Transportation System Plan 2018-2038
Medford · Page 343 of 398 · Adopted 2018-12-06
Table F-2 Continued
Planned Short-Range Roadw ay System Improvements
Medford UGB
Funding Agency
Project Location Project Description Project Ty peMedford Other Cost
Jackson County Tier 1 – Short-Range (2001-2005)
Table Rock Rd, Pine St, Biddle to
Wilson Rd Widen to five lanes w ith bike lanes and
sidew alks Capacity $4,160,000
Vilas Rd, Table Rock Rd to Hw y 62 Widen to three lanes w ith bike lanes
and sidew alks Capacity $3,343,000
Sage Rd, Posse to Ehrman Way Widen to three lanes w ith bike lanes
and sidew alks Capacity $1,760,000
Oak Grove Rd, Medford UGB to
Hwy 238 Widen to tw o & three lanes w ith bike
lanes and sidew alks Capacity $390,000
Jackson County Short Range Costs - $9,653,000
ODOT Tier 1 – Short-Range (2001-2005)
Hwy 62/N. Medford Interchange
Corridor Solutions Construct five lane overpasses, w iden
bridge, re-configure interchange –
ODOT+Federal Shares) Capacity $35,000,000
S. Medford Interchange Construct new interchange – ODOT
share Capacity $35,700,000
S. Medford Interchange Construct new interchange –
Medford/Developer/MURA share Capacity $15,000,000
ODOT Short Ra nge Cos ts - $54,039,000
Source: Regional T ransportation Plan, RVCOG, 2002 (updated to account for proj ects completed in 2002/2003).
Together the City of Medford and Jackson County have over $29 m illion in short-range roadway system
improvem ents program med for im plem entation within the City ’s UGB. The City ’s short-range
improvem ents include capacity and operations projects, while Jackson County ’s short-range
improvem ents are all capacity improvem ents. All C ity and County capacity improvem ents regardless of
timefram e include sidewalks and bicy cle lanes.
Table F-3 summarizes over $16 million in m edium -range im provem ents slated for the 2006-2010 period.
As with the short-range im provem ents, the City has identified both capacity and operational projects, with
County projects focusing on capacity improvem ents.
Table F-3
Planned Medium-Range Roadw ay System Improvements
Medford UGB
Funding Agency
Project Location Project Description Project Ty peMedford Other Cost
Medford Tier 1 – Medium -Range (2006-2010)
N. Front St., Jackson to Edw ards Construct new three lane road w ith bike
lanes and sidew alks Capacity $5,000,000
Cherry Ln, N. Phoenix Rd to
Hillcr est Rd Widen to three lanes w ith bike lanes
and sidew alks Capacity $4,000,000
Springbrook, Cedar Links Rd to
Delta Waters Rd Widen to three lanes w ith curb, gutter,
bike lanes and sidew alks Capacity $1,250,000