Transportation System Plan 2018-2038

Medford · Page 210 of 398 · Adopted 2018-12-06

These projects are further discussed in the paragraphs below. Construction of New Bicycle Lanes as Part of Roadw ay Improvements A num ber of bicy cle facility improvem ents will be constructed as part of the street improvem ents (including new construction and str eet reconstruction projects) that are described in Chapter 5 and illustrated in Figure F-1. In addition to the percent of arterial and collector streets that currently have bicycle lanes, the planned/ program med improvem ents identified in Figure F-1 will cover another 26 percent of the arterial and m ajor collector street sy stem , bringing the total coverage to about 68 percent. 100 percent coverage of arterial and collector streets would contribute to an ideal bicy cling environm ent, but this goal is probably not feasible due to lack of right-of-way , built or natural environm ental impacts, extraordinarily high costs, the priority need for on- street parking, or other factors. Retrofitting Bicycle Lanes onto Existing Streets Beyond the bicy cle sy stem improvem ents that will be constructed as part of a street improvem ent project, other im provem ents are will be m ade through retrofitting the existing street system . The improvem ents are intended to address the strategic approach to providing im proved bicy cle circulation in Medford that was discussed in the section on “Strategies”. They are also intended to m eet State, regional, and local goals and requirem ents for bicy cle sy stem enhancem ents that were discussed earlier in this under “Policy Context and Background”. Figure 10-1 illustrates th e bicy cle facility improvem ents, and Table 10-5 provides a detailed list of the sam e projects. If fully implem ented, the bicy cle facilities will result in a coverage of 88 percent of Medford’ s arterial and coll ector street sy stem . This would exceed Medford’ s share of the RTP Alternative Measures goal of 60 percent for the RVMPO region. Table 10-5 New Bicycle Facilities Street From To On-Street Bicy cle Lanes Beall Lane Urban Grow th Boundary Highw ay 99 Biddle Road Airport Road (south) Airport Road (north) Biddle Road Business Park Drive Table Rock Road Black Oak Drive Lawrence Avenue Barnett Road Black Oak Drive Siskiy ou Boulevard Acorn W ay Brookdale Avenue Spring Street McAndrew s Road Bullock Road Highw ay 62 North end of street Cedar Links Road Springbrook Road Wilkshire Drive Central Avenue McAndrew s Road Riverside Avenue Coal Mine Road North Phoenix Road East Urban Grow th Boundary Coker Butte Road North-South Industrial Road Lear W ay Columbus Avenue Prune Street McAndrew s Road Court Street Highw ay 62 Edwards Street Cunningham Avenue/W illow Way Urban Gr owth Boundary Columbus Avenue Dakota Street Columbus Avenue Hamilton Street Delta W aters Road Highw ay 62 Crater Lake Avenue Diamond Street Orchard Home Drive Peach Street Medford Transportatio n System Plan 10-8 Non-M otorized Transportation Plan
Ask AI what this page says about a topic: