are summarized in Table 1. As shown, the capacity 
of heat pipe number 6 is 150 watts, which is consistent with only one 

Table 1. Test Resul ts-Evaporator Elevation 0.3 Inch, 
Adiabatic Temperature = 120°F ,t5°F 
(Effective Length of Pipes = 6t Inches) 


Pipe 

Number 

Config- 

uration 

Power 

Held 

(Watts) 

Power at 
Groove 
Dryout 
(Watts) 

Burnout 

(Watts) 

Comments 

1 

1 

220 

- — 

230 

138 cc inventory 

2 

2 

270 

310 

None; 

stopped 

140 cc inventory 

3 

1 

220 

— 

230 

First pipe tested 
138 cc inventory 

4 

1 

220 

260 

None; 
testing 
stopped 
at 300 
watts 

140 cc 

5 

2 

280 

290 

300 

140 cc 

6* 

2 

>150 

150 

175 

141 cc 

7 

2 

300 

220 

320 

140 cc 


♦Performance below specification. 


17 





artery operating. Repeated attempts to prime both arteries were unsuccess- 
ful. As a result, an additional heat pipe was fabricated and tested. 

Tests results on this heat pipe are shown as pipe number 7 in Table 1. 

Additional tests were performed on heat pipe number 5 to establish the 

performance as a function of evaporator elevation, which is shown in 

Figure 13. The data show no evidence of excess fluid contribution to the 

capacity at 0.3-inch evaporator elevation, which is the one predicted in 

zero gravity. The test configuration was modified to allow testing of 

-6 

HP5 loaded with 6 x 10” lb-moles of nitrogen gas. A cooling block was 
installed on the gas reservoir and 0.25 inch of Teflon was inserted between 
the condenser block and the temperature-controlled base plate. With the 
reservoir temperature controlled between -90°F and -98®F, the heat pipe 
turned on at 97°F and was full on at 118°F. The improved temperature 
control range is attributed primarily to the larger reservoir- to-condenser 
volume ratio resulting from the excess fluid reducing the vapor spaces in 
the condenser section. 



-p 20,000 


- - 11,000 V 
u 

I 

i 

T 

c 

--»,ooo I 


j- M,000 


Figure 13. SEP Phase II “ Heat Pipe No. 5 Capacity 


18 



4.5 INDIVIDUAL HEAT PIPE SUMMARY 

Six out of seven heat pipes met, and some of them substantially 
exceeded, the 14,000-watt-inch capacity goal of this program. 

Test results showed some differences in the performance between 
heat pipes in terms of burnout capacity and capacity at which partial 
groove dryout was observed. Differences in burnout capacity could be 
the result of a reduction in cross section at some point in an artery- 
possibly in the region of the 90-degree b^nd. Such a change in cross 
section would reduce the capacity of the arteries due to increased 
liquid flow resistance. 

Differences in observed partial groove dryout could be due to 
nonuniformities in the configuration of the grooves resulting from 
variations in the tube inside diameter and/or wear of the threading 
tool. This phenomenon, however, should not impact the performance of 
the SEP heat pipe module since partial groove dry-out is observed only 
at capacities higher than the designed operating capacities of the 
SEP heat pipes. 

4.6 MODULE ASSEMBLY 

Two modules were assembled, each consisting of three heat pipes 
soldered to two aluminum saddle halves supplied by NASA LeRC. An 
assembly drawing of these modules, configurations A and B, are shown in 
SK78006 in the Appendix. Heat pipes number 1, 2, and 4 were used in 
module A. Module B used heat pipes 3, 5, and 7. 

After the individual performance tests, the heat pipes were vacuum 
dried, backfilled with nitrogen to 1 atmosphere and pinched off before 
they were sent along with the saddles to an outside vendor for plating. 
The specifications for tin plating the stainless steel tube sections and 
the aluminum saddles are shown in SK77036-A and SK78011, respectively, 
in the Appendix. A special fixture for assembling the modules was fab- 
ricated. The fixture with a module at two different stages of assembly 
is shown in Figures 14 and 15. 


19 




Figure 14. SEP Module Partially Assembled in Soldering Fixture 



Figure 15. Assembled SEP Module Prior to Soldering 


20 


As shown in Figure 15, the saddles are spring loaded in order to 
help alignment during soldering. A partial view of a module baseplate 
after soldering is shown in Figure 16. The rectangular tubes extending 
beyond the end of the baseplate were soldered to the saddle halves to 
provide alternate cooling during ground tests of the SEP FM/PPU. 

4.7 MODULE ACCEPTANCE TEST 

The heat pipes of the assembled modules were individually tested. 

The basic test configuration is sketched in Figure 17. 

Four heater tapes, each 0.375 inch wide and 45 inches long, were 
bonded to one side of the baseplate to provide nearly uniform heating 
of the evaporator saddle. As one heat pipe was being tested, the other 
two heat pipes were turned off by heating their gas reservoirs to '\^130°F. 
The condenser section of the test heat pipe was clamped between two 
2.5-inch x 1.5-inch grooved aluminum blocks. Aluminum foil was used in 
all interfaces for good thermal contact. Heat dissipation from the 
condenser block to ambient air by natural convection was sufficient to 
allow steady-state operation of a heat pipe under a 220-watt heat load 
at an adiabatic temperature of about 110°F. To test the performance at 
hignar temperatures the condenser block was partially insulated. A 
liqi'id-nitrogen-cooled block was mounted on the gas reservoir of the 
test heat pipe. 

i.velve thermocouples were used during the tests, located as shown in 
Figure 17- 

The three evaporator thermocouples were placed on the saddle directly 
above the heat pipe being tested. 

Prior to the test of a module, the fill tube was cut open and each 
heat pipe was vacuum-leak checked, filled with 140 cc of spectral grade 
methanol and loaded with 6 x 10"® lb-moles of 90 percent nitrogen - 10 
percent helium gas. The procedure used to load a heat pipe with gas 
consisted in filling a 133 cc reservoir with gas to 25 psia at room 
temperature and then transferring gas into the heat pipe until a 7.2 psi 
pressure drop was observed in the transfer reservoir. 


21 



oTSSSi 

OUAUTY 



Figure 16. Partial View of SEP Module After Soldering 




Figure 17. SEP Module Test Configuration 


22 



The acceptance test procedure is outlined below; 

1) Heat gas reservoirs (TCll and TC12) to 130° +^5°F. 

2) Cool gas reservoir of test heat pipe (TCIO) to -102° 

+5°F. 

3) Raise evaporator end at least 3 Inches, relevel and 
wal t 5 minutes. 

4) Elevate evaporator 0.30 Inch and apply 220 watts. 

5) Turn-on condition: TCI > 80°F when TC4-TC5 < b°F. Full 

on condition; TCI > 1180F when TC4-TC8 s 5°F. 

Tests on several heat pipes following the above acceptance test 
procedure were unsuccessful. These heat pipes failed under loads 
higher than 150 watts which is consistent with only one artery operating. 
Reevaluation of X-iay data taken on the modules revealed the possible 
cause of the priming problem. It was found that in the last few inches 
of the evaporator section of the failed heat pipes the arteries were not 
parallel to each other; i.e. , one artery was higher than the other in 
the tube cross-section. The slab wick had apparently rotated in the pipe, 
possibly during the clamping/soldering operation. This misalignment was 
approximately 1/32 inch. A change in the test procedure was made in which 
the heat pipes were required to prime with the evaporator 0.040 inch 
lower than the condenser rather than being level. This change in the 
test procedure was successful because in suloequent tests all the heat 
pipes satisfied the acceptance criteria. 

The turn-on and full-on temperatures of each heat pipe are shown in 
Table 2. 

As a final step in the processing of the heat pipes, each fill tube 
was pinched off, welded and vacuum-leak tested. 

The modules were delivered packed in individual wooden shipping 
containers. 


23 



Table 2. Tum-on and Full-on Temperatures of SEP Heat Pipes 


Module 

guratlon 

Heat Pipe 
Number 

Temperature ( 
Turn on 

°F) 

Full-on 

A 

1 

103 

123 


2 

103 

121 


4 

105 

126 

B 

3 

100 

124 


5 

100 

125 


7 

105 

126 


24 



5. SUMMARY AND CONCLUSIONS 


TRW Defense and Space Systems Group has completed a two-phase program 
under Contract NAS 3-21'TO for NASA Lewis Research Center in which two 
variable conductance heat pipe modules were fabricated. Each module 
contained three methancl/stainless steel heat pipes with individual 
capacities in excess of 14,000 watt-inches at 50®C. A two-phase program 
was undertaken co demonstrate, with development heat pipes, that the 
design approach developed from earlier TRW Independent Research and 
Development (I RAD) was sound. 

During Phase I of the program a new heat pipe design was concei-'ed, 
based on the results of 1974 and 1975 TRW IRAD programs. Two versions of 
this design were built in configuration suitable for SEP application. 

These prototypes were tested to confirm that changes in the design would 
successfully resolve sporadic priming encountered during the IRAD programs. 

Two heat pipes were fabricated, one using 0. 070-inch-diameter arteries, 
and one using 0.080-inch-diameter arteries. The arteries ere placed in 
the tube cross-section such that a 0. 040-inch gap existed between the 
artery and the tube wall. The priming cap design consisted of a 0.00027- 
inch stainless steel foil with a single row of 0.0067-inch holes spot 
welded on the inside of a 0.75-inch-long stainless steel tube below a 
window (,it in It. The inside diameter of this tube was 0.001 inch larger 
than the inside diameter of the artery to which it was attached. 

The gas reservoir was identical to the CTS design which yieldec 
reservoi r-to-condenser volume ratio of approximately 1. 

In addition, a technique was devised to splice the arteries in order 
to accommodate the increased length (over 122 inches) of the StP heat 
pipes. 

Prior to the assembly of the two heat pipes, priming tests were 
performed on both prototype arteries, the results leading to the utiliza- 
tion of the 0.081-inch-I .D. priming tubes on the 0.070-inch-diameter 
arteries in order to achieve reliable priming. 


25 


With a 120-cc methanol inventory, the capacities of the 0.070-inch- 
diameter artery heat pipe and the 0.080-inch-diameter artery heat pipe at 
0.30 inch evaporator elevation and 120°F adiabatic temperature were 17,600 
watt-inches and 23,200 watt-inches, respectively. Although both heat pipes 
substantially exceeded the capacity goal of 14,000 watt-inches, only the 
0.070-inch-diameter artery heat pipe with 0.081-inch-I,D. priming tubes 
showed reliable priming. As a result, this design was selected for the 
fabrication of six deliverable heat pipes. 

During Phase II of the program, seven heat pipes were fabricated and 
tested. The methanol inventories of the SEP heat pipes was 138 +1 cc. 

This inventory was determined from tests performed on a single heat pipe 
to which fluid was gradually added until reliable priming was observed. 
Acceptance tests were performed on all heat pipes, and six of seven met 
the 220-watt capacity requirement. A selected heat pipe was loaded with 
6 X 10"^ lb-moles of nitrogen gas to determine the effect of the gas on 
the heat pipe capacity and establish its temperature control characteris- 
tics. It was found that the presence of gas had no effect on capacity and 
the temperature control of the heat pipe exceeded the design requirements 
(turn on at 80°F and full on at 122°F). This heat pipe carried up to 
300 watts (36 percent over the required 220 watts), although partial groove 
dry-out was observed at high power levels. 

The individual heat pipes were then emptied, back-filled with nitrogen 
and pinch-weld closed. The evaporate-'' regions were tin plated and fused 
prior to installation in two heat p<..> modules. Each module consists of 
three heat pipes whose evaporator sections are soldered to two half-aluminum 
saddles which form a baseplate. 

After the module was soldered, the heat pipes were individually sub- 
jected to acceptance tests. Each heat pipe was filled with 140 cc of 
spectral grade methanol and loaded with 6 x 10"^ lb-moles of 90 percent 
nitrogen - 10 percent helium gas. 

The final acceptance test procedure consisted of leveling the heat 
pipe to allow the arteries to prime, cooling the gas reservoir to -102°F, 
elevating the evaporator end 0.30 inch and applying 220 watts. The heat 
pipe was required to turn on at a tetuperature higher than 80°F and to be 


26 


fully on at a temperature higher than 118°F under the applied heat load. 
Several heat pipes failed this acceptance test because one of their 
arteries did not prime. During reevaluation of X-ray data taken on the 
module, it was found that in the last few inches of the evaporator section 
of the failed heat pipes the arteries were not parallel to each other; 
i.e., one artery was higher than the other in the tube cross-section. The 
slab wick had apparently rotated in the pipe, possibly during the clamping/ 
soldering operation. This misalignment was approximately 1/32 inch. 

Tests were repeated in which the heat pipes were allowed to prime with 
the evaporator end 0.040 inch lower than the condenser, and the results 
were successful . 

The six heat pipes turned on at temperatures higher than 100°F and 
were fully on at temperatures higher than 121°F. 

The improved temperature control range is attributed primarily to the 
larger reservoir- to-condenser volume ratio resulting from the excess fluid 
reducing the vapor spaces in the condenser section. 


27 





APPENDIX 
DESIGN DRAWINGS 


DRAWING NO. 

77030 A 

77031 A (1 of 2) 

77031 A (2 of 2) 

77032 A 

77033 

77034 

77035 

77036 B (1 of 3) 

77036 {2 of 3) 

77036 A (3 of 3) 
77040 

78006 

78011 


TITLE 

TUBE AND PLUG, SEP HEAT PIPE 
WICK ASSY, SEP HEAT PIPE 
WICK ASSY, SEP HEAT PIPE 
PRIMING TUBE ASSY. SEP HEAT PIPE 
RESERVOIR WICKS, SEP HEAT PIPE 
RESERVOIR, SEP HEAT PIPE 
PRIMING FOIL 

SEP HEAT PIPE ASSY. CONFIG. NO. 1 
SEP HEAT PIPE ASSY. 

SEP HEAT PIPE ASSY. CONFIG. NO. 2 
ARTERY SPLICE TEST SAMPLE 
SEP HEAT PIPE/BASEPLATE MODULE ASSEMBLY 
SADDLE PLATING 


PAGE BLANK fWT 


A-1 










REVISIONS 


t 


0 ^ ^ 


nm 


CO 



3 


































REVISiONS 



6 








































REVISIONS 


DATE APPROVED 


ORIGINAL PAGE IS 
OF POOR QUALITY 


.030 T-Q c»vreg 

. 0066 0 /A moles 


PdlHItJ&p T-OtL Oe-TAlu. 


toil. 

35*y CiSFS^ .Qoozirnt ^OtL. 

DFSCAfAnOM 

MArpe»Au 


IrrH 

WO 


BIGMEEVING SKETCH 


•leWIATO* 

0 






PQlMfisK:^ ^OIL 


COOL NXNT NQ 

11982 


INUT 1 OF 


tVlTDM Ml « IV . I ». T « 


A-8 


























,-9 




















hginm page «s 

: POOR QUALITY 


» T 
m m 

•. 

•. If 

5 •» 

* i 

£ 55 

j “ 


> 3 

14 < 

a ; 

« 


0 

•: f 

u 

o' 

i : 
“• 3 

. »» 

1 

9 2 


a 

I 

O 


5.f 


*00 H 03'' 



















("St 


1 


1, Dooeufc 


R 

vy 

I 4 

. I 



OfilQflVAL PAGE IS 
OF POOR QUALITY 



A-14 


11982