FM 5-35 OBSOLETE Engineer Field Manual Reference Data

Survival, Water, Medical Field Manuals

Military Manuals

United States. War Department

Document text

FM  5-35 


WAR  DEPARTMENT 

ENGINEER  FIELD  MANUAL 
REFERENCE  DATA 

February  15,  1941 

% 


FM  5-35 


ENGINEER  FIELD  MANUAL 

j* 

REFERENCE  DATA 


Prepared  under  direction  of  the 
Chief  of  Engineers 


UNITED  STATES 

GOVERNMENT  PRINTING  OFFICE 
WASHINGTON  : 1941 


For  sale  by  the  Superintendent  of  Documents,  Washington,  D.  C. 
Price  73  cents 


WAR  DEPARTMENT, 
Washington,  February  15,  1941. 

FM  5-35.  Engineer  Field  Manual,  Reference  Data,  is  pub- 
lished for  the  information  and  guidance  of  all  concerned. 

[A.  G.  062.11  (10-2-40).] 

By  order  of  the  Secretary  of  War: 

G.  C.  MARSHALL, 

Chief  of  Staff. 

Official: 

E.  S.  ADAMS, 

Major  General, 

The  Adjutant  General. 

Distribution: 

R 2,  5,  17  (10),  36,  7 (5) ; 

IR  4 (5) ; Bn  2-11,  17  <5) ; 

C 2,  5,  17  (10) , 3,  6,  7,  9,  10,  11  (5) . 


n 


TABLE  OP  CONTENTS 
Chapter  1.  Engineer  Troops  and  Operations. 

Paragraphs  Page 


Section  I.  General 1-4  1 

II.  Engineer  units 5-14  3 

III.  Camps  and  supply  systems 15-17  25 

IV.  Forms  and  orders 18-22  29 

Chapter  2.  Communications,  Construction,  and  Utilities. 

Section  I.  Roads 23-31  50 

II.  Bridges  and  stream  crossings 32-54  73 

III.  Railways 55-56  118 

IV.  Construction  in  war 57-62  125 

V.  Water  supply 63-72  140 

VI.  Electricity 73-77  159 

VII.  Rigging 78-82  168 

VIII.  Concrete 83-87  186 

Chapter  3.  Defensive  Measures. 

Section  I.  Field  fortifications 88-110  193 

II.  Camouflage 111-128  282 

III.  Explosives  and  demolitions 129-138  305 

IV.  Barriers  and  antimechanized 

defense 139-146  324 

Chapter  4.  Miscellaneous  Data. 

Section  I.  Mathematical  and  physical  data..  339 

II.  Data  on  materials 355 

III.  Troop  movement)  data 363 

Index 365 


III 


FM  5-35 


ENGINEER  FIELD  MANUAL 

REFERENCE  DATA 
CHAPTER  1 

ENGINEER  TROOPS  AND  OPERATIONS 

Paragraphs 


Section  I.  General 1-4 

II.  Engineer  units 5-14 

III.  Camps  and  supply  systems 15-17 

IV.  Forms  and  orders 18-22 


Section  I 
GENERAL 

■ 1.  Purpose  and  Scope. — a.  The  Engineer  Field  Manuals  are 
designed  to  furnish  technical  information,  describe  the  or- 
ganization of  engineer  units,  and  outline  typical  procedures 
that  may  be  followed  in  the  conduct  of  the  more  common 
operations  undertaken  by  engineers  in  the  theater  of  opera- 
tions. Local  conditions  in  the  field  will  always  affect  the  ap- 
plication of  these  procedures,  tables,  and  formulas;  they 
should  be  taken  as  suggestions  and  guides  to  be  used  with 
judgment  and  modified  to  conform  to  the  situation  rather 
than  as  regulations  to  be  rigidly  followed. 

b.  The  purpose  of  this  manual  is  to  present  the  funda- 
mentals from  the  Engineer  Field  Manuals,  FM  5-5  to  FM  5-30, 
inclusive,  in  such  condensed  form  as  to  be  available  in  a single 
text  when  needed  for  ready  reference  in  the  field.  Informa- 
tion and  instructional  matter  not  needed  by  experienced  en- 
gineers or  details  available  elsewhere  required  for  deliberate 
construction  have  been  omitted.  Other  data  required  for 
field  construction  have  been  added. 

■ 2.  Basic  Conceptions. — a.  The  purpose  of  the  engineer 
arm  is  to  assist  in  the  accomplishment  of  the  mission  of  the 
force  as  a whole.  The  amount  and  character  of  engineer 
work  necessary  to  render  this  assistance  will  depend  upon 
the  nature  of  the  terrain,  the  climate,  the  resources  and 
development  of  the  theater  of  operations,  and  the  character 
of  enemy  activity. 

1 


r 


2-4  CORPS  OF  ENGINEERS 

b.  The  mission  of  engineers  is  to  increase  the  combat 
effectiveness  of  all  other  arms  through  the  execution  of 
work  to — 

(1)  Facilitate  movement  of  our  troops. 

(2)  Impede  movement  of  the  enemy. 

(3)  Provide  for  shelter  and  comfort  of  our  troops. 


■ 3.  Duties  in  Theater  of  Operations. 

a.  Remove  or  pass  obstacles. 

b.  Provide  stream  crossings. 

c.  Repair  and  construct  roads. 

d.  Repair,  extend,  and  operate  railways  and  inland  water- 
ways. 

e.  Construct  wharves  and  other  facilities  for  water  trans- 
portation. 

/.  Construct  and  maintain  landing  fields. 

p.  Execute  demolitions  and  create  obstacles. 

h.  Give  technical  assistance  and  furnish  tools,  supplies, 
and  materials  for  construction  of  protective  works  and  cam- 
ouflage. 

i.  Construct  works  requiring  special  equipment  and  training. 

j.  Fight  as  riflemen  in  emergency.  (See  fig.  26.) 

k.  Make  and  distribute  maps. 

l.  Construct  shelters. 

m.  Construct  supply  and  evacuation  establishments. 

n.  Provide  water  supply. 

o.  Provide  and  operate  general  utilities. 

■ 4.  Character  of  Construction. — All  work  of  engineers  in 
war  should  be  simple  in  conception,  design,  and  execution. 
No  construction  should  be  better  than  is  necessary  to  meet 
bare  requirements.  It  should  be  accomplished  with  the  great- 
est possible  economy  of  material  and  force  in  the  minimum  of 
time,  and  plans  therefor  should  be  flexible  to  permit  of  last 
minute  changes  or  alterations.  For  most  structures,  factors 
of  safety  can  be  extremely  low  and  standards  of  durability 
limited.  Standardization  is  desirable  and  will  facilitate  work 
in  rear  areas;  however,  in  the  theater  of  operations  it  will 
generally  be  necessary  to  make  a maximum  use  of  expedients. 
Officers  and  men  alike  must  be  trained  in  locating  materials 
by  engineer  reconnaissance,  and  in  employing  maximum 
ingenuity,  resourcefulness,  and  common  sense  in  their  use. 


2 


REFERENCE  DATA 


5 


Section  II 
ENGINEER  UNITS 

■ 5.  Kinds  of  Units. — a.  General  engineer  troops. 

(1)  With  infantry  divisions. 

(a)  Combat  battalion  (assigned  to  triangular  division). 

(b)  Combat  regiment  (assigned  to  square  division). 

(2)  With  armored  units — combat  battalion  (armored). 

(3)  With  cavalry  units — squadron  (assigned  to  cavalry  di- 
vision) . 

(4)  Nondivisional  units. 

(a)  Combat  regiment  (corps)  (assigned  to  corps). 

(b)  General  service  regiment  (assigned  to  army  and  higher 
units) . 

(c)  Engineer  regiment  (aviation)  (assigned  to  GHQ  Air 
Force) . 

(d)  Separate  battalion  (assigned  to  army  and  higher 
units) . 

b.  Special  engineer  troops. 

(1)  Camouflage  units. 

la)  Army  camouflage  battalion. 

(b)  GHQ  camouflage  battalion. 

(2)  Ponton  units. 

la)  Light  ponton  company. 

(b)  Heavy  ponton  battalion. 

(3)  Railway  units. 

(a)  Railway  operating  battalion. 

lb)  Railway  shop  battalion. 

(4)  Mapping  units. 

(a)  Corps  topographic  company. 
lb)  Army  topographic  battalion. 

(c)  GHQ  topographic  battalion. 

(5)  Supply  units. 

la)  Water  supply  battalion. 

(b)  Dump  truck  company. 

(c)  Depot  company. 

Id)  Shop  company,  mobile. 

c.  Engineer  headquarters. — These  are  indicated  in  the  fol- 
lowing table  for  the  assignment  of  engineer  units  to  a type 
GHQ  force  of  three  armies. 


3 


5 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


5-6 


Table  X. — Assignment  of  engineer  units  to  a type  GHQ  force  of 
three  armies 


Strength 

Designation  of  engineer  unit 

Number 1 normally 
assigned  to  various 
tactical  units 

y 

a 

0 

a 

1 
© 
H 

Officers 

Enlisted  men 

Division 

& 

E 

© 

o 

>» 

S 

E 

< 

GHQ  reserve 

8 

O 

u 

< 

Combat  battalion  (triangular  division) 

* 1 

9 

* l 

« 1 

« 1 

18 

2 

18 

3 

10 

19 

f> 

30 

48 

1 

3 

1 

1 

2 

g 

14 

1 

3 

1 

1 

1 

3 

6 

1 

9 

12 

2 

18 

24 

4 

12 

24 

1 

9 

1 

3 

6 

1 

1 

Engineer  headquarters  (communications 

1 

1 

Engineer  headquarters  (communications 

3 

3 

1 

3 

1 

9 

1 

1 

Engineer  headquarters  (railway  grand  dlvi- 

5 

5 

15 

15 

2 

2 

1 

1 

2 

2 

' Does  not  include  engineer  units  in  subordinate  tactical  units. 
> Per  infantry  division  (triangular). 

* Per  cavalry  division. 

* Per  armored  division. 

* Per  infantry  division  (square). 


Note. — This  distribution  is  merely  illustrative  and  Is  based  on  the 
normal  needs  of  a type  GHQ  Force  consisting  of  a GHQ  Air  Force 
and  3 type  armies  with  3 type  corps  each  consisting  of  1 triangular 
and  2 square  infantry  divisions. 


■ 6.  Engineers  With  Infantry  Divisions. — a.  Combat  bat- 
talion.— As  the  engineer  component  of  the  triangular  infantry 
division,  this  unit  performs  the  normal  generai  engineer  work 


I 

f 


I 


E 


4 


5 


6-8 


CORPS  OF  ENGINEERS 


for  the  division  when  the  division  is  operating  as  part  of  a. 
corps.  The  combat  battalion  will  often  be  reinforced  to  meet 
the  needs  of  an  independent  division.  Transportation  is 
sufficient  for  all  personnel  and  material;  armament  consists 
of  rifles,  bayonets,  caliber  .30  heavy  machine  guns,  and  pistols. 
The  battalion  commander  is  also  on  the  staff  of  the  division 
commander  as  unit  engineer  and  is  responsible  for  engineer 

supply  to  the  division.  . . 

b Combat  regiment.— The  normal  general  engineer  work 
of  a square  infantry  division  (operating  independently  or  as 
part  of  a corps)  is  performed  by  this  unit.  In  addition  to 
equipment  similar  to  that  of  the  combat  battalion,  it  has  a 
map  reproduction  trailer.  Transportation  is  sufficient  for 
all  personnel  and  material.  Armament  consists  of  rifles  with 
bayonets,  caliber  .30  heavy  machine  guns,  and  pistols.  Tfle 
regimental  commander  is  also  division  engineer  (see  o above) . 

■ 7 ENGINEERS  WITH  Armored  Units.— The  engineer  bat- 
talion entirely  motorized,  is  the  engineer  component  of  the 
a rmored  division . Equipment,  other  than  that  of  the  bridge 
company,  corresponds  generally  to  that  of  the  combat  bat- 
talion. The  bridge  company  has  a wrecking + truck,  portabe 
cranes  power  boats,  heavy  ponton  equipment,  units  of  H 10 
and  H-20  portable  steel  bridges  and  portable  steel  trestle 
bridge,  two  portable  ferries,  outboard  motors,  and  radios. 
Armament  consists  of  caliber  .50  machine  guns,  heavy  and 
light  caliber  .30  machine  guns,  submachine  guns,  rifles,  and 
pistols  Transportation  includes  half-track  personnel  car- 
riers, half-track  cars,  and  scout  cars  all  with  armament 
i/2-ton  weapon  carrier  trucks,  and  special  trucks  and  trailers 
for  the  bridge  company.  The  battalion  commander  is  also 
division  engineer  (see  par.  6a) . 

■ 8 Engineers  With  Cavalry  Umrs.-The  engineer  squad- 
ron assigned  to,  and  performing  the  normal  general  engineer 
work  for  the  horse  cavalry  division  is  similar  to  the  combat 
battalion  in  armament  and  equipment  as  well  as  transporta- 
tion which  is  adequate  for  the  simultaneous  movement  of  all 
personnel  and  material.  The  squadron  commander  is  also 
division  engineer  (see  par.  6a) . 


6 


Figure  2. — Engineer  regiment,  combat  (square  division). 


REFERENCE  DATA 


9 


CORPS  OF  ENGINEERS 


■ 9.  Nondivisional  General  Engineer  Units. — a.  Combat 
regiment  (.corps). — Two  such  regiments  are  assigned  to  each 
type  army  corps  for  the  performance  of  general  engineer  work 
in  forward  parts  of  the  corps  service  area  and  such  division 
service  areas  as  may  be  taken  over  by  the  corps.  It  is  the 
primary  source  of  reinforcements  for  divisional  engineers. 
Power  equipment  includes  motorized  air  compressors  with  air 
tools,  a motorized  earth  auger,  a motorized  road  grader,  gaso- 
line shovels,  and  medium  tractors  with  bulldozers.  Trans- 
portation is  sufficient  for  all  personnel  and  material. 

b.  General  service  regiment. — This  unit  is  assigned  organ- 
ically to  army  and  higher  units  for  the  performance  of  gen- 
eral engineer  work  requiring  a high  percentage  of  skilled  labor. 
It  generally  resembles  the  combat  regiment  (corps)  in  organi- 
zation, equipment,  and  armament.  Transportation  is  suffi- 
cient for  equipment  and  supplies  but  is  not  provided  for  per- 
sonnel. 

c.  Engineer  regiment,  aviation. — This  unit  is  attached  to 
the  GHQ  Air  Force  and  operates  under  the  technical  supervi- 
sion of  the  engineer  section  of  that  or  other  task  air  force 
headquarters  for  the  primary  purpose  of  assisting  in  the  pro- 
vision of  necessary  air  bases  and  advanced  airdromes.  Its 
power  equipment  includes  motorized  air  compressors  with  air 
tools,  road  graders,  carryall  scrapers,  a trencher,  tractor 
cranes,  compaction  rollers  of  various  types,  plows,  gasoline 
shovels,  a road-material  mixer,  and  tractors  with  bulldozers. 
Transportation  is  sufficient  for  moving  all  personnel  and 
equipment  simultaneously.  Armament  consists  of  rifles  and 
pistols. 

d.  Separate  battalion. — The  separate  battalion  is  frequently 
attached  in  whole  or  in  part  as  needed  to  reinforce  other  gen- 
eral engineer  units,  or  it  may  operate  alone.  Tools  and  equip- 
ment include  air  compressors,  a road  grader,  and  a gasoline 
shovel,  all  motorized;  medium  tractors  with  bulldozers,  and  a 
concrete  mixer.  Transportation  is  sufficient  to  move  all  ma- 
teriel (but  not  personnel)  at  one  time.  Armament  consists 
of  rifles,  bayonets,  and  pistols. 


in 


REFERENCE  data 


11 


Figure  5. — Engineer  regiment,  combat  (corps). 


282736°— 41 


CORPS  OF  ENGINEERS  REFERENCE  DATA 


I 


REFERENCE  DATA 


10-11 


■ 10.  Camouflage  Units. — a.  Camouflage  battalion,  army. — 
One  such  unit  is  assigned  to  each  type  army  of  three  type 
corps.  Its  primary  mission  is  camouflage  inspection,  disci- 
pline, and  training  in  the  army  area. 


Figure  9. — Engineer  battalion,  camouflage,  army. 


b.  Camouflage  battalion,  GHQ. — This  is  primarily  a manu- 
facturing unit,  but  its  duties  also  include  inspection,  train- 
ing, experimentation,  and  preparation  of  camouflage  plans. 
It  forms  a nucleus  for  the  organization  of  large  camouflage 
factories,  depots,  and  training  centers. 

■ 11.  Ponton  Units. — a.  Light  ponton  company. — This  unit 
maintains  and  transports  its  equipment  but  normally  does  not 
construct  bridges  except  in  emergencies.  The  company  is 
used  to  instruct  or  assist  other  troops  in  the  use  of  the  equip- 
ment, to  guard  and  maintain  completed  bridges,  to  regulate 
traffic  thereon,  and  to  dismantle  the  bridges. 

(1)  Equipment  is  of  three  types,  as  follows: 

(a)  Three  units  of  light  ponton  equipage,  10-ton,  M1938, 
each  of  which  will  provide  a complete  bridge  about  250  feet 
long. 

(b)  Three  units  of  footbridge,  M1935,  each  sufficient  for 
432  feet  of  bridge. 

(c)  One  hundred  twenty  assault  boats. 


15 


BN.COMDR 
LT.  COLONEL 


Figure  10. — Engineer  battalion,  camouflage,  GHQ. 


REFERENCE  DATA 


11-12 


(2)  The  company  has  sufficient  transportation  for  all 
personnel  and  equipment  except  that  prime  movers  for  the 
99  trailers  on  which  the  ponton  equipage  is  transported  must 
be  furnished  from  other  sources  by  higher  command. 


Figure  11. — Engineer  company,  light  ponton. 


b.  Heavy  ponton  battalion. — This  unit  maintains  and 
transports  the  heavy  ponton  equipage,  25-ton,  M1940.  The 
battalion  is  not  organized  primarily  for  construction  of  ponton 
bridges,  which  is  normally  the  function  of  general  engineer 
troops.  However,  under  some  circumstances  the  battalion 
may  construct  the  bridge.  Like  the  light  ponton  company, 
it  is  often  used  to  instruct  and  assist  other  troops,  to  guard 
and  maintain  completed  bridges,  to  regulate  their  traffic, 
and  to  dismantle  them.  Bridging  equipment  carried  on  semi- 
trailers drawn  by  4 by  4 trucks  consists  of  four  complete 
units,  each  of  which  will  afford  250  feet  of  bridge. 

■ 12.  Railway  Units. — a.  Railway  operating  battalion. — The 
mission  of  this  unit  is  to  operate  the  trains  and  yards  of  a 
railway  division;  to  maintain  the  track  and  structures  of 
the  division;  and  to  make  running  repairs  to  equipment.  A 
railway  operating  battalion  may  also  be  assigned  to  the  op- 
eration and  maintenance  of  a large  railway  terminal  or 
regulating  station. 


17 


Figure  12. — Engineer  battalion,  heavy  ponton. 


Figure  13. — Engineer  battalion,  railway  operating 


CORPS  OF  ENGINEERS  I REFERENCE  DATA 


12 


CORPS  OF  engineers 


j>.  Railioay  shop  battalion. — This  unit  handles  the  heavy 
shop  work  of  several  railway  operating  battalions.  It  as- 
sembles locomotives  and  other  railway  equipment  and  makes 


20 


Figure  14. — Engineer  battalion,  railway  shop. 


REFERENCE  DATA 


12-14 


all  major  repairs  thereto.  It  also  manufactures  replacement 
parts  not  available  in  depots. 

■ 13.  Mapping  Units. — a.  Corps  topographic  company. — This 
unit  increases  the  density  of  survey  control  and  extends  it  as 
needed  for  the  coordination  of  field  artillery  fire.  It  provides 
map  information  to  the  corps  more  rapidly  than  it  can  be 
expected  from  the  army  topographic  battalion.  The  company 
also  prepares  and  reproduces  overlays  and  sketches  for  corps 
headquarters. 


Figure  15. — Engineer  company,  topographic,  corps. 


b.  Army  topographic  battalion. — The  primary  mission  of 
this  unit  is  to  provide  map  information  adequate  for  the  tac- 
tical and  strategical  requirements  of  the  army.  Detachments 
may  be  made  to  a corps  operating  on  an  independent  mission. 
1 c.  GHQ  topographic  battalion. — The  primary  mission  of  this 

unit  is  the  reproduction  in  large  quantities  of  maps,  special 
sketches,  and  drawings  for  GHQ  and  for  distribution  to  lower 
echelons.  It  may  frequently  be  required  to  reinforce  army 
topographic  battalions,  although  most  of  its  equipment  re- 
quires semipermanent  installation. 

■ 14.  Other  Units. — a.  Water  supply  battalion. — The  primary 
I mission  of  this  unit  is  to  purify  water  and  transport  it  by  tank 

trucks  to  areas  where  the  local  supply  is  deficient.  It  may 
also  be  required  to  develop  sources  and  operate  water  supply 
points  when  such  work  is  beyond  the  capability  of  the  general 
engineer  troops  in  the  area.  The  unit  may  operate  under 
army  control,  or  elements  may  be  used  to  reinforce  subordi- 
nate units.  One  water  supply  battalion  is  normally  assigned 
to  each  type  army,  but  two  or  more  may  be  used  depending 
upon  the  need  for  transportation  of  water  in  the  army  area. 

21 


CORPS  OF  ENGINEERS  I REFERENCE  DATA 


14 


CORPS  OF  ENGINEERS 


Figure  18. — Engineer  battalion,  water  supply. 


b.  Dump  truck  company. — The  primary  mission  of  this 
unit  is  to  transport  road  metal  or  other  bulky  materials  needed 
in  engineer  operations.  Each  company  has  forty-five  1 Vi- 
to n dump  trucks  for  this  use. 


Figure  19. — Engineer  company,  dump  truck. 


c.  Depot  company. — This  unit  is  employed  in  connection 
with  the  operation  of  engineer  depots  and  other  engineer  sup- 


; 


Figure  20. — Engineer  company,  depot. 
24 


REFERENCE  DATA 


14-15 


ply  points.  It  may  form  a nucleus  for  a large  special  engi- 
neer depot  or  the  engineer  section  of  a general  depot,  or  it 
may  operate  alone  a smaller  engineer  supply  establishment. 
Depot  sections,  or  detachments  therefrom,  may  assist  in  the 
operation  of  engineer  supply  points  in  army  service  areas  or 
may  be  attached  to  corps. 

d.  Mobile  shop  company. — The  mission  of  this  unit  is  to 
accomplish  third  echelon  maintenance  of  all  equipment  (ex- 
cept railway),  for  the  maintenance  of  which  the  corps  of 
engineers  is  responsible. 


Figure  21. — Engineer  company,  mobile  shop. 


Section  III 

CAMPS  AND  SUPPLY  SYSTEMS 

■ 15.  Bivouacs. — a.  Location. — (1)  Location  and  lay-out  de- 
pend upon  the  tactical  situation. 

(2)  Locate  near  the  route  which  is  being  used,  and  parallel 
thereto  when  possible. 

(3)  Make  maximum  use  of  natural  cover  and  avoid  regular 
patterns. 


V 


25 


15-16 


CORPS  OF  ENGINEERS 


B0A1X 


BN  HO  TRANSPORTATION 
..KITCHEN 

/VBN  HQ  8 MESSAGE  CENTER 


□ ‘ 1 . A w| 
x\A  A , 
XaAvno' 

□ U\(R- 

□ n J i 

BN  OFFICERS  . 

° . 

— rO — BN  MO J 

a HQ  CO  AREA  | 


-CoC  - 
AREA 


-Co  a — 
AREA 


CO  TRANSPORTATION 
Co  KITCHEN 
SHELTER  TENTS(I-Co) 


C-  01  MO  l»V  ANtA  |l>  ^ 

Figure  22. — Diagrammatic  lay-out  of  battalion  bivouac. 


(4)  Allow  50  square  yards  per  man  or  animal  and  100 
square  yards  per  vehicle. 

b.  Sanitary  measures. — (1)  Dig  latrines  immediately  at 
rate  of  one  per  company  for  men  and  one  per  battalion  for 
officers.  Keep  latrines  away  from  and  down  wind  of  kitchens. 

(2)  Establish  water  supply  facilities  quickly,  inform  troops, 
and  mark  watering  places. 

(3)  Dig  a garbage  disposal  pit  (4  by  4 by  4 feet)  for  each 
kitchen. 

(4)  Police  site  thoroughly  upon  leaving.  Pill,  mark,  and 
date  all  latrine  and  garbage  pits. 

■ 16.  Camps. — Allow  50  square  yards  per  man  or  animal  and 
100  square  yards  per  vehicle. 


26 


REFERENCE  DATA 


16 


27 


EXPANSION  AREA  NO.  I 


-7777/77. 


TO  THE 
FRONT 


'///////////*  WAREHOUSE 

/.  PHONOGRAPHIC,  ORAP  TRIG.  SURVtYNO,  OFFICE  A HO  ELECTRICAL  EQUIPMENT 
'/  AND  SUPPLIES*  TOOLS*  CEMENT*  MACHINES*  CHEMICALS  ETC, 


LUMBER 


ROAD  METAL 


/ RQAO  1-ONSTROCTIOH  / 

AND  MSOELLANCOUS/  camouflage 
^OMAC.HMEAV.  TOOLS/'  MATERIALS 


LUMBER 


FORTIFICATION  SUPPLIES 


//ROAD  CONSTRUCTION, 
'ANO  MISCELLANEOUS^ 


FORTIFICATION  SUPPLIES 


EXPANSION 
AREA  NO.3 


EXPANSION  AREA  NO.  2 


ROAD  METAL 


FORTIFICATION  SUPPLIES 

SANOSACS,  IRON.  TOOLS.  HA* 0 WARE.  PICKETS, 
WIRE,  IUULS.  ROOPIN*.  ETC. 


LUMBER 


TO  THE 
REAR 


LUMBER 


LUMBER 


LEGEND 


INDICATES  OPEN  STORAGE 


INDICATES  COVERED  STORAGE 


yBARRACKI 


Figure  25. — Typical  army  engineer  depot  In  combat  zone,  showing  communications,  lay-out  of  stocks,  and  expansion  areas  (based 
on  estimated  15-day  stockage  for  army  of  3 corps  of  3 square  divisions  each);  minimum  operating  iorce,  1 depot  company. 


BASE 

DEPOT 


NOTES 


STAFF  CO-ORDINATION  NOT  SHOWN  • 
SUPPLY  BY  CORPS  WHEN  DETACHED 
FROM  ARMY  SAME  AS  ARMY  , 


LEGEND 


REQUISITIONS 

SUPPLIES 

CALL  AGAINST  ESTABLISHED 
CREDITS;  REQUISITION  NOT 
REQUIRED 


figure  24. — Engineer  supply;  normal  routing  of  requisi- 
tions and  forwarding  of  engineer  supplies  in  theater 
of  operations. 


282736°— 41  (Face  p.  28) 


REFERENCE  DATA 


18-19 


Section  IV 

FORMS  AND  ORDERS 

■ 18.  Form  for  Intelligence  Plan. 

INTELLIGENCE  PLAN 
Period: 

Essential  elements  of  enemyHnformation  (as  announced  by  division 
headquarters) . 

1.  

2.  


3.  - 


■ 19.  Form  for  Reconnaissance  Instructions. — In  the  fol- 
lowing form,  check  numbered  items  on  which  information  is 
desired,  and  use  the  blank  right  hand  column  for  additional 
instructions,  listed  a,  b,  c,  etc. 

282736“— 41 3 29 


A 


19 


CORPS  OF  ENGINEERS 
RECONNAISSANCE  INSTRUCTIONS 


No. (Organization) 

(Place) 

Maps: 

(Date  and  hour) 

Reconnoiter  and  report  information i as  indi- 
cated txdow  by  items  checked  (»).  Re- 
port also  any  other  information  of  tech- 
nical importance  incidentally  secured. 

SPECIAL  INSTRUCTIONS 
Areas  ami  roads  to  be  reconnoitcred  in 
connection  with  missions  ordered. 
Hour  and  destination  of  reports. 

1.  GENERAL  FEATURES  (complete 

report  with  particular  attention  to 
other  items  checked). 

2.  ADVERSE  ENGINEER  SITUA- 

TION IN  CONNECTION  WITH 
ATTACHED  UNIT  (column  delay- 
ed, insufficient  engineers  attached, 
insufficient  supplies,  etc.). 

8.  AVENUES  OF  APPROACH. 

4.  BRIDGES. 

6.  CAMP  SITES  (suitable  for  a battalion 
or  larger  unit.  Give  details  on  avail- 


ability of  wood,  water,  cover). 

6.  COVER  (suitable  for  reserve  position 

for  battalion  or  large  unit.  Generally 
suitable  for  camouflage  of  activities). 

7.  DEFENSIVE  POSITIONS. 

8.  DEMOLITIONS  BY  ENEMY  (de- 

tails, labor,  materials,  and  time  neces- 
sary to  repair). 

9.  ERRORS  IN  EXISTING  MAPS. 

10.  FIELDS  OF  FIRE. 

11.  MATERIALS  AND  PLANT. 

12.  OBSERVATION. 

13.  OBSTACLES  TO  OUR  MOVE- 

MENT (natural  and  artificial). 

14.  OBSTACLES  TO  ENEMY  MOVE- 

MENT (suitable  points). 

15.  RAILROADS. 

16.  ROADS. 

17.  STREAMS  (width,  depth,  fords,  fer- 

ries, navigability,  condition  of  banks 
and  approaches). 

18.  UTILITIES  (garages,  machine  shops, 

electric  plants,  water-supply  plants, 
gas  systems). 

19.  WATERWAYS. 

By  order  of 


(Signature) 

(Grade  and  organization) 

30 


REFERENCE  DATA 


20 


■ 20.  Forms  for  Reconnaissance  Reports. — a.  General  recon- 
naissance. 

ENGINEER  RECONNAISSANCE  REPORT 
General  features 


Date Party. 

1.  Route  followed 

2.  Roads  traveled: 


From— 

To— 

Type 

Width 

Condition 

3.  Obstacles  encountered  on  roads  (list  in  order  met  and  describe 

briefly.  Indicate  materials  available  locally  for  passing  each) 

4.  Streams  crossed: 


Name 

Width 

Capacit  y of 
bridge 

Width  of 
bridge 

5.  Telephone  lines. 


From — 

To- 

Number  of 
wires 

Condition 

6.  Towns. 


Name 

Approximate 

population 

W i 

E » 

O * 



7.  Road  materials. 


Located  at — 

Kind  and  quantity 

1 Indicate  serviceability  of  water,  electric,  and  gas  systems. 


31 


20 


CORPS  OF  ENGINEERS 


8.  Camp  sites  at  which  fuel  and  water  are  available. 


9.  Feasible  points  on  roads  or  railroads  for  creating  obstacles. 


Location 

Type  of  ob- 
stacle 

Estimate  of 
explosive  re- 
quired 

1 1 

10.  Additional  information2. 


(Signature) 


(Grade) 

b.  Construction  materials  and  equipment. 

ENGINEEF  RECONNAISSANCE  REPORT 

Construction  materials  and  equipment 

Date Party 

Map  reference 

1.  Area  covered  by  reconnaissance 


2.  Standing  timber: 

General  location  if  plentiful 

Specific  location  if  scarce 

Range  of  sizes 

Accessibility  from  roads 

3.  Lumber  yards. 


Locat  ion 

Quantities 

Cutting 

machinery 

2 Indicate  good  defensive  positions,  location  of  enemy  lines,  navi- 
gability of  streams,  fords,  ferries,  railroad  sites,  condition  of  railroads, 
and  rolling  stock,  etc. 


32 


REFERENCE  DATA 


20 


4.  Hardware  stores. 

Location 

General  description  of  stock 

5.  Gravel  pits. 


Location 

Machinery  at 
pit 

Daily  capacity 

6.  Quarries. 


Location 

Crushing  ma- 
chinery 

Daily  capacity 

j 

7.  Brickyards  (location) 

8.  Road  machinery. 


Location 

Number 

Plows 

Scrapers 

Rollers 

Concrete  mixers 

Miscellaneous. 



33 


20-21 


CORPS  OF  ENGINEERS 


9.  Pile  drivers  (location) 

10.  Barbed  wire. 


Location 

Approximate 

quantity 

11.  Additional  material  or  equipment 

12.  Remarks 

(Signature) 

(Grade) 

c.  Roads,  bridges,  water  supply,  etc. — See  sections  I,  II,  and 
V,  chapter  2. 

■ 21.  Engineer  Situation  Report. — The  following  example 
may  be  used  as  a guide  in  reporting  an  engineer  situation. 
Appropriate  entries  should  be  made  under  applicable  head- 
ings or  different  headings  substituted. 


22 


CORPS  OF  ENGINEERS 


■ 22.  Illustrative  Orders. — The  following  orders  are  sam- 
ples of  orders  issued  by  various  types  of  engineer  units.  They 
are  intended  to  illustrate  form  and  subject  matter  only  and 
must  not  be  taken  as  tactical  models.  Coordinates  of  places 
are  indicated  by  parentheses  ( ) after  the  name.  For 

general  instructions  concerning  combat  orders,  see  FM  101-6 
(SOFM) . 


35 


Illustrative  order  No.  1 

FIELD  ORDER  FOR  A COMBAT  REGIMENT  ENGAGED 
ON  ENGINEER  DUTIES 


5th  Engrs 

RJ  599-D,  near  WHITEHALL,  PA  ( ) 

16  June  19—,  11:00  PM 

FO  23 

Maps:  Topographical  Map,  Gettysburg-Antietam,  1:21,  120;  New  Ox- 
ford, Abbotstown,  Hanover,  Bonneville,  Taneytown,  and 
Kingsdale  sheets. 

1.  a.  The  enemy  on  our  front  occupies  a position  along  the 

general  line  IRISHTOWN  ( )— NEW  OXFORD 

( ) . Our  attack  of  this  date  forced  his  withdrawal 

for  a distance  of  about  2 miles  on  the  left  of  our 
division  front. 

b.  Our  division,  in  conjunction  with  the  rest  of  the  First 

Army,  resumes  the  attack  at  4:00  AM,  17  June;  9th 
Brig  on  the  left,  10th  Brig  on  the  right.  For  details 
of  operations,  etc.,  see  Annex  No  1. 

2.  This  regiment  will  assist  the  attack  by  maintaining  the 

routes  of  communication  and  assisting  the  forward 
movement  of  the  artillery. 

3.  a.  The  1st  Bn  (less  Co  C)  will  repair  and  maintain  roads 

and  bridges  in  rear  of  the  9th  Brig. 

5.  Co  C is  attached  to  the  5th  FA  Brig,  effective  at  4:00  AM, 
17  June.  The  CO,  Co  C,  will  report  to  the  CG,  5th 
FA  Brig,  prior  to  midnight  16-17  June,  for  instruc- 
tions. 

c.  The  2d  Bn  will  maintain  roads  in  the  10th  Brig  zone 

of  action,  and  will  complete  the  trestle  bridge  across 
SOUTH  BRANCH  CONEWAGO  CREEK  near  RJ 
500-A  ( ). 

d.  (1)  Hq  and  Serv  Co  with  the  band  attached,  will  con- 

tinue to  operate  from  its  present  location.  The 
CO,  Hq  and  Serv  Co,  will  provide  for  an  adequate 
supply  of  road  materials  north  of  SOUTH 
BRANCH  CONEWAGO  CREEK. 


36 


REFERENCE  DATA 


22 


(2)  The  Div  Engr  Sec  and  Lighting  Plant  will  continue 

to  operate  with  the  Fwd  Ech  DHQ. 

(3)  The  gravel  pit  and  water  supply  point  will  remain 

in  operation  in  present  location. 
x.  (1)  Priority  of  road  maintenance  will  be  given  to  the 
division  main  supply  road  and  to  those  roads 
shown  on  overlay  No  2,  “Road  Circulation  Plan.” 

4.  a.  Supply.  

(1)  Class  I railhead:  UTTLESTOWN  ( ).— Rail- 

head distribution  at  10 : 00  PM. 

(2)  Ammunition  railhead:  LITTLESTOWN. 

(3)  Engineer. 

Army  depot:  TANEYTOWN  ( ). 

Div.  DP:  RJ  599-D  ( ). 

b.  Aid  Sta:  RJ  599-D.  Evacuation  through  Coll  Stat  at 

CR  633  ( ). 

c.  For  other  administrative  details  see  Adm  O No.  8. 

5.  Command  posts  and  axes  signal  communication. 

5th  Div:  SMALL  ( ) —GEO  LAWRENCE  ( ). 

5th  Engrs:  RJ  599-D— IRISHTOWN  ( ) . 

Hq  and  Serv  Co:  RJ  599-D. 

1st  Bn:  RJ  559-G  ( ). 

2d  Bn:  REBERT  ( ). 

5th  FA  Brig:  VALLEY  SCHOOL  ( ). 

G 

Colonel 

Annex:  No.  1,  G-3  Information. 

Distribution:  A,  and  5th  FA  Brig. 


37 


22 


CORPS  OF  ENGINEERS 


Illustrative  order  No.  2 

FIELD  ORDER  FOR  A COMBAT  REGIMENT  IN  COMBAT 
AS  RIFLEMEN 


3d  Engrs 

WHITE  FARM,  PA  ( ) 

3 Aug  19  — , 1:30  PM 

FO  17 

Maps:  Topograpical  Map,  Gettysburg-Antietam.  1:21,120;  Hunters- 
town — Arendtsvllle  sheets. 

1.  a.  The  enemy  still  occupies  the  observation  station  on  hill 

339  ( ) on  the  right  boundary  of  the  zone  of  ac- 

tion of  the  5th  (left)  Brig. 

b.  Our  division  continues  the  attack  extending  the  zone  of 

action  of  the  5th  Brig  to  the  left  to  include  hill  242 
( ).  1st  Bn,  4th  Inf  is  on  the  right  of  the  5th 

Brig.  2d  Bn,  30th  Inf  is  on  the  left  of  the  6th 
Brig.  1st  Bn,  10th  FA  from  positions  near  SMITH 
S H ( ) supports  operations  in  the  area  includ- 

ing hill  339. 

2.  This  regiment  (less  1st  Plat,  Co  E)  will  seize  and  hold  the 

observation  station  on  hill  339. 

Formation:  column  of  battalions.  LD  and  boundaries 
(see  Opn  overlay) . 

3.  a.  The  1st  Bn  will  clear  WHITE  FARM  and  will  attack 

at  2:00  PM  in  the  direction  RJ  225  ( )— hill  339 

(see  Opn  overlay). 

6.  The  2d  Bn  (less  1st  Plat,  Co  E)  will  await  orders  in 
regimental  reserve  in  vicinity  of  RJ  225. 

c.  The  1st  Plat,  Co  E,  with  three  Hq  and  Serv  Co  trucks 

attached,  will  continue  maintenance  of  the  division 
main  supply  road  extending  its  operations  to  include 
COOKTOWN  and  RJ  243  ( ). 

d.  The  Rr  Ech  will  await  orders  at  WHITE  FARM. 

4.  a.  Am  dump,  RJ  225.  S-4  will  obtain  extra  ammunition 

by  truck  from  LAWTON  ( ) . 

b.  All  vehicles  will  be  held  mobile  and  under  cover  in  as- 

sembly positions  near  WHITE  FARM. 

c.  Aid  Sta:  Initial  location,  SW  of  RJ  225. 

d.  Other  details,  no  change. 

38 


fl 


REFERENCE  DATA 


22 


5.  Command  posts  and  axes  signal  communication. 

3d  Engrs:  WHITE  FARM — RJ  225 — RJ  282  ( ) — 

hill  339. 

Rr  Ech:  WHITE  FARM. 

1st  Bn:  RJ  282. 

2d  Bn:  RJ  225. 

1st  Plat,  Co  E:  HOLT  ( ). 

1st  Bn,  10th  FA:  SMITH  S H. 

4th  Inf:  LAND  CR  ( ). 

30th  Inf:  MERRITT  S H ( ). 

A 

Colonel 

Annex:  Opn  overlay. 

Distribution:  A,  and  to  CO’s  4th  Inf,  30th  Inf,  and  1st  Bn, 
10th  FA. 

Illustrative  order  No.  3 

ENGINEER  PARAGRAPH  IN  A DIVISION  ATTACK 
ORDER 

X X X X 

3.  /.  The  1st  Engrs.  (less  Dets)  will  be  prepared  to  assemble 
at  CR  725  ( ) on  2 hours’  notice  for  use  in  division 

reserve. 


39 


CORPS  OF  ENGINEERS 


9 

i 

i 

i 


G3  | 

d) 


? 

? i 

+ PLATOON  COMMANDER  | 

O FOLLOWS  SCOUTS 
IN  ADVANCE  \ 


• o 

MESSENGER  | 


LEADING  ECHELON  j 
(MAY  BE  I,  2 or  3 SQUADS) 
l I 


SCOUTS 
PRECEDE 
THE  AOVANCE 


| ENOUGH  TO 
, PROTECT  FROM 
j MIDRANGE 
I ENEMY  FIRE 


a i 


□ 


6s, 


0 


a 


□ 


□ 


SOUAO  WEDGE  ON  I 

BROKEN  GROUND  W/ COVER 

0 


SOUAO  AS  SKIRMISHERS 
ON  OPEN  AREAS 


OBSERVES 
TO  RIGHT 


OBSERVES  / 
* TO  LEFT  / 


PLATOON  SERGEANT 
CONTROLS  SUPPORT 


□ 

□ 


a 

□ 

a 

a 


□ 


SUPPORT  ECHFLON 
(MAY  BE  I or  2 S QUA  OS) 
SOUAO  COLUMN  PREPAREO 
FOR  ACTION  TO  LEFT  FLANK 
OR  REINFORCE  LEADING 
ECHELON.  MAY  BE  USEO  FOR 
ENVELOPMENT  OR  FILLING 
GAPS  TO  FRONT. 

I 


V1N  REAR  OF 
LEAOING  ECHELON 
OURING  ATTACK 


FRONTAGE  IOO-  200  YDS 
SCHEMATIC  ONLY 
NOT  TO  ANY  SCALE 
DISTANCES  VARIABLE 


] MESSENGER 
TO  COMPANY 
COMMANDER 


13  PLATOON  NCO 
OBSERVES  TO 
_ J FLANKS  AND  REAR 


VEHICLES  IN  REAR 
WITH  Co.  Rr.  Eeh. 


Figure  26. — Disposition  of  an  engineer  (3-squad)  platoon  in  an 
attack  as  riflemen. 


40 


REFERENCE  DATA 


22 


Illustrative  order  No.  4 

FIELD  ORDER  FOR  A GENERAL  SERVICE  REGIMENT 
WITH  A CORPS 


350th  Engrs 
FAIRFAX,  VA  ( ) 

FO  38  5 Oct  19—,  1:00  PM 

Map:  USGS,  1:125,000;  Mt.  Vernon  quadrangle. 

1.  a.  The  enemy  opposes  Cur  army  on  the  general  line 

WOODBRIDGE  ( )— MANASSAS  ( ). 

b.  Our  army  continues  its  preparations  for  the  attack. 

The  n Corps  prepares  to  attack  in  the  general  direc- 
tion HOLMES  ( ) — MARTINDALE  ( ).  For 

details  see  FO  No  36,  350th  Engrs.  Effective  5 : 00  AM 
6 Oct  the  corps  rear  boundary  is  advanced  to 
HILL  ( )— SEATON  ( )— RJ  258  ( ) (all 

incl)  and  the  divisional  rear  boundary  is  advanced  to 
the  BARR  ( )— HOLMES  ( ) —SMITHSON 

( ) road  (all  excl). 

c.  Army  engineer  troops  take  over  engineer  operations  in 

rear  of  HILL— SEATON— RJ  258  (all  excl)  by  1:00 
PM  6 Oct.  The  351st  Engrs  (Gen  Serv) , First  Army 
take  over  the  area  work  from  the  350th  Engrs.  The 
P RR  (HOYT  ( )— ALMER  ( )— WILTON 

( ))  is  taken  over  by  the  army  for  operation  at 

8:00  PM  today.  For  disposition  of  engineer  troops 
in  H Corps,  effective  5:00  AM  6 Oct  see  Annex  No.  1, 
Engineer  situation  map. 

2.  This  regiment,  with  413th  Engrs  (Sep  Bn)  attached, 

effective  5:00  AM  6 Oct,  will  execute  general  engineer 
work  in  that  portion  of  the  corps  zone  of  action  west  of 
HOLMES— HOLT— WILTON— SEATON  (all  Incl)  and 
will  extend  the  P RR  from  ALMER  JUNCTION  to 
HOLMES. 

3.  a.  The  1st  Bn  (less  Co  A) , with  Co  D,  413th  Engrs  attached, 

will  repair  the  P RR  from to 

b.  The  2d  Bn  (less  Cos  E and  F) , with  Co  C,  413th  Engrs  at- 
tached, will  continue  general  engineer  work  in  its 
present  area. 

41 


22 


CORPS  OF  ENGINEERS 


c.  The  413th  Engrs  (less  Cos  C and  D) , with  Co  A,  1st  Bn, 

350th  Engrs  attached,  will  continue  maintenance  of 
the!  corps  main  supply  road  WHITE  ( ) — HOLT — 

HOLMES  and  will  extend  their  operations  to  in- 
clude HOLMES. 

d.  Co  E will  take  over  general  engineer  operations  in  that 

portion  of  the  corps  zone  of  action  to  be  vacated  by 
the  3d  Div. 

e.  Co  F will  take  over  general  engineer  operations  in  that 

portion  of  the  corps  zone  of  action  to  be  vacated  by 
the  2d  Div. 

/.  Hq  and  Serv  Co  will  operate  from  ALMER.  Detach- 
ments and  equipment  with  units  of  regiment  will 
remain  unchanged. 

g.  The  band  will  remain  attached  to  the  supply  section  of 
Hq  and  Serv  Co. 

x.  (1)  Reconnaissance  of  new  areas  will  be  initiated  at 
once. 

(2)  Troop  movements  will  be  effected  after  7:00  PM 

tonight. 

(3)  For  schedule  of  engineer  work  and  priorities  and 

distribution  of  regimental  and  special  equipment 
see  Annex  No.  2,  Engineer  work. 

4.  a.  Supply. 

(1)  Class  I railhead:  ALMER  JUNCTION  ( ).  S-4 

will  draw  for  the  regiment  and  attached  troops 
at  10:00  PM. 

(2)  Engineer. 

Army  depot:  ALEXANDRIA  ( ). 

Regimental  supply  point:  ALMER. 

b.  Evacuation. 

(1)  Aid  Sta. 

350th  Engrs:  ALMER. 

413th  Engrs:  HOLT. 

(2)  Casualties  by  truck  or  ambulance  to  ALMER. 

c.  For  other  administrative  details  see  Annex  No.  3,  Ex- 

tracts Adm  O No  25,  n Corps. 


42 


reference  data 


22 


5.  Command  posts. 

a.  Engineers. 

350th  Engrs:  ALMER  after  9:00  PM. 

1st  Bn:  ALMER  JUNCTION. 

2d  Bn:  WHITE. 

413th  Engrs:  HOLT  after  5:00  AM  6 Oct. 

Co  E,  350th  Engrs:  RJ  350  ( ) after  5:00  AM 

6 Oct. 

Co  F,  350th  Engrs:  CR  400  ( ) after  5:00  AM 

6 Oct. 

b.  For  command  posts  of  other  engineer  units  and  corps 

and  divisional  troops  see  Annex  No.  4,  Command  posts. 

L 

Colonel 

Annexes: 

No.  1,  Engineer  situation  map. 

No.  2,  Engineer  work. 

No.  3,  Extracts  Adm  O No  25,  n Corps. 

No.  4,  Command  posts. 

Distribution:  A. 


43 


22 


CORPS  OF  ENGINEERS 


Illustrative  order  No.  5 

FIELD  ORDER  FOR  A WATER  SUPPLY  BATTALION 

76th  Engrs  (W  Sup) 
VIVA.  TEX  ( ) 

P0  9 25  May  19 — ,4:00  PM 

Maps:  USGS  1 : 125,000;  Alton,  Millis,  and  Waverly  quadrangles. 

1.  a.  No  important  changes  in  the  enemy  situation. 

b.  Our  army  continues  its  preparation  for  the  attack. 

c.  The  water  supply  in  the  LEWIS  PLATS  area  (ALUS 

( )— BOND  ( )— COLBY  ( )— DEVON 

( ) (all  incl))  must  be  supplemented  by  water 

transported  in  motor  vehicles.  Pour  tank  cars  are  to 
be  spotted  at  OLGA  ( ) siding  at  8:00  PM  and  8:00 

AM  daily,  commencing  26  May.  Purification  sections 
of  Serv  Plat,  Hq  and  Serv  Co,  are  attached  to  corps  as 
follows:  to  I Corps  two  sections  and  to  II  Corps  two 
sections.  Engineer  troops  are  in  charge  of  general 
engineer  work  in  the  LEWIS  FLATS  area  as  follows: 
north  of  LEWIS  ( )— WATSON  ( ) road 

(excl) , m Corps  ; south  of  LEWIS— WATSON  road 
(incl)  and  west  of  AUSTIN  CREEK  ( ) and  MILL 

GULCH  ( ),  21st  Engrs  (Gen  Serv)  First  Army: 

south  of  LEWIS — WATSON  road  (incl)  and  east  of 
AUSTIN  CREEK  and  MILL  GULCH,  60th  Engrs  (Sep 
Bn)  First  Army. 

2.  This  battalion  (less  dets)  will  transport  water  in  the  LEWIS 

FLATS  area  and  will  assist  in  the  establishment  and 
maintenance  of  water  DP’s. 

3.  a.  Co  A,  with  one  purification  sec  Hq  and  Serv  Co  attached. 

will  report  to  the  CG  III  Corps  for  operation  in  that 
portion  of  the  LEWIS  FLATS  area  within  the  corps 
zone  of  action.  Clearing  VIVA  ( ) by  7:00  PM,  it 

will  march  via  ELLSWORTH  ( ) —COLBY  road  to 

LESLIE  ( ) where  it  will  pass  to  the  control  of  the 

in  Corps.  It  will  revert  to  battalion  control  when 
the  corps  rear  boundary  is  advanced  to  exclude  the 
general  line  COLBY— DEVON. 

b.  Co  B will  operate  from  OLGA  and  transport  water  to 
water  DP’s  in  the  area  ALLIS — BOND — JONES  FARM 
( )— BOWIE  ( ) (all  incl). 

44 


REFERENCE  DATA 


22 


c.  Co  C will  operate  from  OLGA  and  transport  water  to 

water  DP’s  in  the  area  LEWIS — WATSON  road 
(incl)— JONES  FARM— BOWIE  (both  excl). 

d.  Hq  and  Hq  and  Serv  Co  (less  dets)  will  operate  from 

OLGA.  Storage  facilities  will  be  established  at  OLGA. 

e.  Water  analysis  dets  will  report  to  CO’s  of  Cos  B,  and  C. 
x.  (1)  The  battalion  (less  Co  A and  dets)  will  clear  VIVA 

by  8:00  PM  and  will  march  via  RJ  248  ( ) to 

OLGA.  Order  of  march:  Hq,  Co  B,  Co  C,  Hq  and 
Serv  Co,  Med  Det. 

(2)  Reconnaissance  of  area  will  be  initiated  at  once  and 
detailed  plans  of  operation  submitted  by  7:00  AM 
26  May. 

4.  a.  Supply. 

(1)  Class  I. 

Rhd:  OLGA  after  4:00  AM  26  May. 

Bn  (less  Co  A and  Dets) : OLGA  10:00  AM. 

Co  A:  through  III  Corps. 

(2)  Engineer. 

Army  depot:  LAWRENCE  ( ). 

Army  shop:  LAWRENCE. 

Bn  Sup  Pt:  OLGA  after  5:00  AM  26  May. 
b.  Aid  Sta:  OLGA  after  5:00  AM  26  May. 

Evacuation  via  Coll  Sta:  OLGA  after  4:00  AM  26  May. 
Medical  mobile  laboratories:  WESTON  ( ) — 

HOGAN  ( ). 

Army  medical  laboratory:  WHEATON  ( ). 

Other  administrative  details:  No  change. 

5.  Command  posts. 

Bn:  OLGA  after  5:00  AM  26  May. 

Co  B:  Same. 

Co  C:  Same. 

Co  A:  through  Engr  Hq  III  Corps  at  HORTON  ( ). 

Army  Engr  Hq:  WHEATON. 

Army  Med  Hq:  WHEATON. 

21st  Engrs:  HOLLY  ( ). 

60th  Engrs:  WILBUR  ( ) . 

W 

Major 

Distribution:  A,  and  21st  and  60th  Engrs. 


282736°— 41- 


45 


22 


CORPS  OF  ENGINEERS 
Illustrative  order  No.  6 

ENGINEER  PARAGRAPHS  IN  A DIVISION 
ADMINISTRATIVE  ORDER 

1st  Div 

Adm  C 12  MILTON,  MD<  > 

2 Aug  19 — , 4:00  PM 

Maps:  Topographical  Map.  Gettysburg-Antietam.  1:21,120;  Emmits- 
burg,  Taneytown  and  Kinsdale  sheets. 

1.  SUPPLY. 

a.  

b.  Class  I: 

Rhd:  GALT  ( ) effective  8:00  PM  4 June. 

1st  Engs:  9:00  PM. 



d.  Water.  , . __ 

(1)  DP’s:  LEWIS  FARM  ( ),  AKRON  ( ).  KJ 

694  ( ). 

(2)  All  water  for  drinking  will  be  chlorinated. 

e.  Engineer. 

(1)  Rhd:  PINEY  CREEK  ( ). 

(2)  DP  commencing  3 June:  CR  626  C ). 



2.  EVACUATION. 

a. 





d.  Captured  material. 

(1) 

— 

(3)  Engineer  materials  will  be  taken  over  by  1st  Engrs 

and  utilized  for  divisional  work. 

3.  TRAFFIC. 

a.  Circulation. 

(1)  See  Annex  No.  3— Circulation  Map,  effective  6:  00 

AM  4 June. 

(2)  Control.  . ...... 

(a)  Traffic  control  posts  will  be  maintained  at 

GALT,  CR  469  ( ) , TANEYTOWN  ( ) . 

WHITE  MILL  ( ) and  DASHERS  MILL 

( ),  and  at  such  temporary  detours  as 

may  be  established. 

46 


L 


. 


REFERENCE  DATA  22 

(b)  Traffic  priority:  Ammunition  vehicles,  en- 
gineer vehicles,  ration  vehicles, 
b.  Construction  and  maintenance  of  routes. 

(1)  Division  main  supply  road:  WESTMINSTER  ( ) — 

TANEYTOWN  — BRIDGEPORT  ( ) — two- 

track. 

(2)  GALT— CR  538  ( )— TANEYTOWN  road  will  be 

will  be  maintained  for  motor  traffic — two-track. 

(3)  RJ  438  ( ) to  RJ  490  ( ) road  (south  of 

TANEYTOWN)  will  be  maintained  for  motor  traf- 
fic— one-track. 

(4)  All  crossings  over  PINEY  CREEK  will  be  maintained. 

(5)  Signs  will  be  posted  indicating  direction  of  traffic  as 

shown  on  circulation  map. 

4.  TRAINS. 


d.  1st  Engrs:  RJ  626  ( 
5.  PERSONNEL. 


) released. 


6.  MISCELLANEOUS. 


c.  For  employment  of  engineer  troops  see  Annex  No  7,  Engi- 

neer plan. 

d.  


By  COMMAND  OF  MAJOR  GENERAL  A: 


Official: 

Y 

AC  of  S,  G-4 
Annexes: 

No  3,  Circulation  map. 
No  7,  Engineer  plan. 


X 

Chief  of  Staff 


47 


22 


CORPS  OF  ENGINEERS 


Illustrative  order  No.  7 

ENGINEER  ANNEX  TO  A DIVISION  ADMINISTRATIVE 

ORDER 


ANNEX  NO  7 TO  ADMINISTRATIVE  ORDERS  NO  18 
1st  Division 
Engineer  Plan 

1st  Div 

MILTON,  MD  ( ) 

2 Aug  19 — , 4:00  PM 

Maps:  Gettysburg-Antietam.  1:21.120,  Taneytown  and  Kingsdale 
sheets. 

1 ROADS  AND  BRIDGES. 

a Priority  will  be  given  the  following  work: 

' Maintenance  of  ALTON  TURNPIKE  ( ) as  two- 

track  divisional  main  supply  road.  ^ „_A 

Maintenance  of  HOLT  ( >-CR  590  ( )-SEA* 
TON  ( ) road  as  two-track  road  for  corps  loads. 

Repair  and  maintenance  of  CR  590— RJ  600  ( ) 

road  as  one-track  motor  road  for  divisional  loads. 
Maintenance  of  roads  in  immediate  vicinity  of  railhead 
and  engineer  distributing  point, 
b Other  roads  indicated  on  circulation  map  will  be  main- 
tained for  light  motor  transport  only, 

c.  Road  and  traffic  signs  will  be  supplied  for  road  system 
and  all  temporary  detours. 

a.  All  bridges  over  MARSH  CREEK  ( ' will  be  main- 

e TraffiTcontrol  on  temporary  detours  will  be  under  the 
engineers  until  it  can  be  taken  over  by  the  military 

police. 

2 WATER  SUPPLY. 

a.  Following  water  supply  points  for  drinking  water  wll  be 
operated  by  the  engineers  commencing  5:00  AM  3 

Aiig 

AKRON  ( ) • two  2,000-gallon  tanks  operated  by 

divisional  pumping  set. 

48 


REFERENCE  DATA 


22 


SMITH  FARM  ( ),  LEWIS  S H ( ),  and 

RJ  430  ( ) : each  a 3,000-gallon  canvas  tank. 

b.  Distribution  of  water  will  be  controlled  by  the  division 

engineer. 

c.  All  water  sources  will  be  marked  with  signs  in  accord- 

ance with  GO  8. 

3.  ENGINEER  SUPPLY. 

a.  Supply  points. 

Army  depot:  SMITHTOWN  ( ). 

Division  distributing  point:  RJ  438  ( ). 

b.  Local  and  captured  engineer  material  will  be  taken 

over  for  divisional  use. 

c.  Intrenching  tools  for  divisional  troops  will  be  delivered 

to  regiments  upon  request  of  commanders. 

d.  Dumps  of  engineer  material  in  division  area  will  be 

taken  over  by  the  corps  as  the  advance  progresses. 

e.  No  changes  in  methods  of  Issue. 

4.  MISCELLANEOUS. 

a.  5 KW  set  will  accompany  the  Fwd  Ech  of  Div  Hq.  The 

local  plant  at  EIBERT  ( ) will  be  operated  for 

the  Rr  Ech  of  Div  Hq. 

b.  Map  section  will  operate  from  RJ  438  after  9:00  PM  2 

Aug. 

5.  ENGINEER  TROOPS. 

a.  1st  Bn  1st  Engrs  (less  Co  A)  with  command  post  at  CR 

500  ( ) will  be  in  charge  of  general  engineer  work 

in  the  area  north  of  line:  CR  590  ( ) — WOOD 

( ) (both  excl.). 

b.  2d  Bn  1st  Engrs,  with  Co  A attached,  with  command 

post  at  CR  480  ( ) on  ALTON  TURNPIKE  will  be 

in  charge  of  general  engineer  work  in  the  area  south 
of  line:  CR  590— WOOD  (both  incl.) . 

c.  Div  Engr  Sec  accompanies  the  Fwd  Ech  of  Div  Hq. 

d.  Command  post,  1st  Engrs:  RJ  438. 

By  command  of  Major  General  A: 

X 

Chief  of  Staff 

Official: 

Y 

AC  of  S,  G~4 

Distribution:  Same  as  Adm  O No  18. 


49 


CHAPTER  2 

COMMUNICATIONS.  CONSTRUCTION.  AND  UTILITIES 

Section  I.  Roads 

II.  Bridges  and  stream  crossings 

m.  Railways  

IV.  Construction  in  war 

V.  Water  supply 

VI.  Electricity 

VII.  Rigging 

VIII.  Concrete 

Section  I 
ROADS 

■ 23.  Traffic  Capacity.— The  maximum  capacity  of  a single 
road  lane  is  obtained  when  vehicles  move  about  33  miles  per 
hour.  However,  for  all  practical  purposes  the  capacity  re- 
mains constant  for  speeds  from  25  to  45  miles  per  hour.  At 
these  speeds  the  normal  capacity  of  a single  traffic  lane  car- 
rying military  vehicles  only  is  about  750  vehicles  per  hour. 

At  bottlenecks  this  may  be  increased  by  cutting  the  distance 
between  vehicles  to  about  one-third  of  that  for  open  high- 
way driving.  This  ultimate  capacity,  with  speeds  of  25  to  35 
miles  per  hour,  is  about  2,000  vehicles  per  hour.  At  night  the 
ultimate  capacity  at  15  miles  per  hour  is  about  1,200  vehicles 
per  hour. 

■ 24.  Minimum  Design  Requirements. — a.  Width. — 9 feet  per 
lane;  10  feet  desirable  (4  feet  for  trails  used  by  foot  troops 
and  horse  cavalry). 

b.  Carrying  capacity. — 9,000-pound  wheel  load  on  pneu- 
matic tires. 

c.  Grades. — Not  more  than  10  percent  for  motor  traffic. 

d.  Curves. — Radii  greater  than  150  feet  (otherwise  addi- 
tional width  should  be  provided) . 

e.  Overhead  clearance. — 11  feet;  14  feet  desirable. 

■ 25.  Traffic  Signs.— These  are  needed  to  mark  the  location 
of,  or  direction  to,  military  installations,  crossroads,  geograph- 
ical points,  etc.  Letters  should  be  of  the  following  sizes: 

a.  For  roads  traveled  only  by  foot  troops. — 4 inches  high. 

50 

L 


Paragraphs 

23-31 

32-54 

55-56 

57-62 

63-72 

73-77 

78-82 

83-87 


REFERENCE  DATA 


25-27 


b.  For  main  roads. — 4 inches  high  (sign  should  be  not  less 
than  17  by  17  inches,  and  at  least  4 feet  above  the  road 
crown) . 

■ 26.  Form  for  Road  Reconnaissance. 

REPORT  OF  ROAD  RECONNAISSANCE 

1.  Road  reported  upon 

(Name  or  designation  of  road  and  points 


between  which  inspection  was  made) 

2.  Date  of  reconnaissance 

3.  Character  of  road 

(Concrete,  macadam,  gravel,  earth,  etc.) 

4.  Thickness  of  pavement 

(Indicate  if  estimated) 

6.  Usable  width 

(Also  indicate  whether  one,  two,  or  more  tracks) 

6.  Limiting  grades 

7.  Bridges  and  culverts. 


Location 

Dimensions 

Capacity 

Conditions 

1 

8.  Priority  and  nature  of  needed  repairs  or  Improvements. 


Location 

Work  needed 

Estimated 

man-hours 

Materials 

required 

9.  Materials  available  locally. 


Kinds  of  materials 

Location 

Quantity 

(Name,  grade,  organization) 

■ 27.  Construction  of  Military  Roads. — a.  General. — The 
basic  necessity  of  all  road  construction  is  to  provide  adequate 
drainage  (“Get  water  off  and  rock  on”) . Base  courses  should 
be  well  graded  and  compacted.  Top  course  should  be  capable 
of  resisting  the  abrasive  action  of  traffic  for  which  the  road  is 
designed.  In  general,  civil  standards  are  too  high  for  military 
roads. 

51 


REFERENCE  DATA  29 

■ 29.  Determination  of  Cross-Sectional  Area  of  Culverts. — 
Having  determined  the  drainage  area  in  acres,  the  following 
nomograph  will  give  the  necessary  area  of  cross  section  of 
culvert  to  supply  proper  drainage: 

1000  -» 

900 
900  — { 


CREEK 


CHARACTER  OF 
TERRAIN 


CULVERT 


TRIANGULAR 

DITCH 


ROLLING 


b.  Steps  in  construction.— Construction  oi  a, 

(1)  Clearing  trees,  brush,  and  vegetation  from  the  right-of- 

way. 

(2)  Grubbing  stumps  and  roots  from  the  foundation. 
(Stumps  cut  off  at  ground  level  may  be  left  if  fill  will  be  over 
1 foot  high.) 

(3)  Grading,  shaping,  and  compacting  the  subcourses. 

(4)  Laying  and  shaping  the  upper  and  top  courses. 

■ 28.  Organization  of  Maintenance  Parties.  In  general,  the 
two  methods  of  organizing  engineer  units  for  most  efficient 
maintenance  of  roads  are  as  follows: 

a Patrol — A certain  designated  section  of  road  is  assigned 
to  a small  designated  unit,  this  unit  working  as  a whole  or  in 
shifts  depending  on  the  situation.  For  continuous  mainte- 
nance, under  normal  conditions,  a combat  or  general  service 
platoon  should  be  assigned  about  5 to  10  miles  of  road  with 
trucks  to  move  men  readily  and  less  under  adverse  conditions 
b.  Gang.— A.  large  unit  goes  over  the  road  at  infrequent 
intervals  making  all  necessary  repairs.  This  method  of  or- 
ganization should  be  used  in  military  operations  only  in  cases 
nf  Viiffh  tvnp  roads  subject  to  slight  or  infrequent  damage. 


A*  AREA  Of  CULVERT  OPENING  IN  SQUARE  FEET 
C*  COEFFICIENT  DEPENDING  ON  CHARACTER  OF  TERRAfR 
0»  ORAINAGE  AREA  IN  ACRES 


EXAMPLE- THE  AREA  OF  CULVERT  FOR  A ORAINAGE  AREA 
OF  SOO  ACRES  IN  GENTLY  ROLLING  TERRAIN  (COEFFICIENT 
T*«0.4)  IS  42  SQUARE  FEET.  (SEE  DASHEO  LINE,  ABOVE) 

Figure  28. — Nomograph  based  on  Talbot's  formula. 

Note. — Culverts  should  have  slope  at  bottom  to  carry  off  flows 
and  extend  well  beyond  side  slopes  of  road  unless  elopes  are  weU 
revetted. 


30 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


30 


30.  Typical  Cross  Sections  of  Roads. 


top  COURSE  Z { TO  4-  BASE  COURSE  S“TO  6* 


GRAVEL  SUBBASE  6"T0B“-0R- FIELD  STONE  SUBBASE 
( OMIT  SUBBASE  IF  SUBGRADE  IS  GOOO  ) 

Figure  29.— Waterbound  macadam  road. 

Note. — Crown : %-  to  %-lnch  rise  per  foot.  Slope  on  shoulders: 
X Inch  per  foot. 


Note. — Have  stringers  break  joints.  Bore  %-lnch  holes  for  floor 
spikes.  Spike  planks  with  one  spike  per  stringer.  Place  pickets  at 
15-foot  centers.  Leave  gaps  in  guard  rails  for  drainage. 

Figure  31. — Single-lane  plank  road. 


/o-o- 


flooring  4-10*10 0\  z‘to3' 
"Guard  rail  CxCr  | * — 'dse 


At  least  /'O'OdoH  subgrdde 


Figure  32- 


Y^^ffiStr/ngers  4 -m'-io'-o' 

■Cross  Sleepers 4'/0*/0-<C 
Pickets  lwhen  necessary) 

® rtALr  sSccnorr 

Two-lane  plank  road  (see  note,  flg.  31). 

55 


REFERENCE  DATA 


CORPS  OF  ENGINEERS 


FLOORING:  J"T0  4"XIO”XIO'0 


Standard  lumber. 


FLOORING  2 LAYERS  2"XIO' 


Improvised  materials. 
Plank-tread  road. 


6‘ Bound  Logs  catered 
/ with  brush  earth 


Corduroy-tread  road. 


d-  6 'Hound  tags  tren- 

f r cfrtj  jnf0  ground 

Bound  Pickets 


dt  least  t'O'beloi  subgrade 


Metal-tread  road. 


Mean  6" diameter  Logs  - /II ternate  ftps  £ buffs 
Longitudinal  section. 


Sandbag-tread  road. 

Figube  34. — Types  of  tread  roads. 


30-31 


CORPS  OF  ENGINEERS 


O/d  Boat/ 


4{‘loSf wearing  1 Surface 


Figure  36. — Widening  of  old  road. 


9 

Sena  Bugs 


[E*y 


<■ 


TjtMvr* 

Q)  /7II  */e/tj4/7dd3p3 


© fill  m/h  Cr/itong 

Figure  37. — Repair  of  shell  hole. 

■ 31.  Useful  Road  Data. — a.  Formulas. — (1)  For  computing 
volumes  of  earthwork. 

i/_  (At+A,) L 
2 X27 

where 

V =volume  of  cut  or  fill  in  cubic  yards. 

4,— area  of  cross  section  at  one  end  in  square  feet. 

A- = area  of  cross  section  at  other  end  in  square  feet. 

L =distance  between  end  sections  in  feet. 

58 


■ 


REFERENCE  DATA 


31 


(2)  For  transportation  of  earth,  gravel,  or  crushed  rock. 

®=-^7xC 

d+ti 

r 


where 

Q=cubic  yards,  place  measure,  moved  per  hour. 

Z=length  of  haul  in  feet. 

C=cubic  yards  moved  per  load. 

d=minutes  during  which  vehicle  is  not  in  motion  (loading, 
unloading,  waiting). 

r=rate  of  vehicle  in  feet  per  minute  (normally  about  200 
for  animal-drawn  vehicles;  700  for  trucks). 

b.  Tables. — Add  8 percent  to  figures  in  work-capacity  tables 
to  allow  for  officers  and  noncommissioned  officers.  Add  20 
percent  to  figures  on  loose  earth,  crushed  rock,  etc.,  to  allow 
for  shrinkage  when  rolled. 


Table  n. — Man-hours  required  for  various  operations  in  road 

construction 


Operation 


Man-hours  required  for 
100  linear  yards 


(1)  Grading 

(2)  Tlacing  large  stones 

(3)  Spreading  small  stones. 

(4)  Placing  stones,  (2)+(3) 


(0 


(») 


(*) 


(0 


290 

200 

70 


270 


120 


85 


(5)  Placing  plank 

(6)  Spiking  plank 

(7)  Laying  plank  road,  (5)+(6) 


65 

30 

95 


(8)  Cutting  and  placing  corduroy 


(9)  Construction,  (l)+(4),  (l)+(7)  or  (l)+(8). 

(10)  Ditching 

(11)  Construction,  (9) +(10) 

(12)  Unloading  material 

(13)  Construction,  (11) +(12) 


560 

260 

820 

85 

905 


255 

260 

515 

40 

555 


230 

260 

490 

60 

550 


80 

165 

260 

425 


1 Macadam  road,  9 feet  wide,  12  inches  of  rock,  ditches  4.5  square  feet  cross  section. 
1 Macadam  tread  road,  2.5  feet  wide  under  each  wheel,  12  inches  of  rock,  ditches 
4.5  square  feet  cross  section. 

* Plank  road,  9 feet  wide,  ditches  4.5  square  feet  cross  section. 

* Corduroy  road,  9 feet  wide,  ditches  4.5  square  feet  cross  section. 


59 


31 


CORPS  OF  ENGINEERS 


Table  m. — Loosening,  excavating,  and  loading  earth 


Cubic  yards  per  man  per  hour 


Material 

Loosening  earth 

Excavation  with  pick  and  shovel 
to  depth  indicated  (feet) 

Loading 
trucks  or 
wagons — 
man  with 
shovel  in 
loose 
soil 

Man 

with 

pick 

Man  with 
2-horse 
plow 

0 to  3 

0 to  5 

0 to  8 

0 to  10 

2. 1 

1.8 

1.5 

1.5 

1.8 

Sandy  loam 

6.0 

60 

2.0 

1.7 

1.4 

1.3 

2.4 

1.5 

1.4 

1.2 

1.  1 

1.7 

Common  loam 

4.0 

40 

1.3 

1.2 

1.0 

1.0 

2.0 

Light  clay  

1.0 

27 

.9 

.8 

.7 

.7 

1.7 

Dry  clay.. 

1.4 

20 

.6 

.6 

.5 

.6 

1.7 

Wet  clay 

1.2 

17 

.5 

.5 

.5 

.4 

1.2 

Uardpan 

1.4 

20 

.4 

.4 

.4 

.4 

1.7 

Table  XV. — Man-hours  required  for  clearing  and  grubbing 


Man-hours  ikt  100  linear  yards 


Width  (feet) 

Light 

clearing 

Medium 
clearing  * 

Heavy 

clearing 

30 

lMO 

40-105 

105-630 

40 

14-55 

65-140 

140-840 

50 

18-70 

70-175 

175-1,050 

* In  tho  eastern  part  of  the  United  States  the  average  for  this  class  of  work  is  about 
350  man-hours  per  acre. 


60 


REFERENCE  DATA 


31 


Table  V.— Capacities  oj  various  items  of  road-construction 
equipment 


Item 


Power  shovels: 
H-yard  bucket. . 

M-yard  bucket. 

54-yard  bucket  . 

Steam  roller 


Elevating  grader: 

Small 

48-inch  belt 

Blade  grader,  7H-ton  solf- 
propelled. 


Capacity 


34  cubic  yards  per  hour  assuming  medium  soil,  good 
operator,  adequate  depth  of  cut,  no  lost  time. 

30  cubic  yards  per  hour  assuming  medium  soil  good 
operator,  adequate  depth  of  cut,  no  lost  time. 

40  cubic  yards  per  hour  assuming  medium  soil,  good 
operator,  adequate  depth  of  cut,  no  lost  time. 

e\i  cubic  yards  of  loose  rock  compacted  in  1 hour. 

25  square  yards  new  macadam  road  rolled  in  1 hour. 

50  cubic  yards  place  measure  loaded  per  hour. 

250  cubic  yards  place  measure  loaded  per  hour. 

440  square  yards  gravel  road  surface  scarified  and 
reshaped  per  hour. 

50  cubic  yards  loose  rock  or  loose  earth  spread  per 
hour. 


Table  VI. — Capacity  of  scrapers 


Slip 

Fresno 

Rotary 

Fresno 

2-wheel 

4-whcel 

Size,  cubic  yards. . . 

Under  100 

H-l 

300 

M-2M 

600 

H-io 

300-3,000 

1-12 
500-6, 000 

Economical  hauls,  feet. . 

282736' 


61 


J 


31 


CORPS  OF  ENGINEERS 


Table  VII.— Cubic  yards  per  hour  ( compact  measure)  moved  by 
60-hp.  bulldozer 


Length  of 

Rate  of  grade  in  percent 
up  hill 

Level 

Rate  of  grade  in  percent, 
down  hill 

haul  (feet) 

— 

15 

10 

5 

0 

5 

10 

15 

20 

50 

32.6 

49.0 

65.3 

81.6 

114.0 

146.0 

179.0 

212.0 

100 

20.1 

30.1 

40.2 

50.2 

70.3 

90.4 

110.5 

130.6 

150 

14.0 

21.2 

28.3 

35.3 

49.3 

63.5 

77.5 

91.8 

200 

10.9 

16.1 

21.6 

26.9 

37.7 

48.5 

59.1 

69.9 

250 

8.5 

12.9 

17.1 

21.5 

30.0 

38.6 

47.3 

55.8 

300  

7.2 

10.6 

14.2 

17.8 

24.9 

31.9 

39.1 

46.1 

350 

6.0 

9.0 

12.0 

15.0 

21.0 

26.9 

33.0 

38.9 

400 

5.2 

7.7 

10. 2 

12.9 

18.1 

23.1 

28.4 

33.5 

450  

4.5 

8.7 

8.9 

11.2 

15.7 

20.1 

24.7 

29.0 

500  

3.9 

5.8 

7.8 

9.8 

13.8 

17.6 

21.7 

25.5 

550 

3.5 

5.2 

6.9 

8.7 

12.2 

15.6 

19.2 

22.5 

600 — 

3.2 

4.6 

6.1 

7.8 

10.9 

13.9 

17.1 

20.1 

Note — For  otner  sizes  oi  duuuwkj  **  ° ’ 

0 75  lor  a 45  hp.  or  1.60  for  a 95  hp.  tractor.  (The  heavy  line  drawn 
across  each  column  indicates  the  economical  limit  of  haul.) 

Table  Vin. — Man-hours  required  for  spreading  by  hand 


Material 

Cubic  yards 
per  man-hour 

2X 

Loose  rock: 

2H 

1 

62 


REFERENCE  DATA 


31 


Table  IX. — Man-hours  required  for  effecting  emergency  passage 
of  mine  craters 


Method  of  repair 


Man-hours  required 


With  shovels  alone 

With  shovels  and  wheelbarrows  

With  shovels  and  wagons  where  distance  is  not  over 
200  yards  and  number  of  wagons  is  one-fourth  num- 
ber of  men. 

With  shovels  and  scrapers 

With  standard  bridgo  trestle  and  bents  (trained 
workmen). 

With  timbers  (trees  in  vicinity,  trained  workmen) 
Detour  of  corduroy  (corduroy  available  in  vicinity) 
Detour  of  planks 


4 X volume  in  cubic  yards. 
2 X volume  in  cubic  yards. 
2 X volume  in  cubic  yards. 


1 X volume  in  cubic  yards. 
15  X diameter  in  yards. 

fiO  X diameter  in  yards. 

18  X diameter  in  yards. 

9 X diameter  in  yards. 


Note. — Hie  volume  of  a conical  mine  crater  is: 


Where 

V= volume  of  crater  in  cubic  yards. 
,•=3.1416  (or  22/7  approx.). 

D— distance  across  top  of  crater  in  yards, 
depth  of  crater  in  yards. 


Table  X. — Cubic  yards  of  gravel  or  crushed  rock,  loose,  required 
per  100  linear  yards  of  road 


Width  of  road  (feet) 

Depth  spread  (inches) 

3 

3>/, 

4 

41* 

5 

6 

8 

9 - 

25.0 

29.2 

33.3 

37.5 

41.7 

50.0 

66.7 

10.- 

27.8 

32.4 

37.0 

41.7 

46.3 

55.5 

74.1 

18 

50.0 

58.4 

66.7 

75.0 

83.3 

100.0 

133.3 

20 

55.5 

64.8 

74.1 

83.3 

92  6 

111.1 

148.2 

Note. — Screenings  are  required  at  the  rate  of  (4  cubic  yard  for 
each  cubic  yard  of  loose  material  comprising  the  wearing  surface. 
Crushed  rock  usually  weighs  between  2,300  and  2,800  pounds  per 
cubic  yard.  Granite  weighs  2.800  pounds  per  cubic  yard  and  lime- 
stone 2.500  pounds  per  cubic  yard.  For  a water-bound  macadam 
road  10  gallons  of  water  may  be  required  per  square  yard  of 
surface.  Crushed  stone  decreases  20  percent  in  volume  when  it 
is  rolled. 


63 


31 


CORPS  OF  ENGINEERS 


Table  XI. — Materials  required  per  100  linear  yards  of  plank-tread 
road  for  motor  transportation 


Material 

Requirements  per  100 
linear  yarns 

Number  of 
pieces 

Weight 

(tons) 

180 

10 

120 

1.7 

M0 

0.12 

Note. — Leave  V4  Inch  between  edges  of  floor  plank.  Boat  spikes.  6 
inches  by  »/a  Inch,  are  driven  staggered,  one  for  each  plank  in  each 
sleeper,  in  %-inch  round  holes.  In  emergency,  naU  with  60d  wire 
nails. 


Table  XII. — Materials  required  for  single-lane  plank  road  for  motor 
transportation 


Material 

Requirements  per 
100  linear  yarns 

Number 
of  pieces 

Weight 

(tons) 

(1)  Pickets,  6 inches  X 0 inches  x 4 feet 

40 

0.8 

(2)  (iuardrail,  6 inches  X 6 inches  X 10  feet 

55 

2.8 

(3)  Flooring,  4 inches  X 10  inches  X 10  feet 

351 

19.5 

(4)  Stringers,  4 inches  X 10  inches  x 10 feet.. 

120 

6.7 

(5)  Sleepers,  4 inches  X 10  inches  X 10  feet 

75 

4.2 

220 

(7)  Floor  spikes,  6-inch 

1,404 

.3 

Note For  an  18-foot  road  all  quantities  are  doubled  except 

items  (I),  (2).  and  (6),  which  remain  as  above.  Average  weight 
of  lumber  is  40  pounds  per  cubic  foot.  Sleepers  are  used  only  when 
necessary. 


64 


REFERENCE  DATA 


31 


Table  xm. — Materials  required  for  single-lane  corduroy  road  with- 
out stringers  or  guardrails 


Material 

Requirements  per 
100  linear  yards 

Number 
of  pieces 

Weight 

(tons) 

600 

28 

Note. — Any  available  material  may  be  used.  Calculations  are 
based  on  white  oak  at  48  pounds  per  cubic  foot.  Timber  will 
generally  be  cut  alongside  road  and  transported  by  hand  or 
snaking. 

Table  XIV. — Materials  required  for  single-lane  corduroy  road  with 
stringers  and  guardrails 


Material 

Requirements  per  100 
linear  yards 

Number  of 
pieces 

Weight 

(tons) 

(1)  Stringers,  6 inches  moan  diameter,  10  feet  long 

120 

10 

(2)  Flooring,  6 inches  mean  diameter,  10  feet  long 

GOO 

28 

(3)  Guardrails,  6 inchos  mean  diameter,  10  feet  long 

55 

2.6 

(4)  Pickets,  6 inches  greatest  diameter,  4 feet  long 

40 

.6 

220 

2,400 

.9 

Note. — Any  available  material  may  be  used.  Calculations  are 
based  on  white  oak  at  48  pounds  per  cubic  foot.  Timber  will 
generally  be  cut  alongside  road  and  transported  by  hand  or  snak- 
ing. For  an  18-foot  road,  items  (1),  (2).  and  (6)  are  doubled; 
items  (3),  (4),  and  (5)  remain  as  above.  Spikes  are  Vi -inch. 


65 


31 


CORPS  OF  ENGINEERS 


Table  XV. — Man-days  and  materials  required  per  mile  for  main- 
tenance of  double-fane  macadam  road,  conditions  average 


Conditions 

Traffic 

Men 

OCT 

day 

Material 

(tons) 

3-ton 
truck - 
loads 

6 

2 

j 

12 

3 

1 

16 

16 

6 

80 

so 

27 

Continuous 

120 

» 24 

8 

Continuous  (under 

240 

i 40 

14 

shell  fire). 

i Under  such  conditions  road  material  would  be  piled  alongside  of  road  whenever 


possible. 


Table  XVI. — Volumes  of  cuts  cmd  fills  in  cubic  yards  per  100  linear 
feet  of  length 


Average  depth 
of  cut  or  height 
of  fill  (feet) 

Side  slope  1 on  1— width  of  base  of  cut  or 
crown  of  fill  (feet) 

Add 
for 
each 
addi- 
tional 
2 feet 
of 

width 

Add 
where 
slope 
is  44 
on  1 

Add 
where 
slope 
is  2 
on  1 

14 

16 

18 

20 

22 

24 

26 

28 

1 

56 

63 

70 

78 

85 

92 

100 

107 

m 

2 

2 

119 

133 

148 

163 

178 

192 

:■  -V 

7 

3 

1X9 

211 

256 

278 

323 

344 

K, 

16 

4 

267 

296 

326 

356 

385 

415 

444 

474 

30 

30 

5 

352 

3X9 

426 

463 

537 

574 

611 

37 

46 

6 

444 

4«9 

533 

578 

622 

667 

710 

7.56 

45 

67 

7 ... 

5H 

596 

648 

700 

752 

855 

52 

91 

8 

652 

711 

770 

830 

889 

948 

1,067 

59 

118 

9 . 

767 

m 

1,033 

1, 167 

67 

150 

889 

936 

1,111 

1, 185 

1,259 

1,333 

74 

185 

370 

11 

1.181 

1.344 

1,426 

1,507 

1,  589 

82 

224 

448 

12.  - 

1. 156 

1,  24  4 

1,333 

1,422 

1, 511 

nriiii 

1,688 

1,778 

89 

267 

534 

13 

1,396 

1,493 

1,589 

1.685 

1,781 

1,888 

1,974 

96 

313 

628 

14 

1,452 

1,556 

223 

1,763 

DEi 

1,970 

EE2 

2,178 

104 

363 

725 

15.  

1,611 

1,722 

Area 

1,944 

2,055 

2,166 

2,268 

2,389 

111 

428 

16.  

1,778 

1,896 

2,015 

2,133 

2,251 

2,370 

2,488 

22 

119 

474 

948 

17 

1,952 

2,079 

2,450 

2,581 

126 

534 

1,068 

IS  

2.133 

2,267 

2,666 

2, 933 

133 

599 

1,196 

19 

2,463 

2,744 

3,168 

141 

667 

1,334 

5? 

2,519 

2,667 

2.815 

2,963 

3,111 

3.259 

j,f  Y;j 

148 

KTn 

1,480 

21  

2,722 

2.878 

m 

3, 199 

3, 344 

3,811 

156 

815 

1,630 

22.  

3.259 

3,422 

3,585 

3, 749 

3,913 

4, 074 

163 

894 

1,788 

Note— For  fills  under  2 feet  allow  20  percent  for  shrinkage;  over 
2 feet  allow  15  percent. 


66 


REFERENCE  DATA 


31 


Table  XVII .—Gyratory  rock  crushers 


Dimensions,  receiving 
spider  openings 
(inches) 

Capacity  in  tons 
per  hour  varying 
with  character  of 
rock 

Horse- 
power for 
crusher, 
elevator, 
and 
screen 

Each 

about 

Both 

about 

Tons 

T o pass 
diameter 
ring 
(inches) 

8 x 22 

8 X 44 

5-  10 

2 H 

12-  15 

8)4x24 

8)4  X 48 

10-  20 

2)4 

20-  25 

9 X 27 

9 X 54 

15-  30 

2K 

25-  30 

12  X35J4 

12  X 71 

25-  50 

30-  50 

12)4  X 37 

12)4  X 74 

45-  90 

! 

40-  60 

14  X 44 

14  X 88 

90-150 

75-125 

19  X 60 

19  X 120 

130-225 

' 21* 

100-150 

25)4  X 72 

25 H X 144 

400-600 

175-250 

Approxi- 

mate 

weight 

of 

crusher 

(pounds) 


10, 

15,  (XX 
23, 5a 
32,  (XX 
44,  (XX 
67, 5 (X 
100,  OOf 
180,  (XX 


Table  XVIII. — Jaw  rock  crushers 


Jaw  opening  (inches) 


10  x 16. 
9 x 20. . 
12  X20. 
15X20. 
4 X 40... 
9 X 40... 
18  X38. 
21  x 38. 


Weight  on 
skids 
(pounds) 


4,700, 

9,800 

9.900 

10,200 

8,500 

14.000 

29.000 

30.000 


Horse- 

power 

required 


18-25 

25- 35 

26- 35 
25-35 
35-50 
40-55 
60-90 
60-90 


Capacity  (cubic  yards  per  hour)  * 
for  indicated  ring  size  product 


(inches) 


H 

D 

2h 

3)4 

6 

8 

li 

7 

10 

18 

30 

6 

9 

16 

28 

9 

16 

27 

14 

20 

32 

11 

16 

38 

52 

27 

50 

1 Average  capacities  shown  may  vary  25  percent  according  to  character  of  material 


67 


Table  XIX  A. — Bituminous  road  materials 


Material 

Source 

Form 

Grade  designa- 
tion-tempera- 
ture °F.  applied 

Remarks 

Cutback  asphalts  (RC  and 
MC). 

Product  of  refining  crude 
petroleum  oils  contain- 
ing asphalts. 

Liquids— asphalt  residues 
fluxed  with  more  vola- 
tile petroleum  distillates. 

Rapid  curing 
RC-0  50-120 

-1  50-120 

-2  100-175 

-3  150-200 

-4  175-250 

-5  175-250 

Naphtha  (highly  volatile), 
evaporating  quickly,  leaving 
asphalt  cement  binder,  per- 
mits early  use  of  surface. 

03 

CO 

Medium  curing 
MC-0  50-120 

-1  80-125 

-2  150-200 

-3  175-250 

-4  175-250 

-5  200-275 

Kerosene  (less  volatile)  docs 
not  evaporate  so  quickly  and 
cures  more  slowly  than  RC 
types. 

Asphaltic  road  oils  (SC)_.. 

Product  of  reflining  crude 
petroleum  oils  contain- 
ing asphalt. 

Liquids— low  volatile  oils 
left  or  blended  w ith  as- 
phalt residues  near  end 
of  refining  process. 

Slow  curing 
SC-0  50-120 

-1  50-120 

-2  120-180 

-3  175-250 

-4  200-275 

-5  200-275 

-6  250-300 

Penetration  200. 

Asphaltic  cements  (AC)  or 
paving  asphalts. 

Product  of  refining  crude 
petroleum  oils  contain- 
ing asphalts. 

Semiliquids  or  solids.. 

AC-l  250-350 
-2  250-350 

-3  250-350 

Also  graded  by 
penetrations. 

Penetrations  30  to  100  used  for 
crack  and  joint  fillers. 

Powdered  asphalt  (PA) . - 

Product  of  refining  crude 
petroleum  oils  contain- 
ing asphalt. 

Hard  and  solid  asphalts 
ground  to  powder. 

I'sed  with  SC  oils  to  produce 
extra  tough  road  surfaces. 

Asphalt  emulsions  (AE)... 

Asphalt  cements  in  water 
with  an  emulsifying 
agent. 

Liquids 

Rapid,  medium,  and 
slow  setting 
RS-1  60-120 

MS-1  60-120 

-2  60-120 

-3  60-120 

SS-1  60-120 

-2  50-120 

Freezing  destroys  emulsion. 

(Penetration  and  surface  treat- 
\\  ments. 

Road  and  plant  mixes  with 
coarse  aggregate. 

Road  and  plant  mixes  with 
fine  aggregate. 

Road  tar  (RT)  priming  oils 

All  road  tars  are  products 
of  coking  bituminous 
coal. 

Liquids.. 

RT-1  60-125 

-2  60-125 

-3  80-150 

■Waterproofs  surfaces  prepara- 
tory to  placing  other  bitu- 
minous surfaces. 

Cold  tars  (TC) 

All  road  tars  are  products 
of  coking  bituminous 
coal. 

RT-4  80-150 

-5  80-150 

-6  80-150 

-7  150-225 

Road  mixes  and  patching. 

1 


00 


CORPS  OF  ENGINEERS 


Table  XIX  A. — Bituminous  road  materials — Continued 


REFERENCE  DATA 


31 


Table  XIX  B — Typical  users  of  asphaltic  materials 


Grade  or  designation 

Purpose  or  use 

Rapid 

curing 

Medium 

curing 

Slow 

curing 

Paving 
asphalts 
with  pene- 
tration 1 

of— 

MC-0,-1,-2 

SC-0,  -I,  -2 

Prime  coat*: 

Tightly  bonded  sur* 

MM 

SC-l 

Loosely  bonded  fine 

MC-1 

8C-2 

Loosely  bonded  coarse 

MC-2 

SC-3 

Seal  and  carpet  coats: 
With  or  without  light 

RC-0 

RC-1 

nr -9 

Coarse  sand  cover 

Clean  aggre- 

MC-2. -3 

Clean  H-inch  aggre- 

R03 

150-200 

Clean  H-inch  aggregate 

RC-4 

150-200 

Clean  $4-inch  aggre- 

RC-5 

MC-4,  -5 

150-200 

Graded  gravel  agere- 

MC-2,-3 

SC-3 

MC-2 

SC-2 

Road  mix: 

Open  graded  aggregate: 

RC-1,-2 

MC-3 

Maximum  diame- 
ter 1 inch,  high 
percentage  pass- 

MC-3,-4 

Macadam  aggre- 

RC-2,  -3 

Dense  graded  aggre- 
gate: 

High  percentage 
passing  200  ntesh 
Maximum  diame- 
ter 1 inch,  high 
percentage  pass- 
ing 200  mesh 

MC-2 

SC-2 

MC-2,  -3 

80-2, -3 

1 Penetrations  of  100,  120,  150,  and  200  show  increasing  softness  or  fluidity.  Pene- 
trations of  85, 70, 60, 50, 40,  etc.,  show  increasing  hardness  or  solidity.  Road  oil  SC-6 
(with  high  viscosity)  and  the  softest  paving  asphalts  both  have  penetrations  of  about 
200. 


71 


31 


CORPS  OF  ENGINEERS 


Table  XIX  B. — Typical  uses  of  asphaltic  materials. — Continued 


1 

Purpose  or  use 

Grade  or  designation 

Rapid 

curing 

Medium 

curing 

SHow 

curing 

Paving 
asphalts 
with  |)enc- 
t rat  ion 
of— 

Cold  patch: 

Open  graded  aggregate 
])en«e  graded  aggregate 
Cold  laid  plant  mix: 

Open  graded  aggregate: 

RC-2 

MO-3 

MC-2 

SC-3 

SC-2 

RC-2, -3 

RC-3 
RC-4,  -5  ' 

Maximum  diame- 
ter 1 inch,  high 
percentage  pass- 

SC-3 

Macadam  aggre- 

Dense  graded  aggre- 
gate: 

High  percentage 
passing  2U0  mesh 
Maximum  diame- 
ter 1 inch,  me- 
dian percentage 

MC-3,-4 

MC-i 

MC-0 

MC-4,-5 

SC-3,  -l 

SC-4 

SC-1 
SC-5, -6 

SC-0 

Aggregate  precoating 
followed  with  asphalt 

RC-4,  -5 
RC-5 

150-200 

Penetration  macadam: 

100-200 

40-150 

1 


72 


REFERENCE  DATA 


Section  II 

BRIDGES  AND  STREAM  CROSSINGS 


II  32.  General  Data. 

Table  XX. — Commercial  sizes  of  timber  in  inches 


Note Ordinary  lengths  are  12  to  20  feet.  Bills  of  material  show 

number  of  pieces,  cross  section,  length,  kind,  grade,  and  surfacing, 
as  4 — 6"  x 12"  x 16'  yellow  pine  (YP),  No.  1,  rough  (Rgh). 
Dimensions  before  surfacing  are  given. 

Table  XXI. — Design  and  reconnaissance  data 


Examination  of  existing 
structures 


Design  of  new  bridge 


Safety  factors: » 
Wood 


Impact  allowable: 
Wood 


None  except  25  percent  for 
abutments. 


25  percent. 


25 (May  use  25  per 

t25)  cent  for  small 
bridges.) 

80  percent  (if  reasonably  well 
distributed,  otherwise  less, 
based  on  any  one  stringer 
carrying  more  than  its  pro- 
portional share). 


(L+125) 


90  percent  (oven  number 
of  stringers  well  distrib- 
uted). 

80  percent  (odd  number  of 
stringers  well  distrib- 
uted). 

Compute  (first  assuming 
a dead  load  and  chock- 
ing back  on  it). 


Stringer  efficiency  (same 
for  both  wood  and 
steel,  except  in  large 
and  important  bridg- 


Gcnerally  assumed  from  data 
in  Field  Manual  (or  com- 
puted if  time  permits). 


Dead  load. 


i In  dosigning  large  and  important  bridges,  which  may  be  used  over  protracted 
periods,  it  will  be  better  to  employ  the  factors  of  normal  civil  practice  (4.0  for  wood 
and  2.2  for  steel) . * L is  span  in  feet.  * See  paragraph  38. 


CORPS  OF  ENGINEERS 


Table  XXII. — Typical  and  critical  bridge  loads 


Distance 
in  inches 
between— 


Axle  loads  (pounds) 


Description 


weight 


Front ! 


140  lx- r foot 
250  per  foot 
185  i>er  foot 

5.000  1.8a 

5,700  1,4a 

0. 000  2,2a 

15,450  4, 05( 

14. 000  3,  ea 

(10,500  6.1a 


Pack  train  in  single  file 

Horse  cavalry  in  single  file. 
Escort  wagon,  4-mule. . . 

Car,  motor,  heavy 

Truck,  lH-ton 

Truck,  2H-ton,  searchlight 
Truck,  3-ton,  cargo  . 

Truck,  4-ton,  cargo  (towing) 
155-mm  howitzer 


10,000 


Tractor, medium,  Ml  (towing), 
155-mm  howitzer 


16.000 

(10,000 

19.000 

21.000 
20,000 
21, 150 
15,700 
17.  OX) 
18,900 


Combat  car,  M2. 


Balloon  winch,  type  C-2. . . 

Shovel,  engineer 

Truck,  water  purification. 

Koad  grader,  engineer 

Tractor,  carrier,  engineer. 
Tractor,  carrier,  semitrailer 


11,5a) 

8,8a) 

14,400 

9,700 

12,500 

7,300 


Truck,  7^4-ton,  114  inches  from 

and  towing  . 

155-mm  gun,  Ml. 

Truck  (A A),  120  inclios  from 

and  towing 

3-inch  A A gun,  M2A2 

Tractor,  heavy.  Ml 

Tank,  light*,  M2A4 

Truck,  field  servicing,  E-2 

(AC) 

Truck,  wrecking,  F-2  (AC)... 
Truck,  crane,  engineer 


8,000 

10,000 


13,200 

10,000 


13,200 

10,000 


35, 500 

17.000 

30.000 

23.000 


34.000 

32.000 
33,400 


1 Distance  in  inches  l>etween  axle  of  towed  load  and  last  axle  of  prime  mover. 

* Length  of  normal  ground  contact  of  crawler  tread. 

3 Can  be  carried  on  H-10  timber  trestle  bridge  with  spans  less  than  20  feet.  Medium 
tank  requires  bridges  built  for  H-20  loads. 


QUARTERMASTER ORDNANCE ORDNANCE AIR  CORPS MEDICAL 

Truck  2 1 ton  Cargo  Combat  Car  3'aaGunMt.  Field  Servicing  Truck  Operating  Room 


REFERENCE  DATA 


32 


Figure  38. — Typical  wheel  and  axle  loads. 


For  corps  and  array  bridges  over  25  feet  in  span. 


H-20 


AA 


b 

<0 


EACH  REAR  WHEEL  HAS  T«£  WOTH 
Of  3/4"  PER  TOW  OF  CROSS  LOAO 


1-9 'I*  I L...2 

Figure  40. — Distribution  of  wheel  loads  for  design. 

Table  XXIV. — Capacity  of  masonry  arch  bridges 

ICrown  thickness  required  for  all  loads  up  to  and  including  10-ton  axles  or  20-ton 
} tanks) 


Span 

Thick  ness  of  arch  ring  at  crown 

Span 

Thicknessof  arch  ring  at  crown 

Brick  in 
cement 

Plain 

concrete 

First- 
class  cut 
stone 
(ashlar) 

Brick  in 
cement 

Plain 

concrete 

First- 
class  cut 
stone 
(ashlar) 

Inches 

Inches 

Inches 

Feet 

Inches 

Inches 

Inches 

10 

12 

8 

8 

50 

26 

22 

20 

12M 

I3H 

9 

9 

55 

27 

23 

20H 

15 

15 

10 

10 

60 

28 

24 

21 

17H 

I6M 

11 

11 

65 

29 

26 

22 

20 

17H 

13 

12 

70 

30 

27 

23 

22H 

18 

14 

13 

75 

32 

28 

24 

25 

19 

15 

14 

80 

34 

29 

25 

27  H 

20 

16 

15 

85 

35 

30 

26 

30 

21 

17 

16 

90 

36 

32 

28 

35 

22 

18 

17 

95 

38 

34 

29 

40 

23 

20 

18 

100 

40 

36 

30 

44 

25 

21 

19 

282736°— 41 


77 


32-33 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


33 

(2)  Build  road  surface  1 inch  above  the  bridge  flooring  ini- 
tially. If  traffic  develops  holes  in  the  road  pavement  about 
2 feet  from  the  end  of  the  bridge,  these  must  be  kept  filled 
with  tamped  gravel. 
b.  Abutments. 


Figure  41. — Abutments  for  simple  stringer  bridges. 


Figure  42. — Pile  retaining  wall. 

79 


33 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


34 


c.  Design  of  foundations  and  footings. — (1)  Compute  the 
required  area  of  bearing  on  the  ground  (see  table  CXLI)  to 
carry  total  load.  If  mudsills  are  required,  assume  abutment 
sill  provides  no  bearing  and  mudsills  provide  full  area. 

(2)  Select  number,  length,  and  width  of  mudsills  and  test 
against  bending  using  formula  or  table  below. 

(a)  Formula. 

where 

If— projection  of  mudsill  beyond  bridge  seat  or  trestle  sill  in 
feet. 

C —constant,  depending  on  material  of  mudsill. 

P=safe  pressure  in  pounds  per  square  foot  on  bottom  of 
footing  course  or  safe  bearing  power  of  soil. 
f=thickness  in  inches  of  mudsills. 

(b)  Footing  material. 

Values  of  C 

1-2-4  concrete 7.0 

Limestone 11. 5 

Timber 20.  0 

The  value  of  C=V//3  where  f is  the  safe  allowable  bending 
stress  for  the  kind  and  condition  of  material  used  as  a mud- 
sill. For  timber  with  /=1,875  pounds  per  square  inch  C will 
be  25.  However,  the  value  of  C=20  for  /=1,200  is  sufficiently 
accurate  for  ordinary  use  for  inspection  or  design  where  tim- 
ber may  be  under  water  or  in  contact  with  muddy  ground. 


Table  XXVI. — Safe  unsupported,  projection  (K)  of  timber  mud- 
sills iri  feet  (based  on  C*=20  in  formula  from  (a)  above) 


Distributed  load  in  tons  per 
square  foot 

Thickness  of  timber  in  inches 

1 

2 

3 

4 

5 

6 

H- 

0.51 

1.03 

1.54 

2.06 

2.57 

3.09 

1 - — - 

.44 

.89 

1.34 

1.79 

2.23 

2.68 

m 

.36 

.73 

1.09 

1.46 

1.82 

2. 18 

2 

.31 

.63 

.94 

1.26 

1. 57 

1.89 

2H 

.28 

.56 

.85 

L 13 

1.41 

1.70 

4 

.22 

.44 

.67 

.89 

L 11 

1.34 

80 


I 


■ 34.  Other  Design  Criteria.- 


. Minimum  width  of  roadway. 


Feet 

Men  on  foot,  single  file iy2 

Antitank  gun 6 

Machine  gun  carts 41^ 

One  lane  for  vehicles 10 

Two  lanes  for  vehicles 18 


b.  Headroom. — 11  feet,  minimum,  14  feet  if  possible. 

c.  Clearance  for  navigation. — Sufficient  for  the  river  traf- 
fic permitted. 

d.  Camber. — No  camber  is  required  for  the  usual  military 
fixed  bridge  when  in  use.  When  all  settlement  has  oc- 
curred, the  bridge  floor  should  be  on  a uniform  grade  from 
abutment  to  abutment;  where  the  abutments  are  at  the  same 
level  this  grade  is  horizontal.  Where  settlement  of  founda- 
tions must  be  allowed  for,  the  footings  should  be  initially  as 
much  above  grade  as  required;  this  introduces  some  camber 
which  will  disappear  as  settlement  occurs. 

e.  The  deflection  of  the  bridge  under  load  should  not  ex- 
ceed 14oo  of  the  span. 

/.  Curbs. — Curbs  should  be  of  6 by  6 inch  timber  bolted 
to  the  outer  edges  of  the  flooring.  A 4 by  6 inch  timber  on 
edge  or  one  built  up  from  2 by  6 inch  timbers  may  be  substi- 
tuted. Spikes  or  lashings  may  be  substituted  for  the  bolts. 

g.  Flooring. — Use  at  least  11-foot  lengths  for  a 10-foot 
roadway.  If  longer  lengths  are  available,  lay  diagonally. 
For  heaviest  traffic  provide  a flooring  of  at  least  two  layers 
of  3-inch  thickness.  For  light  vehicular  traffic  use  chess  or 
flooring  of  at  least  2-inch  thickness.  Use  at  least  one  spike 
(preferably  two)  per  stringer.  Lay  dry  flooring  with  %- 
inch  spaces  between  planks. 

h.  Handrails  of  2 by  4 inch  timber  with  4 by  4 inch  posts 
3 feet  high  are  desirable  outside  the  curbs.  They  may  be 
knee-braced  to  floor  planks  extending  2-3  feet  beyond  guard 
rails. 


35 


CORPS  OF  ENGINEERS 


■ 35.  Bending. — a.  Criterion  for  maximum  bending. 
Distance  r=WVXj£,(fig-  43) 


IFj!  < FACTOR  x L , Mmax  IS  AT  -ffc  FROM  <E- 


IF^^FACTORxL,  MmaxIS  AT  <t 

Figure  43. — Positions  of  heavier  axle  load  (WR)  on  bridge  to 
produce  maximum  bending. 

Table  XXVII. — Values  of  load  factor  ( see  fig.  43) 


Iyoad 

proportioning 

Value  of  factor 

WK-n'r 

0.586 

IVk=2»> 

.561 

.535 

Wk-4 H> 

.527 

REFERENCE  DATA 


35-36 


b.  Bending  moment. — (1)  The  formulas  for  bending  mo- 
ment are — 


WL 

M= (concentrated  center  load  IV) 

4 

WL 

M= (total  load  W uniformly  distributed  over  span  L) 

8 

IV  (4a+b) 

M= (uniform,  moving  load  TV  partially  distributed) 

8 

where 

JW=moment  in  inch-pounds  at  center  of  a simple  beam. 
IV=total  load  in  pounds. 

L=span  In  inches. 
b=length  of  load  in  inches. 

L-b 

a= , or  distance  in  inches  of  each  end  of  load  from 

2 

nearest  end  of  span. 

(2)  Resisting  moment  must  be  equal  to  or  greater  than 
the  total  maximum  external  bending  moment.  The  for- 
mulas for  resisting  moments  are — 


M=fS  (all  beams) 
fbd 3 

M= (rectangular  timbers) 

6 

fd‘ 

M= (round  timbers) 

10 


where 

AT = resisting  moment  in  inch-pounds. 

/=  maximum  working  fiber  stress  for  material  (see  ch.  4) . 
b=breadth  of  rectangular  timber  in  inches, 
d—depth  of  rectangular  timber  in  inches  or  diameter  of 
round  timber. 

S=section  modulus,  I/y  in  inches  cubed  (in.*)  from  hand- 
books. 

■ 36.  Stringer  Strength. — a.  Design  and  check  strength  of 
stringers,  using  the  following  formulas,  diagrams,  and  tables. 
Impact,  dead  load,  and  stringer  efficiency  are  not  considered. 
I-beams  listed  are  the  lightest-weight  standard.  Values  of  f: 
1,600  (rectangular  timber);  1,000  (green  logs) ; 18,000  (steel). 


83 


1 


36-37 


CORPS  OF  ENGINEERS 


b.  The  following  formulas  give  the  allowable  loads  on  par- 
ticular stringers.  An  allowance  for  impact  of  25  percent  is 
included. 

(1)  Rectangular  wooden  stringers: 


w=(-j— 

\22.5, 


\bci1 

4uL 

) L 

10 

(2)  Standard  I-Beams  of  minimum  web  thickness: 


1^=930^  _o.4ui 

(3)  Standard  I-beams  of  average  web  thickness: 
W'=1050^2-0.4uI, 

Li 

For  uniformly  distributed  loads,  the  total  load  given  above 
may  be  increased  to  the  amount  given  by  the  following 
formula: 

where 

L=stringer  span  in  feet. 
iV=number  of  I-beams. 

T=length  of  tank  or  tractor  track  in  contact  with  the  floor, 
in  feet. 

17 —total  uniformly  distributed  safe  load  of  length  T in 
pounds. 

W-— allowable  concentrated  load  in  pounds. 
b=total  width  of  stringers  of  depth  d in  inches. 
d= depth  of  stringer  in  inches. 

/=allowable  bending  stress  in  pounds  per  square  inches 
(usually  1,000  to  1,800;  see  table  CXLIII) . 
«=uniform  dead  load  of  span  in  pounds  per  linear  foot 
(see  table  XXXI) . 


■ 37.  Dead  Load. — In  hasty  design  of  short  span  bridges  it  is 
usually  sufficient  to  add  an  extra  stringer  to  take  care  of  the 
dead  load.  For  long  spans  using  light  stringers  it  may  be  nec- 
essary to  add  25  percent  of  the  number  needed  for  the  live  load. 


88 


REFERENCE  DATA 


37-38 


Table  XXXI. — Dead  loads,  highway  bridge  decks 


Pounds  per  linear  foot 


Steel - 

Wood 

Concrete. 
800  up. 
1,300  Up. 

250-350 

250-400 

350-500 

400-700 

Note. — The  figures  on  concrete  are  based  on  a slab  thickness  of  6 
inches  and  weight  at  150  pounds  per  cubic  foot.  The  weight  of 
timber  is  about  40  pounds  per  cubic  foot. 


| 38.  Stringer  Arrangement  and  Distribution. 


Figure  46. — Transverse  cross  section  of  typical  stringer  bridge. 


a.  For  design  the  proportion  cf  the  wheel  load  on  any  one 
stringer  is: 

SL+1 

8 rN 

where 

N= total  number  of  stringers. 

S'  - stringer  spacing  in  feet  center  to  center. 

b.  For  a simple  one-track  stringer  bridge,  with  an  even 
number  of  stringers,  it  is  considered  that  stringers  can  be 
placed  to  allow  a stringer  efficiency  of  90  percent  to  be  used 
in  design.  For  reconnaissance  the  determination  of  stringer 
efficiency  is  a matter  of  judgment.  If  the  flooring  is  satis- 
factory, assume  a stringer  efficiency  of  80  percent.  Tables 
XXXV  and  XXXVT  provide  a quick  means  of  determining 


38-41 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


41 


bridge  capacities  for  various  classes  of  stringers.  For  the 
worst  conditions,  figure  the  live  load  supported  by  stringers 
on  the  basis  that  the  flooring  acts  as  a simple  beam  between 
stringers. 

■ 39.  Shear. — The  maximum  vertical  shear  develops  at  the 
supports  and  occurs  as  the  maximum  load  passes  that  point. 
In  timber  the  maximum  horizontal  shear  occurs  when  the 
load  is  at  a distance  from  the  support  of  three  times  the  beam 
depth,  or  at  the  center  when  the  span  is  six  times  the  depth  or 
less.  Horizontal  shear  per  unit  of  horizontal  stringer  cross 
section  area  is  equal  to  the  reaction  at  the  support  divided 
by  the  vertical  stringer  cross  section  and  multiplied  by  3/2. 
This  is  important  only  for  short  spans. 

■ 40.  Caps  and  Sills. — The  width,  ordinarily  equal  to  the 
diameter  of  the  posts,  should  be  the  least  dimension.  Investi- 
gate special  and  doubtful  cases  for  shear  and  crushing  of  posts 
into  cap  or  sill. 

■ 41.  Posts. — Posts  are  designed  as  columns,  using  a,  b,  or 
c below.  The  L/d  ratio  must  not  exceed  40;  L and  d must 
be  given  in  same  units  (both  in  inches  or  both  in  feet) . 

a.  Where  L/d  <11 

p=s  (Using  table  CXLm,  this  gives  a factor 
of  safety  of  3.) 

b.  Where  11  <L/d<K  and  K=0M^/E/s 

rj_l/  i V]  (Using  table  CXLin,  this 
p s[_  3 \Kd)  J gives  a factor  of  safety 

of  2.25.) 

c.  Where  L/A>K  and  K 0.64-/E/S 

p=  1.2X0.274  - E - (This  gives  a factor  of 

(L./a) 

safety  of  2.5.) 

d.  For  round  columns  replace  d in  the  above  formulas  by 
70/79  times  the  diameter. 

e.  For  reconnaissance  investigations  use  the  formula: 

p=s(i-dy 


where 

Z,= unsupported  length  of  the  column. 
d=least  dimension  of  the  column. 

F=modulus  of  elasticity. 

s=unit  working  stress  for  compression  parallel  to  the  grain 
(table  CXLm). 

X=0.64  E/s  (for  select  merchantable  Douglas  fir  If -=22.5) 
p=allowable  unit  load. 

P=total  load=pA. 

A - cross-sectional  area. 


Table  XXXII. — Values  of  the  expression 


Values  of 


— ratio  of  length  to  least  dimension  in  rectangular  timbers 


K 

11 

12 

13 

14 

15 

16 

17 

IS 

19 

20 

21 

22 

23 

0. 67 

81 

.75 

0. 67 

.92 

.80 

.80 

.74 

0.67 

80 

.74 

0.67 

88 

.84 

.79 

.73 

0.67 

Q3 

.90 

.87 

.83 

.78 

.73 

0.67 

20  - 

.98 

.96 

.94 

.92 

.89 

.86 

.83 

.78 

73 

0.67 



21 

.98 

.97 

.95 

.93 

.92 

.88 

.86 

.82 

.77 

.72 

0.67 



22..-. 

.98 

.97 

.96 

.94 

.93 

.91 

.88 

.85 

.81 

.77 

.72 

0.67 

23 

.99 

.98 

.97 

.95 

.94 

.92 

.90 

.87 

.84 

.81 

.77 

.72 

0.67 

Note — This  table  can  also  be  used  for  timber  columns  not  rectan- 
gular i/d  being  equivalent  to  0.289  L/r  where  r Is  the  least  radius 
of  gyration  of  the  section. 


90 


91 


41-42 


CORPS  OF  ENGINEERS 


Table  XXXIII. — Safe  loads,  square  wood  posts,  and  /or  various 
values  of  L/d  in  formula  of  paragraph  41e 


[Fiber  stress  assumed  to  be  1,200  in  the  formula.  Proportionate 
increases  or  decreases  should  be  used  for  higher  or  lower  stresses) 


Size  (inches) 

Length 

(feet) 

L 

d 

Safe  unit 
working 
stress  p 

Safe  load  P 
for  post= 
pA 

4 by  4 

2 

6 

1,080 

17,280 

4 by  4 

4 

12 

960 

15,360 

4 by  4 

6 

18 

840 

13, 440 

4 by  4 

8 

24 

720 

11,520 

4by4  

10 

30 

600 

9,600 

fi  by  fl 

4 

8 

1,040 

37, 440 

6 by  6 

6 

12 

9(50 

34,560 

fi  by  fi 

8 

16 

880 

31,680 

6 by  fi 

10 

20 

800 

28,800 

6 by  6 

12 

24 

720 

25,920 

6 by  0..  

14 

28 

640 

23,  (M0 

fiby  fi 

10 

32 

560 

20,160 

8 by  8 

0 

9 

1,020 

65,280 

8 by  8 . 

8 

12 

960 

61,440 

8 by 8... ..  .... 

10 

15 

900 

57,600 

8 by  8... - 

12 

18 

840 

53, 760 

8 by  8... 

14 

21 

780 

49,920 

8 by  8 

16 

24 

720 

46,080 

8 by  8.  

18 

27 

660 

42, 240 

8 by  8 

20 

30 

600 

38,400 

8 by  8 

22 

33 

540 

34,560 

8 by  8 

24 

36 

480 

30,720 

■ 42.  Piles. — Construct  pile  bents  in  dimensions  similar  to 
trestle  bents.  When  the  height  from  the  bottom  is  less  than 
8 feet  no  bracing  is  required.  Place  bracing  above  water 
when  required.  For  greater  stability  batter  piles  are  fre- 
quently used.  If  the  pile  rests  on  a hard  stratum  it  is  designed 
as  a column.  Otherwise  determine  the  safe  load  by  loading 
test  piles  or  by  the  following  rough  formulas: 

For  piles  driven  by  drop  hammer:  P=^^- 

For  piles  driven  by  steam  hammer:  P=  -rx/n 


92 


REFERENCE  DATA 


42-44 


where 

P=safe  load  in  pounds. 

weight  of  hammer  in  pounds. 
h=height  of  fall  of  hammer  in  feet. 

s= average  penetration  of  the  pile  under  several  successive 
blows  of  the  hammer,  in  inches. 

Table  XXXIV. — Bearing  power  of  piles  of  1 foot  mean  diameter 


Character  of  soil 

Penetra- 

tion 

(feet) 

Probable 
safe  load 
(pounds) 

Character  of  soil 

Penetra- 

tion 

(feet) 

Probable 
safe  load 
(pounds) 

Soft  mud 

15 

4,500 

Compact  sand 

10 

20,000 

30 

10.000 

12 

24,000 

Soft  clay 

10 

7,000 

15 

28,000 

Compact  silt 

15 

10,000 

20 

36,000 

20 

13,000 

30 

48,000 

30 

20.000 

Sand  and  gravel.  . 

8 

20,000 

Stiff  clay 

10 

15,000 

10 

24.000 

15 

23,000 

12 

28,000 

20 

30,000  1 

15 

34, 000 

30 

45,000 

20 

43.000 

Compact  sand 

8 

16,000 

30 

60,000 

Note. — For  other  pile  diameters  the  safe  load  will  vary  In  propor- 
tion to  the  diameter. 

■ 43.  Timber  Piers. — Make  timber  piers  of  trestle,  pile,  or 
crib  construction.  They  are  used  when  simple  bents  do  not 
provide  sufficient  support,  stability,  and  stiffness. 

■ 44.  Bridge  Reconnaissance  Form. 

FORM  FOR  BRIDGE  RECONNAISSANCE 

Bridge  

Class  

Sheet  No in sheets 


Map  reference 

Date Party 

(If  necessary,  use  back  of  sheets,  repeat  number  of  headings.) 

Location 

1.  Designation  of  route 

(road,  railroad,  canal,  or  stream) 

2.  Two  towns  on  route 

8.  Name  of  nearest  town;  direction  and  distance  from  bridge.... 


282736°— 41- 


93 


/ 


44 


CORPS  OF  engineers 


4.  Stream,  canal,  road,  or  railroad  crossed  by  bridge 

5!  Local  name  of  bridge 

6.  Remarks  


Description  of  bridge 

7.  Type - 

8.  Spans 

9.  Total  length 

10.  Net  length 

11.  Total  width 

12.  Width  of  roadway 

13.  Clearances. 

/ Horizontal 

Above  roadway \ Vertical 

Under  roadway 

14  Floor  system. 

(а)  Flooring  

(б)  Stringers  and  floor  beams 

(e)  Curbs,  handrails 

15.  Number  and  width  of  sidewalks 

16.  Piers 

17.  Abutments  

18.  Wing  walls 

20.  Maximum  loads:  Now  using  bridge Reported  capacity 

21.  Remarks 


Description  of  crossing 

(Make  plan  and  profile  on  extra  sheet  Bhowlng  (a)  all  bridges 
' involved  in  crossings;  (b)  bridge  being  reported  on) 

22.  One  of bridges  Involved  in  crossing 


(Low  water 

High  water 

Observed  

24.  Velocity:  Feet  per  second 

25!  Floods  per  year months — 

26  Amount  and  character  of  debris  carried  at  high  water.. 

27!  Character  of  bed  and  banks  of  stream 

28.  Approaches'^  stralght  iength width height 

cut  or  fill. 

(h)  ..end.  Straight  length width height 

cut  or  fill. 

29.  Remarks 


”36."  Description  of  "connecting  roadway  between  several  bridges 
involved  in  crossing 


94 


REFERENCE  DATA 


44-45 


Recommendations 

31.  List  in  order  of  practicability  for  new  construction. 

(Pile  bents,  trestle,  crib  supports,  etc.) 

32.  Remarks  

83.  Estimate  of  time  required  for  construction 

34.  Troops 

35.  Bill  of  materials  (use  extra  sheet) 

36.  Location  of  construction  camp 

37.  Remarks 


■ 45.  Determination  of  Allowable  Loads  on  Existing 
Bridges. — a.  General. — Newer  bridges  are  usually  designed  on 
the  basis  of  H-loadings  (figs.  39  and  40)  as  follows: 

Main  Federal  and  State  highways  (including 


strategic  highways) H-15 

Principal  State  and  county  roads H-10 


Older  bridges  will  vary,  and  no  assumption  should  be  made  as 
to  design  basis  unless  indicated  on  the  bridge  or  by  posted 
sign  capacity.  For  new  bridges  with  heavy  concrete  or  other 
type  floors  giving  wide  load  distribution,  the  H-loading  (in 
tons)  may  be  exceeded  by  50  percent  on  one-lane  bridges, 
and  by  100  percent  on  multiple-lane  bridges,  by  single  vehicles 
at  steady  speeds  of  5 m.  p.  h.  For  other  bridges  under  same 
conditions  the  posted  capacity  should  not  be  exceeded  by  more 
than  25  percent.  Wherever  excessive  deflections  or  signs  of 
strain  appear  after  trial  the  posted  loads  should  not  be  ex- 
ceeded. Assume  that  flooring  and  stringers,  especially  in 
older  bridges,  are  weaker  than  abutments  and  intermediate 
supports  unless  these  are  obviously  damaged  or  rotted.  In 
case  of  doubt,  the  following  more  detailed  check  methods 
should  be  employed. 

b.  Flooring. — Rule  of  thumb:  For  heavy  loads,  planking 
thickness  (inches)  should  be  at  least  V/2  times  clear  distance 
between  stringers  (feet) ; minimum  permissible  thickness  is 
2V2  inches  if  worn  or  2 inches  if  new.  In  doubtful  cases,  way 
planks  or  a second  layer  of  flooring  (spiked  down)  should  be 


95 


Table  XXXV. — Hasty  estimation  of  bridge  capacities — steel  stringers 
[Number  of  I-bcams  required  for  10-ton  single-axle  loadl 


Depth  and  weight  of  standard  minimum  weight  beams 


(feet) 

6" 

12.5# 

7" 

15.3# 

8" 

18.4# 

9" 

21# 

10" 

25.4# 

12" 

31.8# 

15" 

42.9# 

18" 

54.7# 

20" 

65.4# 

6 

4.2 

2.  9 

2.2 

1.4 

8 

5.  6 

4.0 

2.9 

1.  9 

1.  7 

10 

7. 1 

5.0 

3.  7 

2.4 

2.  2 

1.4 

12 

8.  6 

6.0 

4.4 

2.9 

2.6 

1.7 

14 

10.2 

7.2 

5.3 

3.5 

3.0 

2.0 

16 

12.2 

8.3 

6.1 

4. 1 

3.5 

2.3 

L 5 

18 

13.  6 

9.6 

6.9 

4.6 

4.0 

2.  6 

L 7 

20 

10.  6 

7.8 

5.2 

4.5 

3.0 

1.8 

25 

10.2 

6.8 

6.0 

3.7 

2.4 

1.6 

30 

8.6 

7.6 

4.9 

3.1 

2. 1 

35 

a 1 

3.7 

2.  5 

1.9 

Notes. — 1.  Explanation  of  use  of  table: 

a.  To  find  the  safe  concentrated  load  for  ordinary  traffic  moving 
at  standard  speeds,  take  the  ratio  of  number  of  I-beams  available  to 
tabular  value  and  multiply  by  10  tons. 

b.  If  beams  are  not  minimum  weight  and  ratio  of  actual  weight 
of  beams  to  minimum  weight  of  beams  for  size  can  be  determined, 
increase  the  value  found  in  a above  by  *4  the  percentage  of  increase 
in  weight  over  minimum  weight.  Otherwise  assume  beams  are 
minimum  and  disregard  actual  weights. 

c.  For  emergencies,  with  traffic  control  guards  to  insure  reduced 
speeds,  only  one  vehicle  on  bridge  at  a time,  and  no  gear  shifting 
on  bridge,  l'/2  the  value  found  above  may  be  used. 

d.  To  find  the  gross  truck  weight  allowable,  multiply  the  safe  axle 
load  by  1.25. 

2.  The  above  table  is  based  on  the  following  data: 

Dead  load  of  4-inch  plank  flooring  10  feet  long  with  two  6-  by 
6-inch  curbs  plus  actual  stringer  weight. 

25 

Impact  on  basis  of  formula:  7=  y25)  ( L equals  span  in 

feet) . 

Stringer  efficiency  of  80  percent  included. 

Safe  tensile  stress  of  18,000  p.  s.  1.  used. 


96 


REFERENCE  DATA 


40-46 


Table  XXXVI. — Hasty  estimation  of  bridge  capacities — wooden 
stringers 


[Total  stringer  widths  in  inches  required  tor  10-ton  single-axle  load) 


Notes. — 1.  Explanation  of  use  of  table: 

a.  To  find  the  safe  concentrated  load  for  ordinary  traffic  moving  at 
standard  speeds,  take  the  ratio  of  stringer  width  available  to  tabular 
value  and  multiply  by  10  tons. 

b.  In  emergency,  with  traffic  control  guards  to  insure  reduced  speeds 
only  one  vehicle  on  the  bridge  at  a time,  and  no  gear  shifting  on 
bridge,  1 % this  value  can  be  used. 

c.  To  find  the  gross  truck  weight  allowable,  multiply  the  single 
safe  axle  load  by  1.25. 

2.  The  above  table  is  based  on  the  following  data: 

a.  Dead  load  of  4-inch  plank  flooring  10  feet  long  with  two  6 by  6- 
inch  curbs  plus  actual  stringer  weight. 

b.  Impact  of  25  percent  and  stringer  efficiency  of  80  percent  in- 
cluded. 

c.  Fiber  stress  of  1600  p.s.i.  used.  If  actual  allowable  fiber  stress  is 
less,  decrease  allowable  load  on  proportional  basis. 

d.  Trestles. — For  caps  and  sills  see  paragraph  40.  For  posts 
use  table  XXXIII  and  table  XXXIV  for  piles. 

e.  Other  parts. — If  sufficient  time  is  available,  continue  the 
investigation  to  the  other  parts  of  the  structure. 

■ 46.  Suspension  Bridges. — a.  Formulas  for  determining 
stresses  in  cables. 

(1)  For  a uniform  load: 


(2)  For  a concentrated  load  (approximate) : 
r=iy/S^f'A(S+)V)J 


97 


46-47 


CORPS  OF  ENGINEERS 


where 

T=maximum  cable  tension  (in  all  cables  at  one  tower) . 
W= concentrated  live  load  on  bridge. 

S=sum  of  all  live  and  dead  loads  on  bridge  cables  (including 
Impact  and  all  other  loads). 

L=span  in  feet  between  towers. 

d— deflection  (sag)  of  cable  in  feet  at  midpoint  below  tops 
of  towers. 

0=angle  made  with  the  horizontal  by  tangent  to  cable  at 
tower. 

b.  Formula  for  length  of  cables  between  towers. 

(approximation  based  on  a circular  curve). 

c.  Formula  for  length  of  slings  (omitting  any  allowance  for 
camber) . 

/4 d\_. 


where 

2!=length  of  sling. 

x=distance  from  middle  point  of  bridge  to  sling. 

■ 47.  Footbridge  Equipment,  M1935. — One  unit  makes  432 
feet  of  footbridge  or  144  feet  of  wide  bridge.  Standard  load  for 
a 1 1/2- ton  truck  is  9 bays  or  108  feet  of  footbridge.  An  infan- 
try rifle  company  can  cross  on  this  bridge  in  3 minutes  dur- 
ing daylight  or  in  10  minutes  at  night. 


Figure  47. — Construction  of  footbridge  by  successive  bays. 
98 


Figure  48. — Assembled  footbridge  using  anchor  and  float  cables. 


CORPS  OF  ENGINEERS 


Guy  L mcs  j dib\Month  Rop*x- 


F/oot  remo* 
from  end  S 
+*hen  beach 
bridge. 


Figure  49. — Assembled  footbridge  using  guy  lines, 


Table  XXXVII. — Cables  and  guy  lines  lor  footbridge 
[Not  applicable  to  wide  bridge] 


< Any  length. 


Current 
in  main 
channel 
of 

stream 

(m.p.b.) 

Maxi- 
mum 
practica- 
ble bridge 
length 
with 
anchor 
cable 
(feet) 

Anchor 

cable 

required 

for 

bridge 

length 

over 

(feet) 

Bridle  lines, 
anchor  cable 
to  bridge 

Float 

cable 

required 

for 

bridge 

length 

over 

(feet) 

Guy  lines  required  both 
sides  bridge  to  bank 
when  anchor  cable 
not  used 

0 

1,000 

500 

Each  10  bays. 

0 

Only  required  over  100 
feet. 

100-300  feet  at  end. 
300-500  feet  at  ond  and 

center. 

1 

700 

300 

Each  0 bays. . . 

300 

Less  than  100  feet  at  end. 

100-300  feet  at  end  and 
each  6 bays. 

2 

500 

200 

Each  4 bays... 

200 

At  end  and  each  4 bays. 

3 

350 

100 

F,ach2bays... 

100 

A t end  and  each  2 bays. 

4 

200 

(>) 

Each  bay 

« 

Anchor  cable  required. 

REFERENCE  DATA 


47-48 


Table  XXXVIII. — Number  of  12- foot  footbridge  bays  constructed 
per  minute 


Current  (m.  p.  h.) 


Less  than  2. 

2 to  3 

Over  3 


Hay 


2 

lHl 

1 


Night 


Note.— These  rates  require  40  to  50  trained  men  (depending  upon 
the  current)  under  service  conditions  with  a good  site.  (See  table 


■ 48.  Kapok  Footbridge.— One  unit  of  this  bridge  consists  of 
twenty-two  12-foot  sections,  or  264  feet,  and  can  be  trans- 
ported on  two  1 ‘/2-ton  trucks. 


I 


101 


REFERENCE  DATA 


■ 49.  Ponton  Bridges. 


Figure  52. — Method  of  construction  by  parts.  (First  bay  may  be  a 
trestle  bay  instead  of  as  shown.) 


CURRENT 


Figure  51. — Method  of  construction  by  successive  pontons. 


Note. — The  length  of  cable  between  anchor  and  ponton  should  be 
at  least  ten  times  the  depth  of  the  stream. 


MHitS 


REFERENCE  DATA 


Figure  54.— Hinge  sill  raft  being  used  for  placing  trestle. 


hinge  sill- 


sill  raft  and  trestle  (23-ton  M1924  bridge) 


49 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


49 


Table  XXXIX. — Characteristics  of  standard  ponton  equipage 


Heavy 
ponton 
battalion, 
M 1924 

Light 
I>onton 
company, 
Ml  938 

Normal  load 

» 23 
46 
*250 

146 

6-8 

16 

16 

16 

4-12 

16 

12 

24 

48 

4,000 

32 

6H 

27. 100 
4,100 

23.100 

Reinforced  load . 

Length  of  bridge  Der  bridge  platoon 

*250 

103 

Construction  time: 

Hours 

Spans: 

Abutment  to  trestle 

15 

15 

15 

4-12 

15M 

Trestle  to  trestle 

Trestle  to  hinge 

Effective  length  of  hinge  sill  raft 

Ponton  to  ponton 

Number  of  boats: 

Per  bridge  platoon _ _ _ 

do 

Total  per  bridge  company 

Total  per  battalion 

Characteristics  of  boats: 

Weight 

1, 450 
28 
W 
15,000 
2,600 
12,400 

Length 

- - feet 

Safe  buoyancy  (freeboard  9 inches)  

pounds.. 

Net  buoyancy  * 

do 

See  footnotes  at  end  of  table. 


Table  XXXIX. — Characteristics  of  standard  ponton  equipage. — Con. 


Heavy 
ponton 
battalion, 
Ml  924 

Light 

ponton 

company, 

M1938 

Trestles: 

4 

4 

Capacity,  unreiniorced - tons  . 

Weight pounds 

Width  of  roadway  (clear) feet 

Number  of  balk  under  roadway  per  span,  normal  con- 

25 

« 1,690 
lltf 

9 

20 

1,050 

10 

8 

58 

*25 

7 to  9 

» 5 to  7 

1 Loads  over  20  tons  must  be  at  intervals  of  over  32  feet. 

“Four  trestles  are  used  In  this  bridge  In  normal  construction. 
Using  all  basic  quantities,  lengths  given  can  be  built.  Unless  all 
trestles  can  be  used,  length  of  single  bridge  that  can  be  built  by 
several  platoons  of  equipage  end  to  end  is  considerably  less  than  250 
feet  times  the  number  of  units  employed.  In  this  case  exact  length 
of  bridge  that  can  be  built  must  be  computed  using  only  number  of 
spans  which  can  be  actually  employed. 

• The  approximate  net  safe  buoyancy  of  the  boat  in  the  bridge  is 
the  displacement  of  the  ponton  with  a safe  freeboard  (approx.  0 in.) 
minus  the  weight  of  one  span  of  flooring.  The  weights  of  one  span 
of  flooring  of  the  23-ton  bridge,  M1924,  and  the  10-ton  bridge, 
M1938,  are  approximately  4,100  and  2,600  pounds,  respectively. 

*A  duralumin  trestle  has  also  been  made  weighing  1,200  pounds. 

0 With  outboard  motor,  ferrying  capacity  is  40  passengers  with 
crew  of  3. 


107 


106 


49 


CORPS  OF  ENGINEERS 


r - 


Table  XL. — Maximum  safe  loads  for  various  types  of  ponton  bridges 


Type  of  bridge 

Maxi- 

mum 

gross 

load 

(pounds) 

Maxi- 

mum 

axle 

load 

(pounds) 

Mini- 

mum 

distanco 

between 

vehicles 

(feet) 

Maxi- 
mum 
speed 
(m.  p.  h.) 

Width  of 
road- 
way 
(clear) 
(feet) 

7^-ton,  M1928,  normal 1 

15,000 

12,000 

32 

5 

10 

7Vi-ton,  M1926,  reinforced  * 

30,000 

24,000 

32 

6 

10 

10-ton,  M 1938,  normal  - 

20,000 

16,000 

35 

5 

10 

10-ton,  M1938,  reinforced 4 

40,000 

32,000 

35 

5 

10 

23-ton,  M1924,  normal 8 

25-ton,  M 1940 8 

46,000 

32,000 

32 

5 

UH 

1 Normal  span  of  16  foot  between  boat  centers,  seven  4-  by  6-inch  balk  and  2 siderails 
in  each  ponton  bay  and  each  trestle  and  hinge  span,  and  1 layer  of  2^-inch  chess. 

* One  extra  boat  in  each  boat  span.  Seven  balk  and  2 siderails  in  boat  spans  and 
12  balk  and  2 siderails  in  abutment,  trestle,  and  hinge  spans.  (This  is  tho  15-ton 
bridge.) 

* Normal  span  of  15 Vi  feet  between  boat  centers,  eight  4-  by  6-inch  balk  and  2 side- 
rails  in  each  ponton  bay  and  in  each  trestle  and  hinge  span,  and  1 layer  of  2H  inch 
chess. 

4 One  extra  boat  in  each  boat  span.  Eight  balk  and  2 side  rails  in  boat  spans  and 
14  balk  and  2 siderails  in  nbutment,  trestle,  and  hinge  spans.  (This  is  the  26-ton 
bridge.) 

8 Normal  span  of  10  feet  between  boat  centers,  nine  5M«*  by  7^-inch  l>alk  and  2 
siderails  in  each  bay,  1 layer  of  2%~inch  chess,  and  1 transverso  balk  in  tho  center  of 
each  span. 

0 This  bridge,  now  under  design,  will  replace  the  23-ton  bridge,  M1V24. 


108 


L I 


I 


HASTY  METHOD.  TOE  NAILING  WITH  60*  NAILS 
ANGULAR  SLOCKS  NAILED  TO  EACH  SIDE  OF 
GROUP  OF  STRINGERS 


ELEVATION  OF  BENT  LONGITUDINAL  ELEVATION  OF  BRIDGE 

57. — Multiple  short  span  (nonfloating)  bridge  lor  corps  and  army  loads  (I 
loading).  Wood  stringers  in  spans  up  to  15  feet. 


Table  XLI. — Material  used  in  standard  trestle  bridge 
Material 


Flooring 

Curbs 

Stringers 

Posts 

Cap  and  sill.. 
Bracing 


Sire 


2 layers  of  3-  by  12-inch  by  11-foot  planks. 

6 by  6 inches. 

8. 6 by  12  inches  (not  to  exceed  16  feet  in  length). 

4. 6 by  8 inches  (not  to  esceed  16  feet  In  length). 
6 by  8 inches  by  12  feet. 

2 by  10  inches. 


REFERENCE  DATA 


50 


Note. — Bents  over  16  feet  high  are  double  story.  Round  posts 
must  be  9 inches  In  diameter.  Logs  for  caps  and  sills  must  be  10 
Inches  In  diameter  before  shaping.  The  second  layer  of  flooring 
may  be  temporarily  omitted.  If  the  span  exceeds  15  feet,  use  6 
standard  steel  beam  stringers  as  follows: 


Clear 

spans 

(feet) 

Class  of 
beam 
index 

Weight 
(pounds 
per  foot) 

Nominal 

dimensions 

(inches) 

Actual 

length 

(feet) 

Material  strength 

15-17X—. 

CB  101 

21 

IOjSH 

19 

Standard  commercial. 

17H-20 

OB  101 

21 

21H 

Do. 

20-22H-— 

CB  121 

25 

12x6H 

24 

Do. 

22^-25.... 

CB  121 

25 

12X6H 

26H 

Do. 

61 


51 


CORPS  OF  ENGINEERS 


■ 51.  Steel  Trusses. — a.  Portable  H-10  type. 


Table  XLJI. — Permissible  loadings  of  portable  H-10  truss  bridge  for 
various  lengths  of  span 


Number  of 
girders 

36  feet 

48  feet 

60  feet 

72  feet 

84  feet 

96  feet 

108  feet 

2 

H-20 

H-15 

H-10 

3 

H-20 

H-15 

H-10 

4... 

H-20 

H-15 

H-10 

Note. — The  12-foot  box  girder  section  weighs  1140  pounds.  The 
72-foot  (2-girder)  span  can  be  carried  on  nine  1*4 -ton  trucks  or  five 
2 (4  -ton  trucks.  Under  ideal  conditions  an  experienced  crew  of  42 
men  under  an  officer  can  construct  a (2-girder)  60-foot  span  in 
about  1 hour. 


REFERENCE  DATA 


51-52 


Figure  62. — Single-  and  double-lock  spar  bridges. 


b.  Portable  H-20  type. — The  long  span  (nonfloating)  bridge 
for  corps  and  army  loads  (H-20  loading)  built  with  two  girders 
will  carry  all  army  loads  on  spans  up  to  125  feet.  The  box 
girder  section,  2 by  6 by  12  Vi  feet,  weighs  1,730  pounds.  The 
material  for  the  125-foot  span  weighs  about  43  tons  and  can 
be  carried  in  twenty-four  lVi-ton  trucks. 

■ 52.  Spar  Bridges;  Trestle  Bents. 


113 


I 


[ 

I 

I 


: 


I 


REFERENCE  DATA  53-54 

■ 53.  Passage  by  Fords  and  on  Ice. 


Table  XLm. — Fordable  depths 


Type  of  unit 

Depth  of 
water 
(feet) 

Infantry . 

3H 

4H 

3 

2 

Light  tanks 

1-3 

2-4 

4-6 

Note. — These  depths  require  a moderate  current  and  a hard  bot- 
tom. 


Table  XLTV. — Carrying  capacity  of  ice 1 


Thickness  (inches) 

Will  support— 

3 

Small  groups  of  men. 

4-6 

7 

Wagons  and  75-mm  guns. 
Divisional  loads. 

Army  loads. 

9-12 

20 

* New  sound  ice  in  Heating  contact  with  water. 


■ 54.  Passage  by  Boats,  Rafts,  and  Ferries. — The  assault 
boat  weighs  200  pounds.  Ten  boats  are  the  normal  load  of  a 
l>/2-ton  truck.  Besides  its  engineer  crew  of  two  a boat  will 
carry — 

9 men. 

8 men  and  a machine  gun  or  60-mm  mortar  with 
some  ammunition. 

7 men  and  one  heavier  item  of  infantry  battalion 
equipment  (81-mm  mortar  or  communication  sec- 
tion) . 


115 


54  CORPS  OF  ENGINEERS 


Figure  64. — Rafts  made  from  ponton  equipage. 


A two-boat  light  ponton  raft  with  two  simple  landing  stages 
(see  fig.  66)  can  be  constructed  in  about  1 hour  by  48  men 
after  equipment  is  delivered.  This  ferry  has  a 10-foot  by 
21-foot  platform  that  carries  one  gross  truck  load  of  5 tons 
or  a uniform  load  of  7 tons,  making  6 or  more  round  trips 
per  hour.  On  narrow  streams  the  ferry  may  be  drawn  across 
by  cables  fixed  to  both  banks  or  by  cables  attached  to  the  raft 
pulled  from  shore.  When  outboard  motors  are  used  on  free 
rafts,  several  may  operate  at  one  site.  See  further  details 
on  rafts  in  TM  5-270. 


116 


REFERENCE  DATA 


54 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


■ 55.  Reconnaissance. — Information  to  be  secured: 

a.  Number,  location,  and  gage  of  lines. 

b.  Condition  of  roadbed,  ties,  and  rails. 

c.  Number,  types,  condition,  and  nature  of  rolling  stock  and 
other  equipment. 

d.  Number,  length,  and  location  of  passing  tracks  and 
sidings. 

e.  If  line  is  passable  throughout,  and,  if  not,  at  what  points 
and  for  what  reasons  stoppages  of  traffic  may  occur. 

/.  Ruling  grade  and  maximum  curvature. 

g.  Location  and  amounts  of  fuel,  water,  ballast,  and  mainte- 
nance material. 

h.  Facilities  for  repair  and  servicing. 

i.  Locations  favorable  to  construction  of  detours. 

j.  Condition  of  right-of-way  for  marching  troops  along  the 
line. 

k.  Drainage  and  liability  to  overflow  or  wash-out. 

l.  Number,  location,  dimensions,  and  strength  of  tunnels 
and  bridges. 

m.  Location  and  capacity  of  platforms,  ramps,  loading  and 
storage  facilities. 

n.  Signal  communications. 

■ 56.  Useful  Data. — a.  Capacity  of  railways. — A single- 
track  railway  line  in  good  condition  with  ruling  grade  of  1 
percent  and  passing  tracks  at  6 to  10  mile  intervals  can  pass 
10  trains  per  24  hours  in  each  direction,  the  length  of  the 
train  being  fixed  by  the  clear  length  of  sidings  and  the  maxi- 
mum tonnage  hauled  per  train  not  exceeding  1,500  tons. 
Excess  grade  (over  2 percent)  reduces  tonnage  hauled  per 
train  rather  than  number  of  trains  passed.  Capacity  of 
double-track  lines  is  usually  limited  by  capacity  of  facilities 
for  dispatching  and  receiving  trains.  Rule  of  thumb  for 
determining  the  capacity  of  a terminal:  Cars  handled  per  24 
hours  equal  two-thirds  of  total  length  of  track  in  receiving 
or  classification  yard  divided  by  average  length  of  car. 


© FOR  TUNNEL,  SINGLE  TRACK 


FOR  BRIDGES 


RADIUS  VARIES  WITH 
DISTANCE  BETWEEN 


TRACKS 


SUBGRAOC 


6"  DRAIN  PIPE  OF  CAST  I ROn'  s"  OPENING 
© FOR  TUNNEL,  DOUBLE  TRACK 

Figure  67. — Standard  clearance  diagrams  for  bridges  and  tunnels 


/ - 

‘0 

V 

TOP  OP  RAIL^ 

- J " £ / 

^ SUBGRAOC 

J 

r--- 

O 

SPACING  OF  TRACKS  “ 

TO  CONFORM  TO 

RAILWAY  STANDARDS 

8-0* 

J 

0“ — * 

— 4’0“-^ 

.t  7 

° / 

1 v 

\ 

56 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


56 


b.  Gage. — Standard  gage  is  4 feet  8 Vi  inches  measured  at 
point  % inch  below  top  of  rail.  Overgage  on  curves:  A 
inch  per  degree  over  8°  (maximum,  4 feet  9Vi  inches). 

c.  Roadbed. — Width  at  top  of  single-track  embankment: 
15  feet;  width  at  bottom  of  single-track  cut:  14  feet  (plus 
ditches) ; width  at  top  of  double-track  embankment:  27  feet; 
width  at  bottom  of  double-track  cut:  26  feet  (plus  ditches). 
Minimum  spacing  of  adjacent  parallel  tracks:  13  feet  (spac- 
ing increased  on  curves). 

d.  Ties. — Ties  are  8 to  9 feet  long,  by  6 to  7 inches  thick, 
by  8 to  10  inches  wide.  The  normal  spacing  is  20  inches, 
center  to  center. 

e.  Clearance. — The  clearance  shown  in  figure  67  should  be 
departed  from  only  under  exceptional  circumstances. 

/.  Rails. — For  military  use,  85-pound  rails  are  satisfactory. 
Rail  lengths  vary  between  30  and  39  feet  (normal,  33  feet). 

g.  Curves, — Formula  for  simple  railway  curve: 

Y2  unit  chord 

Rad  iUS = nr 

sin  y2  (degree  of  curve)  or 

R=-A£ 

sin  y2  D 

For  unit  chord  of  100  feet,  R=5730/D,  with  R in  feet,  D in 
degrees.  (See  TM  5-235  and  TM  5-236  for  more  complete 
data  on  surveys  and  location.) 


Figure  68. — Method  of  determining  approximate  degree  of  curvature. 


h.  Ballast. — Ballast  is  used  only  when  absolutely  required 
for  support  or  drainage. 

Table  XLV. — Quantity  of  ballast  per  mile  of  standard  gage  one-track 

railway 


Inches  of 
ballast  under 
tie 

Cubic  yards  of 
ballast  per  mile 

4 

1,529 

5 

1,779 

6 

2,032 

7 

2,295 

8 

2,577 

9 

2.863 

10 

3, 137 

Note. — Ties  6 by  8 Inches  by  8 feet,  spaced  20  inches  center  to 
center;  ballast  dressed  even  with  the  tops  of  the  ties  and  sloping 
from  the  ends  of  ties  1 on  4. 


120 


121 


122 


i.  Characteristics  of  rolling  stock.  g 


Table  XL VI. — Dimensions  and  capacities  of  cars 


Capacity 

Weight 
empty 
in  tons 

Dimensions  in  feet 

Type  of  car 

Tons 

Men  (8 
square 
feet  per 
man 
and 
equip- 
ment) 

Ani- 
mals 
(light 
draft 
at  22 
inches) 

Cubic 

feet 

Height 
from 
rails  to 
top  of 
floor 

Outsirlo 

Inside 

Length 
(center 
of  cou- 
plings) 

Width 

Height 

Length 

Width 

Height 

Military: 

20 

24 

13 

12 

3.8 

28 

9.6 

24.2 

8 

8 8 

20 

10 

3.8 

28 

9.0 

24.4 

8 

3.3 

14 

3.8 

28 

9.0 

22  1 

13 

3.8 

28 

9.5 

20. 6 

8 

Typical  commercial:  * 

Box 

30 

38 

20 

2, 750 

18 

3.5 

39.8 

10.3 

14.5 

36 

8.5 

9 

40 

43 

22 

3, 100 

20 

3.6 

44.3 

10.3 

14.5 

40.5 

8.5 

9 

50 

43 

22 

3,100 

24 

44.3 

10.3 

14.5 

40.5 

8.5 

9 

Flat 

40 

18 

42.0 

10.0 

■ml  Jr  » 

40.0 

9 

50 

20 

47.0 

10.0 

■Sfej 

45 

9 

70 

25 

Sl/v* 

62.0 

10.0 

6.7 

50 

9 

Stock 

30 

20 

2,625 

20 

mt 

39.  5 

9. 5 

14.0 

36 

8.5 

40 

2^  625 

22 

39.5 

9.5 

14.0 

36 

8.5 

8.5 

50 

1.  570 

22 

3.7 

44.5 

70 

25 

3.7 

62.5 

10.3 

48 

10.0 

4 

40 

45 

22 

3, 100 

20 

3.6 

44.3 

10.3 

14.5 

14.5 

40.5 

50.5 

8.6 

8.6 

dla.  6. 6 

9 

9 

Tank: 

50 

63 

27 

3,850 

25 

3.6 

54. 3 

10.3 

40 

... 

20 

3.7 

38.3 

9.3 

13. 2 

50 

24 

3.7 

38.3 

9.3 

14.0 

13.5 

13.5 

33 

40.5 

40.5 

8.2 

8.2 

30 

m 

2,570 

28 

3.7 

41.5 

10.0 

7 5 

40 

2,570 

30 

3.7 

43.5 

10.0 

8 

..... 

45 

3.7 

70.0 

10.0 

14.0 

60 

9. 1 

20 

3.7 

38.0 

10.0 

14.0 

90 

3.7 

83.0 

10.0 

14.0 

78. 5 

Passenger  capacity 

2 per 
double 
seat 

3 per  2 
double 
seats 

3 per 
section 

70 

46 

60 

3.7 

72.0 

10.0 

14.0 

63.0 

9.1 

8 

Sleeper,  12  sections  and  drawing 

53 

40 

40 

70 

3.7 

82.5 

10.0 

10.0 

14.0 

74.0 

9.1 

8 

8 

64 

48 

48 

70 

3.7 

82.6 

. 

_ 

' 

1 



All  types  have  similar  variations  in  capacity « 

* Ice  capacity,  4 tons. 

* Ice  capacity,  5 tons. 


cji 

Oi 


CORPS  OF  ENGINEERS  REFERENCE  DATA 


56 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


56-57 


j.  Man-hour  data. 


Table  XLVin. — Rates  of  miscellaneous  tasks  in  railway  construction. 


Man-hours  required  * 
for— 

Task 

Each  100 
linear 
yards 

Each  Job 

16 

32 

16 

256 

*3 

Constructing  turn-out: 

» 192 

*96 

GASOLINE -MECHANICAL  LOCOMOTIVE 

Figure  69. — Standard  locomotives. 

Table  XLVII. — Characteristics  of  standard  locomotives 


1 — 

75-ton  steam 

30-ton  gasoline- 
mechanical 

1,000-ton  train 

500- ton  train. 
250  tons. 

700  feet. 

35  gallons. 
150  gallons. 

600  tons 

1,400  feet 

Fuel  consumption  per  hour 

4,400  pounds  coal 

10  tons  coal 

Water  consumption  per  hour 

3,400  gallons 

124 


■ Material  on  job.  Special  equipment  available.  Grading  previously  completed. 

* Assumes  use  of  12  experienced  men. 

Section  IV 

CONSTRUCTION  IN  WAR 

■ 57.  Reconnaissance  Data. — a.  Requirements  for  aJl  types 
of  construction  sites. — (1)  Sufficient  size  for  present  needs 
and  future  possible  expansion,  with  adequate  room  for  disper- 
sion. 

(2)  Adequate  water  supply. 

(3)  On  or  near  railroad  of  sufficient  capacity  for  supply 
and  personnel  movement. 

(4)  Available  for  lease  (if  not  already  owned  or  leased  by 
the  Government)  for  period  up  to  5 years. 

(5)  Largely  free  from  floods. 

(6)  Adequate  drainage  with  porous  soils. 

(7)  Roads  good  or  potentially  good. 

(8)  Climate  favorable  for  training  contemplated. 

(9)  No  insect  pests. 

(10)  Location  strategically  convenient. 

(11)  Material  and  labor  locally  available  at  reasonable 
prices. 

262736° — 41- 


-9 


125 


57-58 


CORPS  OF  ENGINEERS 


b.  Additional  requirements  for  semipermanent  camp 
sites.— (1)  Accessible  to  adequate  training  area. 

(2)  Accessible  to  suitable  target  range  area. 

(3)  Recreational  facilities  nearby. 

(4)  Grazing  facilities  for  animals  (applies  also  to  re- 
mount depot  sites) . 

Table  XLIX. — Space  requirements  for  preliminary  estimates 


Per- 


Mau. 

Animal. 

Vehicle. 


Space  (square  yards) 


Semiper- 
manent Bivouacs 
camps 


50  50 

50  50 

100  100 


Note. — This  Includes  room  for  roads,  assembly  areas,  and  other 
space  requirements  except  for  training  and  storage.  Oho  ocre 
equals  4,840  square  yards.  Dispersion  and  concealment  are  desirable 
for  bivouacs. 


■ 58.  Semipermanent  Camps. — o..  Requirements.  (1)  Neces- 
sary facilities:  barracks,  messes,  latrines,  baths,  lavatories, 
administration  buildings,  hospital,  guardhouse,  storehouses, 
post  exchange,  officers’  mess,  officers’  quarters,  recreation 
building.  Tents  can  be  used  where  erection  of  buildings  is 
impracticable. 

(2)  Also  necessary  for  horse  units:  stables,  corrals,  water- 
ing troughs. 

(3)  Also  necessary  for  motor  units:  shops. 

(4)  Locate  kitchens,  hospitals,  warehouses,  stables,  motor 
parks,  and  offices  near  roads. 

(5)  Locate  latrine^,  stables,  and  incinerators  away  from 
kitchens  and  mess  halls  to  minimize  fly  and  odor  nuisance. 

(6)  Provide  compact  lay-out  but  allow  for  future  expan- 

S1°(7)  Use  standard  building,  20  by  100  feet,  for  all  possible 
construction  in  semipermanent  camps. 


126 


Table  L. — Bill  of  materials,  standard  building  20  by  100  feet 


REFERENCE  DATA 


58 


. 


t 


A 


Description 

Lumber. 

Do. 

Do. 

Do. 

Do. 

Nails. 

Do. 

Do. 

(spunod) 

iqspAv 

3,111 

2.034 

850 

534 

150 

32 

11 

7 

Feet. 

board 

measure 

fe  88  3 8 $ 

r-  n»*  « *h 

ja 

§ 

a 

3 

8 feet 

12  feet 

12  feet 

12  feet 

12  feet... 

V 

c 

£ 

S 

_c 

cs 

j 

00 

2 by  4 inches 

2 by  4 inches 

7A  by  4 inches 

by  2 inches 

7A  by  6 inches 

20d 

1 

5 

Unit 

Piece 

..-do 

...do 

...do 

...do 

Pound 

—do 

—do 

a ^ 

is 

^ to  to  C CC  r-l 

Item 

1 1 1 I l 

|(lil 
(till 
l 1 1 ■ ■ 

l 1 l 1 1 

(•III 

• l l l I 

« oi  M to 

t- 

00 

127 


metal  caps,  and  cement. 


1 

Table  L. — BUI  of  materials,  standard  building  20  by  100  feet — Con.  oi 


For  corrugated  steel  covered  building  (add  to  bill  No.  1) 

Bill  No.  3. 


Item 

Quan- 

tity 

Unit 

Size 

Length 

Feet, 

board 

measure 

Weight 

(pounds) 

Description 

1 

100 

26 

289 

22 

11 

11 

18 

2 

400 

2i 

8 feet  ...  

534 

2.225 

26 

3.613 

22 

11 

330 

18 

2 

200 

2 

Lumber. 

Nails. 

2^-inch  corrugated  steel  sheets,  black,  28 
gage. 

Nails,  barbed,  roofing,  10  gage. 

Rivets. 

Building,  paper. 

Wire,  galvanized. 

Staples,  poultry  netting. 

Laths. 

Nails  15  gage. 

2 

Pound  . 

20d  

3 

8 feet 

4 

Pound 

Roll 

5 

6 

7 

Pound . . 
do 

No.  16 

8 

34  inch 

Vk  by  inches . 

3d 

4 feet 



10 

Pound.. 

Note  — 

•Materials  included  in  items  Nos.  6,  7, 8,  9 

, and  10  will  be  used  if  insulation  is  required. 

Bill  No.  4. 

For  24  sash 

1 

48 

12  feet.... 

144 

600 

Lumber. 

2 

1 

Roll  

100  feet 

50 

3 

3 

4d_. 

394 

For  2 pairs  of  doors,  type  1 


1 

4 

Piece 

2 

23 

Piece 

383 

3 

2 

Piece 

4 ... 

1 

Piece 

H inch 

3 feet 

Wood  dowel. 

5 ... 

8 

Each 

6. 

IM 

Pound 

frd 

1M 

T-hinges  and  necessary  screws. 
Nails. 

7 

>4 

Pound 

4-d  

8 

1 

Piece  ... 

96  inch 

9 

2 

Each  

Screw  eyes,  wire,  #106  Sargent  or  equal. 

10 

4 

Each 

Bill  No.  6. 

For  50  two-man  bunks 

1 

100 

Piece 

2 

300 

Piece 

Lumber. 

3... 

136 

Piece 

?6  by  6 inches... 

8,  < 50 
2,266 

4 

26 

Piece 

70 

5 

100 

Piece 

6. 

84 

Piece 

168 

Do. 

7 

28 

Pound  ... 

8-d 

Do. 

8 

20 

Pound 

frKl 

9 

4 

Pound 

3-d.. 

Do. 

CORPS  OF  ENGINEERS  REFERENCE  DATA 


Bill  No.  7. 


Table  L. — Bill  of  materials , standard  building  20  by  100  /eet— Con. 

Electrical 


Item 

Quan- 

tity 

Unit 

Size 

Length 

Feet, 

board 

measure 

Weight 

(pounds) 

Description 

1 

210 

Feet 

5K 

1 

Wire.  R.  C.  S.  B.,  solid  copper. 

Cut-out,  main  line,  plug  fuse,  double  pole. 

Fuses,  plug. 

Socket,  pull,  brass,  S22  (P.  and  S.  cat.  38, 
base  B.  P.). 

Knobs,  split  porcelain,  with  nail  and 
leather  washer. 

Tubes,  porcelain. 

Lamps,  Mazda,  115-volt. 

Screws,  for  cut-out  and  socket,  No.  8, 
F.  H.  bright. 

Cord,  linen,  with  chain  and  link  tassel 

2 

1 

30  amperes,  125 
volts. 

3 

2 

4 .. 

4 

I K 
7H 

5 

50 

6 

2 

7 

4 

8 

10 

9 

4 

3 feet 

Number  of  pieces  of  wood  sheathing  must  be  adjusted  when  specified  width  is  not  available. 

Allowance  included  for  cutting  waste  only.  To  cover  other  losses  add:  For  lumber,  3 percent  (minimum,  1 piece  each  size);  for  nails, 
rivets,  and  screws,  10  percent. 


CORPS  OF  ENGINEERS 


2 Ply  Roofing  Felt 
32" Wide,  Lopped  37 

%m»6mWooJ 

Sheathing . 

Ve'x4“  Ecve  Strip, 

3"  Overhang 

(From  Frame  J 

WOOD  8 FELT  t p/y  Roofing  Felt 
COVERED  32“ W/de,  L opped  e\ 
Wood  Sheathing 
Under  Felt , 


y*x  ift"  Wood 
Laths  Over  Felt. 

Grade  Level 


,3  Lap  at  ridge 


f fi'se'.o"  Sheets, 
Bent  Over  Ridge. 

27  ft'se'.o"  Sheets. 

3 Jit'  Overhang. 

tr  ftmx  s’-o"  Sheets. 


— 27 /t's  e'.o * Sheets. 


CORR.  STEEL 
COVERED 


Hats 

AH  Sheets  of  29  Gage 

Corrugated  Steel,  Block,  Wood  q re,( 

3 ft  Lops  except  where  covered. 

noted. 

Grade  Level. 


J-  Corn.  Steel 
Covered. 


FRONT  ELEVATION 

SHOWING  ALTERNATE  COVERINGS  AND  FRAME 


SECTION  A-A 

SHOWING  ALTERNATE  COVERINGS  a FRAME 


100-Cf 


s'.  al 


jSJ3- 


3 


. s-e 


JLS— 


a'- o' 


.3:0.. 


t 


9-.Q1 


B’O" 


.3  0 


jl-qL 


*':Q: 


Doors  Type  #/ 
Detail  on  Sheet  k 4 


JL&L 


~2* 1 4“  Window  Post  2“x4*Upright- 


Shdmg  Sosh,  Detail  on  Sheet  03 


r 


25W 

o~ 


~-2-  0/4  RC.S  B.  Wire 


_£U2_ 


EARTH  FLOOR 
Bun  a Detoil  on  Sheet  04 

e£jL 


25W 

--S-- 


25W 

~0~ 


Cut-Out  Overhead 
Detoil  on  Sheet  0 3 - 


..ZlrQl 


Doors  Type  01 
Detail  on  Sheet  i 4 


t 


String  Sosh.  Derail  on  Sneer  0J 


jia:. 


-£a. 


{C.DC-. 


jlil. 


32 


• ,2"x4"  Window  Post  2“e  4" upright 


too'- O' 


B-0 





jcm" 


jLQL 


FLOOR  PLAN 

Figure  70.— Standard  building  20  by  100  feet. 


U S.  GOVERNMENT  PRINTING  OFFICE  : 1941  — 0-282730 


20'0' 


^ liS  UaUtf  1 V - 


ELEVATION  'C-C' 


ELEVATION  "D'CF 


ON  .ORAM  OF  BUNK 


Figure  71. — Bunk  for  one  or  two  men. 


^ 2«4  *12'  Foot  Bloch 

• <• 

T 

END  ELEVATION 

WW1 


SECTIONAL  PLAN 


En  trances  to  be  screened  with  burlap  or  brush  screens, when  necessary. 


NOTE- Omit“Prepared  Roofinq’if  Cover  Strips  are  used 


[bill  for  latri  ne  shelter-wood  roof  1 

Notts 

Sire 

Length 

rrBM 

Items 

34' 

?}  4 

8:0" 

"Vsi 

Sturfa  U <3c  L.End  Girts  fit  Foot  Blocks 

6 

2-4’ 

10-0 

40 

Roof  Rollers 

8 

2*4 

12-0 

64 

Plotesft.  Lower  Girts  on  Sides 

20 

Jfi'b 

it-  6" 

160 

Sheathing  or*  Sides 

49 

/&•  6 

10-  0 

245 

Sheathinq  on  Roof  &E.nds 

6 

12-0- 

24 

Purlins 

40 

Ts-3 

10-0 

IOO 

Str:  ps  for  covering  Roof  ioints  if  used. 

3 Rons 

32  W. 

2 Ply  Prepared  Roof, nq, Noils. Caps.Cem. 

bibs 

20  d. 

4“ 

Nails  for  Framing. 

Slits 

10  d. 

3 •. 

Noils  for  Framing. 

12165 

6 d. 

2X2 

Noils  for  Sheathirtg 

Labor  on  Shelter(woodroof)incl.2  Urinal  Troughs  = 24  Man  Hrs. 


BILL  FOR  12  HOLE  LATRINE  BOX 

No  Pcs 

Size 

Length 

FrSM 

Items. 

4 

2*’*  4 

12- 

32 

Frame 

6 

tvs 

8 0* 

22 

Cover.Toponly 

4 

1 2-0* 

24 

Ltdsond  Two  End  Boards. 
End  Boards, Sides&.Fillers. 

10 

JVV 

10-0 

33 

3 

JVj 

0-0 

6 

Lid  Battens  and  Stop  Blocks. 

1 lb 

20  d. 

4' 

Nails  for  Framing, 

K lb 

ICd. 

3’ 

Mails  for  Framing. 

Nails  for  sheathing. 

Tar  Fb  per  for  Fly-proof  inqtNaib,Cbp5.etc. 
H i ng  es,  Fast  Joi  n T &nece  ssory  screws. 

s lbs. 

ad. 

2% 

i Roll 
24 

32‘W. 

2‘W 

3% 

Labor  = 2a  man  Hours 


BILL  FOR  TWO  URINAL  TROUGHS 

No  Pcs 

size 

Length 

FT.6M. 

Items. 

1 

6*0 

4 

Brocket  Support 

1 

tv  8" 

6-0 

4 

End  Boards 

3 

5»>6' 

IOO 

15 

Trough  and  Splash  Boards 

1 

tv  4" 

6-0 

2 

Bracket 

1 Roll 

32"  w. 

40 14' 

Tar3apcr.Hcovy.incl  Nails, Cement&Cops 

* lb. 

10a. 

3' 

Nails 

1 lb. 

Sd. 

2V 

Nails 

2 

2“ 

Elbows  for  Conductor  Pipe.Galv. 

2 

i" 

2-6" 

Conductor  Pipe.Galv. 

2 

Zm 

4-0 

Conductor  Pipe.Galv 

Labor*  3 man  Hours 


BILL  FOR  METAL  ROOF  ON  SHELTER  IF  USEol 

Nofti 

Size 

Length 

ft.BM 

Items. 

■ 4 _j 

'/ 1 lb. 

27i'w 

"10 

£5iKok 

10-0" 

K 

Corrugated  Steel  Sheets,  No  28  Ga. 
Nails  Barbed  Roofinq 
Lead  Washers 

Bl  LL  FOR  TEMPORARY  LATRINE 

SHELTER 

Notts 

Size 

Length 

frBM 

Items 

14 

l 

1 

2*  4 
4 0. 
4-0 

10.- o' 

21-0" 

3oo' 

93 

La 

Canvas  for  Screening  ;or  Burlap 
)ORs  5 ManHouRS 

F10 ubx  70. — Latrine. 


U S.GOVIANIUNT  PRINTING  OFFICC  : lt4l — 0-2I27H 


'Cooks  Rk 


3o  Tables  -6  Men  to  Vac  I 


AH  Cirli  omi 


Bill  for  15  Standing  Tables^ 


KITCHEN 


PLAN  or  MESS  HALL 

CAPACITY  240  MEN 

(z- 20*  too  Buildings  joined  together) 


INTINC  OFFICE  i 1141  — 0-28273* 


Figure  74.— Standard  building  adapted  for  kitchen  and  mess. 


PLAN 


Cover  top  of  fro  me  with 
one  sheet  of  Golv  Sheet 
Steel,  26  * 96  - No  266a  . 

Lop  over  edges  •' 
and  nail.  ♦ z'  ^ 

\ 


KITCHEN  AND  MESS  HALL 


• ^ Capacity  120  men 


Legs 


Where  Round  Leas 
ore  used  on  dirt  floors. 


ends  w»!l  be  driven 
into  dirt  floor  8-dcep. 


m 

Corner  Detail 


Trim  corner  as  shown 
so  Leg  will  wedge  in  tight 


15  151^12045  Legs  Corne 

49  T?*4  e o iji  frame  & Comer Bnoces 

'lfy,3S  ^^'6“±rJop)  Standing  Table 

I lb  12  % Noils.Roofincj.jJo'jtfd. 

3»lb  6d  Nolls  for  Fnjmirg.  Labor:  1^5  ManHrS. 

15  2 0 i*o  ftound  Leqs  if  used. 


REFERENCE  DATA 


58-59 


I Z OVERMANS 


QwOuND  Line 


FOOTINGS  itf&QL 


Figuke  77. — Open-sided  storage  shed. 


■ 59.  Hospitals. — a.  Provide  hospitalization  at  station  hospi- 
tals for  5 percent  of  troops  in  the  area.  Provide  hospitali- 
zation at  general  hospitals  for  approximately  10  percent 
additional  of  troops  in  theater  of  operations. 

b.  Place  latrines,  feces  destructor,  and  morgue  well  away 
from  other  buildings,  where  odor  and  fly  nuisances  are  mini- 
mized. 

c.  Provide  road  access  to  wards,  operation  rooms,  clinics, 
storehouses,  kitchens,  and  administration  buildings. 

d.  Use  tents  where  building  construction  is  not  feasible. 

e.  In  estimates,  allow  for  floors  in  wards,  operating  rooms, 
clinics,  kitchens,  dining  rooms,  and  administration  buildings. 


AREA 


CORPS  OF  ENGINEERS 


...  ... 

— no  loo — » - voo — — too  -r* — r 


Figure  78. — Typical  lay-out  for  250-bed  station  hospital. 

■ 60.  Depot  Lay-out. — a.  Lay  out  warehouse  area  in  sec- 
tions with  ladder  track  on  each  side  connected  by  house 
tracks  about  1,700  feet  long. 

b.  Space  house  tracks  150  feet  apart. 

c.  Place  warehouses  on  one  side  of  each  house  track.  Pro- 
vide open  storage  on  opposite  side. 

d.  Provide  fire  breaks  50  feet  wide  between  open  and  cov- 
ered storage  areas. 

e.  Store  as  many  articles  as  possible  in  the  open. 


»"  * 

2 Union  SGalv.Pipe 

Note:;  All  partitions  full  height.  Flooring  thruout  building.  .-Sliding  sash  3i-3’'*3,-3 


W9  OCNOTES  WAUWA! 


nBlji 

— 

... ... ' 

. | M 

Studding -ii  spaces <S  8 =68-o 


STATION  HOSPITAL 

92FT  Hospital  Ward -(  Above) 

NormalCapacity  25  Patients 


GENERAL  HOSPITAL 

184 FT  HospitalWard- (Below,) 

NormalCapacity  50  Patients 


V DENOTES  a'V  GALV  STEEL  VENTILATORS.  W.B  DENOTES  WALL  BOARD. 

1 2*- o'- 4* 8-E- — J 2*4"SllL.  2*4'!-StuDS' rJ-3"*3-3"  SLIDING  5 ASH. 


3|SH£LVES;|ST  3 ABOVE  FLOOR.  OPENING  24*24 

4>L>4UPABmi^^HE^TV 


-t 6SPACES  (5’  g‘=  43-0p  Studding  Spacing  - 

J J. II 


-x6SP@8Mfi 


|'m8'4 8' 


s' »H-6SPS&8’=4S'— 3 SPACES  @ 8'=  24  o"- 

-62-6" 


-Tr. b Ws '84 

^2  DRAIN.  l£5UPPLY.  4 BlBBS.  FLOORS  THRUOUT  BUILDING.  ROOF  VENTS  TO  BE  PROVIDED  BY  EITHER  GALV  VENTILATORSOR  OPEN  RIDGE  WITH  LOUVRES 

Figure  79. — Hospital  wards. 


__ 


282736°— 41  (Face  p.  136) 


Defence  between  runnino  trucks  sufficient 
to  provide  room  for  expansion  in  reception 


yord to  three  times  oriqinot  requirements. 


NOTE.: 

Receiving  and  Departure  Yards  may  be 
Seperated  from  Warehouse  Area  if 
necessary  for  protection  aqainst  air  bombinq 


Receiving  Yard 


Mo/n  Line 


Body  Tracks 


Room  for  expansion 


Roadwo j 


House  Track 


Warehouse 


Maximum 
16°  Curve 


DEPARTURE  YARD 


Roadwo j 


NOTE - 

Receiving  ond  Departure  Yords  may  be 
separated  from  Warehouse  Area  if 
necessary  for  protection  agoinst  air  bombing. 


'•Tom  around  may  be 
replaced  by  o Y“ 


Road  wo  y 

Room  for  expansion 


CUT  LINE 


61  CORPS  OF  ENGINEERS 

■ 61.  Advanced  Airdromes. — a.  Facilities  necessary. — Land- 
ing field,  airplane  parking  areas,  personnel  shelters,  limited 
repair  shelters,  ammunition  dump,  truck  park,  gasoline 
storage  area. 

b.  Requirements. — (1)  Provide  landing  strips  of  hard, 
well-drained  ground.  Provide  at  least  two  strips,  3,000  feet 
by  500  feet,  one  parallel  to  prevailing  wind  and  one  to  storm 
wind.  Add  250  feet  in  length  for  each  1,000  feet  elevation 
above  sea  level.  Make  grades  less  than  2l/2  percent,  with 
no  changes  over  one-half  percent  in  any  100-foot  inter- 
val. Cut  grass  to  15-inch  height  or  less.  Provide  boundary 
lighting. 

(2)  Park  planes  under  natural  cover. 

(3)  Shelter  personnel  in  existing  buildings  or  in  tents. 

(4)  Provide  operations  office  and  machine  shop  in  con- 
cealed small  buildings. 


138 


REFERENCE  DATA  61-62 

(5)  Locate  ammunition,  gasoline,  and  truck  storage  areas 
with  view  to  localizing  damage  from  explosion. 

(6)  Make  maximum  use  of  camouflage  and  concealment. 

■ 62.  Useful  Data. 


Table  LI. — Personnel  for  erection  of  standard  building  20  by  100 

feet 


Operation 

Number  of 
men 

24 

36 

to 

w 

36 

36 

36 

36 

21 

* All  available. 

* 9 at  each  end. 


Table  HI. — Unit  requirements  for  theater  of  operations  facilities 


Facility 

Size  of  typical 
unit 

Number  of  men  per 
typical  unit 

Basic  ratio 

Barrack.. 

20  feet  by  lOOfeet. 

50  (single  bunks) 

40  square  feet  per  man. 

20  feet  by  92  feet 
20feet  by  184  feet. 
20  feet  by  8 feet. 

(12  seats). 

20  feet  by  21  feet. 

20 feet  by  12  feet. 

100  (double  tier 
bunks)  (in 
emergency). 

25 

20  square  feet  per  man. 

(ail  facilities). 

60 

240-480 

1 scat  per  20-40  men. 

1 bathhouse  per  battalion 
area. 

1 lavatory  per  company. 

240 

100-200 

139 


62-63 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


63-64 


Table  Lin. — Approximate  man-hours  for  construction  under  average 
conditions 


Type  of  construction 


Man-hours 


Standard  barracks  (no  floor),  20  by  100  feet 

Type  A floor 

Type  B floor 

92-foot  hospital  ward: 

Type  A floor 

Type  B floor 

184-foot  hospital  ward: 

Type  A floor 

Type  B floor - 

Mess  hall,  20  by  100  feet  (no  floor) — 

Latrine,  12-seat 

Bathhouse: 

Concrete  floor 

Wood  and  corrugated  iron  floors 

Open-sided  storage  shed  (216  feet  long) — 

SO  bunks  (2-man) - 

Camp,  1,000-man  unit,  buildings  only  (all  floors  type  A) . . . 
Station  hospital,  buildings  only  (250-bcd)  (all  floors  type  A) 

General  hospital,  buildings  only  (all  floors  type  A) 

Camp,  triangular  infantry  division 


270 

360 

590 

335 

550 

670 

1,090 

330 

50 

225 
200 
300 
200 
13,500 
10,000 
28,  750 
165,000 


Section  V 
WATER  SUPPLY 

■ 63.  General. — a.  Methods  of  supply. — In  the  theater  of 
operations  water  is  procured  locally  by  using  organizations 
wherever  practicable.  However,  when  local  supplies  are  lim- 
ited or  unsatisfactory,  engineer  personnel  install  and  operate 
the  necessary  water  supply  facilities. 

b.  Responsibility. — Under  the  latter  conditions  engineers 
are  responsible  for  the  quality  and  quantity  of  water  supplied 
and  for  delivery  to  the  point  where  it  is  distributed  to  using 
organizations.  Medical  personnel  assist  as  may  be  necessary 
for  laboratory  examinations  and  sanitary  inspections.  Han- 
dling of  water  in  organization  water  containers  and  sterilizing 
bags,  and  in  the  canteen  of  the  individual  soldier,  is  the  re- 
sponsibility of  organization  commanders,  acting  with  the 
advice  and  assistance  of  attached  medical  personnel. 


c.  General  water  supply  duties  of  engineers. 

(1)  Reconnaissance  and  collection  of  data. 

(2)  Development  of  sources. 

(3)  Purification. 

(4)  Construction  and  operation  of  establishments. 

(5)  Transportation  to  distributing  points. 

d.  Water  supply  activities  of  unit  engineers. — In  addition  to 
the  general  engineer  water  supply  duties,  unit  engineers  are 
responsible  for  the  following  specific  activities  within  their 
areas: 

(1)  Recommendations  as  to  methods  of  supply,  quantity  of 
water  to  be  supplied,  and  conservation  of  water. 

(2)  Collection  and  transmission  to  higher  echelons  of  data 
pertaining  to  water. 

(3)  Enforcement  of  water  discipline  at  water  supply  points. 

(4)  Regulation  of  traffic  at  water  supply  points. 

(5)  Posting  of  signs  to  indicate  safe  and  unsafe  water. 

(6)  Preparation  of  maps  and  sketches  to  show  locations  of 
water  supply  points. 

(7)  Maintenance  of  records  of  water  supply  establishments 
in  the  area. 

(8)  Arrangements  with  higher  engineer  echelons  for  the 
delivery  of  water  by  truck,  railway,  or  pipe  line  when  local 
supplies  are  inadequate. 

e.  Basic  considerations. — (1)  Camouflage,  defense  against 
air  and  chemical  attack,  and  wide  dispersion  of  water  supply 
points  are  provided  insofar  as  possible. 

(2)  Water  supply  work  in  forward  areas  is  taken  over  by 
engineers  of  rear  echelons  whenever  time  and  existing  condi- 
tions permit. 

(3)  General  engineer  troops  normally  execute  all  engineer 
water  supply  tasks,  except  those  involving  the  transportation 
of  water  by  truck  or  railway  and  the  operation  of  purification 
trucks. 

■ 64.  Water  Supply  Points. — a.  Factors  to  be  considered  in 
selecting  water  distributing  points. — (1)  Proximity  to  kitchens 
and  troops  to  be  supplied. 

(2)  Accessibility  to  water  source. 

(3)  Safety  from  enemy  light  artillery. 


140 


282736”— 41 10 


141 


64 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


64 


(4)  Concealment  from  enemy  air  and  ground  observation. 

(5)  Parking  space  for  waiting  vehicles. 

(6)  Situation  with  regard  to  general  scheme  for  traffic 
control. 

(7)  Existence  of  a natural  elevation  suitable  for  installation 
of  storage  tanks. 

(8)  Hardness  of  ground  and  natural  drainage. 

(9)  Type  of  containers  to  be  filled. 

b.  Lay-out  of  water  distributing  points. 


Table  LIV. — Man-hours  for  installing  a water  distributing  point 


Task 

Man- 

hours 

required 

Size  of 
party 
(squads) 

Remarks 

| 

Erect  timber  trestle  platform 

16 

1 or  2 

Materials  at  tho  site  using 

for  3,000-gallon  canvas  tank. 

power  tools. 

Erect  3,000-Ballon  tank 

2 

1 

After  platform  is  constructed. 

Set  up  pump  and  hose 

1 

W 

Install  260-gallon  animal  water- 

1 

ing  tank  and  hand  pump. 

c.  Organization  of  water  distributing  points. 


Table  LV. — Type  organization  for  operating  a water  distributing 

point 


Task 

Size  of  party 

Remarks 

2 shifts  of  M squad  each. 

2 shifts  of  1 man  each. 

3 shifts. 

Do. 

Operatiug  power  pump  — 

2 men 

Notes. — 1.  Organizations  are  supplied  with  10-gallon  milk  cans 
for  carrying  water.  A 1 Vi -ton  truck  will  carry  30  such  cans.  At 
the  distributing  point  the  cans  may  either  be  filled  on  the  truck 
with  multiple  hoses  or  replaced  from  a reserve  of  filled  cans. 

2.  Animals  ordinarily  are  watered  from  water  basins  rather  than 
directly  from  a stream.  A group  of  10  can  drink  from  the  standard, 
circular,  260-gallon  basin  in  about  5 minutes.  Hose  liable  to  damage 
should  be  elevated  or  buried.  Drainage  ditches  and  spread  gravel 
will  remedy  muddy  conditions. 


CORPS  OF  ENGINEERS 


■ 65.  Water  Tank  Platform. 


V x c 
'ttus ' 


'xf'XH' 


Figure  83— Timber  trestle  platform  for  the  3,000-gallon  canvas 
storage  tank. 


REFERENCE  DATA 


66-67 


■ 66.  Standard  Pumps. 


Table  LVI. — Standard  pump  characteristics 


Type 

it? 

||| 

Size  of 
connections 
(inches) 

Horse- 
power  of 
motor 

Speed  of 
pump 
(revolu- 
tions per 
minute) 

Standard  portable,  centrifugal 1 

1 55 

* IH 

2h 

2.000 

Purification  truck  * 

< 100 

(•) 

14 

2,000 

> The  pump  issued  with  the  portable  purification  unit  is  interchangeable  with  the 
standard,  portable,  centrifugal  pump;  these  data  are  applicable  also  to  the  portable 
purification  unit  when  it  is  operated  as  a simple  pump. 

• When  operated  as  a simple  pump. 

* Against  a total  head  of  50  feet  (including  15-foot  suction  lift). 

* Against  a total  head  of  90  feet  (including  a 20-foot  suction  lift). 

< if  bushing  is  removed  this  pump  may  be  used  with  2-inch  connections. 

• Purification  truck  has  a 3-inch  pump.  Actual  intake  connection,  however,  is 
reduced  by  bushing  to  2H  inches;  discharge  connection  is  reduced  to  2 inches. 

■ 67.  Water  Reconnaissance  Report. 

Organization 

Place 

Date 

1.  Location  of  water  source:  Map ; map  coordinates 

; local  name 

2.  Date  and  hour  inspected 

8.  Well,  spring,  stream,  lake,  pond  (line  out  terms  not  applicable) . 


4.  Rate  of  flow gallons  per  day. 

5.  Character  of  water;  Clarity ; taste 

odor 

6.  Temperature  of  water °F. 


7.  Result  of  tests  (if  tests  Impossible  at  time  of  inspection,  take 
sample  of  water  as  prescribed  on  back  of  sheet)  (latest  report  of 
local  Board  of  Health,  if  available) . 


8.  Location  of  possible;  sources  of  pollution. 


9.  Possibility  of  chemical  contamination  (chemical  warfare  agents, 
poisoning,  etc.) 


10.  Accessibility  to  railroad,  highway,  or  trail. 


11.  Well. 

a.  Type  (dug,  driven,  drilled,  or  bored)  (for  characteristics  see 
table  LIX,  FM  5-35). 

b.  Diameter:  top feet;  bottom feet. 

c.  Depth  of  well feet. 


145 


/ 


67  CORPS  OF  ENGINEERS 

d.  Depth  of  water feet. 

e.  Distance  from  surface  of  ground  to  water  surface, 
feet 

/.  Type,  condition,  and  depth  of  casing  or  lining 


~q~  Present  method  of  recovering  water - 

h.  Protection  provided  against  entrance  of  surface  water  (coping, 
watertight  basin,  ditching,  etc.) 


a.  Protection  provided  against  entrance  of  surface  water  (coping, 
watertight  basin,  ditching,  etc.) 


b"  Present  method  of  delivering  water — 

a3  Sketch1  of  cross  section  (show  width,  maximum  depth,  and 
height  of  banks  above  water  surface)  (reference  to  photograph,  if 

one  is  made).  „ . . 

b.  Surface  velocity feet  Per  second. 

c.  Nature  of  bed 

d.  Nature  of  banks 

14  Existing  installations. 

a.  Purification  facilities  (sedimentation  tanks,  chlorinating  appa- 
ratus, filter,  etc.) 

b.  Pumps. 


o i Intake  con- 

Rizo  Speed  (rev-  neetion 

Type  (horse-  olutions  per  (sjz0.  ftn(j 

power)  minute)  type) 

Discharge 
connection 
(size  and 
typo) 

Capacity 
(gallons 
per  day) 

1 

1 

c.  Engines. 

Type 

Size  (horse- 
power) 

Speed  (revo- 
lutions per 
minute) 



e.  Storage  facilities. 

Type 

Elevation 

(feet) 

Capacity 

(gallons) 



] 

— 

146 


REFERENCE  DATA 


67-68 


/.  Pipe-line  lay-out  (draw  sketch  showing  arrangement,  kind, 
lengths,  and  sizes  of  pipe,  elevations,  and  heads  of  water) . 

g.  Condition  of  existing  Installations 


15.  Proposed  development. 
a.  Description 


b.  Material  avallable. 


c.  Material  required . 


d.  Man-hours  required. 


(Signature) 


(Grade  and  organization) 

Note. — Back  of  sheet  may  be  used  for  sketches  or  additional 
information. 

The  following  instructions  should  be  printed  on  the  reverse  side 
of  the  form: 

INSTRUCTIONS  FOR  TAKING  SAMPLES  OF  WATER 

If  sample  Is  to  be  used  for  chemical  examination  only: 

1.  Use  a clean  glass  bottle,  holding  from  2 quarts  to  a gallon, 
with'  a well-fitting  stopper  or  a clean,  unbroken  cork. 

2.  Rinse  out  the  bottle  two  or  three  times  with  the  water  to  be 
sampled. 

3.  In  sampling  a well,  support  the  bottle  in  a string  or  wire 
cradle,  weighted  at  the  bottom.  Lower  the  bottle  until  the  neck 
Is  2 or  3 Inches  below  the  surface.  It  is  advantageous  to  attach 
the  stopper  to  a separate  string,  so  the  bottle  can  be  opened  below 
the  surface  of  the  water.  In  sampling  a stream  or  pond,  hold  the 
bottle  so  the  neck  Is  well  below  the  surface.  Allow  the  bottle  to  fill. 

4.  Insert  stopper  or  cork,  stretch  a clean  cloth  over  It,  and  tie 
down  the  cloth  below  the  flange  of  the  neck. 

5.  Label  the  sample. 

If  the  sample  Is  to  be  used  for  bacteriological  examination: 

1.  Use  a sterilized  bottle  and  stopper.  Never  use  corks. 

2.  Avoid  touching  the  neck  of  the  bottle  or  the  stopper  with  the 
fingers. 

3.  Before  removing  the  stopper  and  after  filling,  the  neck  of  the 
bottle,  and  the  tap  or  spout  from  which  the  sample  is  taken,  should 
be  heated  In  a clean  flame  (alcohol  torch)  to  just  over  the  boiling 
point  of  water  (212°  F.). 

Precautions:  Never  let  the  water  entering  the  sample  bottle  flow 
over  the  hand.  Before  taking  a sample  from  the  spout  of  a pump 
or  from  a tap,  allow  water  to  waste  for  a time. 

■ 68.  Estimating  Quantity  of  Water  at  Sources. — a.  Wells. — 
Draw  the  water  level  down  a measured  distance  by  pumping, 
note  time  required  for  surface  to  reach  its  original  level,  and 


68 


68-69 


CORPS  OF  ENGINEERS 

compute  capacity  in  gallons  between  the  two  levels;  or  run  a 
pumping  test,  using  containers  of  known  volume. 

b.  Springs. — Note  the  time  required  to  fill  a container  of 
known  capacity  or  measure  the  flow  of  the  outlet  stream. 

c.  Streams. — Determine  the  flow  by  Q~av  where  Q is  the 
quantity  of  flow  in  cubic  feet  per  second,  a the  area  of  cross 
section  of  the  stream  in  square  feet,  and  v the  mean  velocity 
(%  of  surface  velocity  in  the  main  current)  of  the  stream. 
A rectangular  weir  built  of  planks  can  be  used  for  measuring 
the  flow  in  small  streams.  (See  table  LVTI.) 


Table  LVII. — Discharge  over  a sharp  crested  rectangular  weir  12 
inches  wide 1 


Depth 

(inches) 

Gallons 
per  minute 

Depth 

(inches) 

Gallons 
per  minute 

Depth 

(inches) 

Gallons 
per  minute 

x 

3(1 

454 

375 

8)4 

900 

m 

60 

« 

405 

854 

939 

1)4 

66 

5)4 

436 

9 

978 

m 

84 

6)4 

468 

9)4 

1,020 

2 

102 

654 

500 

94 

1,062 

2 W 

122 

6 

533 

954 

1, 104 

2)4 

143 

6)4 

667 

10 

1, 147 

254 

165 

6)4 

601 

10M 

1,190 

3 

188 

6)4 

636 

10)4 

1,234 

3)4 

212 

7 

672 

1054 

1.279 

3)4 

237 

7)4 

708 

11 

1, 323 

354 

263 

7)4 

745 

11)4 

1,  369 

4 

290 

754 

783 

11)4 

1,414 

4)4 

317 

8 

821 

1154 

1, 461 

4)4 

346 

8)4 

860 

12 

1,508 

* Depth  Is  measured  from  crest  of  weir  to  surface  of  water  Impounded  by  weir. 


d.  Artesian  wells. — Measure  the  height  of  the  jet  from  the 
top  of  the  vertical  well  pipe  and  obtain  flow  from  table  LVIII. 
For  pipe  diameters  not  listed,  Q varies  approximately  as  the 
square  of  the  diameter. 


REFERENCE  DATA 


Table  LVIII. — Flow  of  artesian  wells  in  gallons  per  minute 


Height  of 
jet  (inches) 

Diameter  of  pipe  (inches) 

Height  of 
jet  (inches) 

Diameter  of  pipe  (inches) 

1 

2 

3 

1 

2 

3 

Vi 

3.96 

15.6 

35.6 

15 

22.0 

87.8 

198 

1 

5.  GO 

22.4 

50.4 

20  

25.4 

102 

228 

2 

7.99 

32.0 

71.9 

30  . 

30.9 

123 

278 

4 . 

11.3 

45.3 

102 

40.. 

35. 8 

142 

323 

6 

13.9 

55.5 

125 

60  ... 

43.8 

175 

394 

8 

16.0 

64.0 

144 

108  .. 

58.9 

236 

531 

10 

17.9 

71.6 

161 

144 

68.0 

272 

612 

■ 69.  Development  of  Sources. — a.  Dams. — A type  design  for 
a small  dam  (usually  not  over  5 feet  in  height)  is  shown  in 
figure  84. 


|< — 2'  o"  to  2'  6" — 


PICKETS  WIRED 
TOGETHER 


CORRUGATED 
IRON  SHEETS 


WOOD  OR  ANGLE 
IRON  PICKETS 


WATER  LEVEL 


SAND  BAGS 
FILLED  WITH 
MUD 


4/1  SLOPE 


4/1  SLOPE 
WATER  LEVEL 


BED  OF  STREAM 

^7 


FOR  LOW  DAMS  A SINGLE  ROW 
OF  SHEET  PILING  BETWEEN  TWO 
ROWS  OF  WALING  WITH  CLAY 
BACKING  WILL  SUFFICE  IF  WELL 
DRIVEN. 


Figure  84. — Design  for  a small  dam. 


1 


148 


149 


69 


CORPS  OF  ENGINEERS 


I 


b.  Springs. — The  following  steps  should  be  taken  In  develop- 
ing a spring: 

(1)  Provide  a substantial  collecting  basin. 

(2)  Walls  of  water-tight  casing  should  extend  1 to  2 feet 
above  and  below  ground  surface  to  exclude  surface  wash. 
V-shaped  ditches  constructed  on  the  up-hill  side  of  the  spring 
Will  assist  in  diverting  surface  wash. 

(3)  Provide  a tight  cover  to  keep  out  dust,  leaves,  etc. 

(4)  Prohibit  dipping  of  buckets  or  containers  in  spring. 

(5)  Supply  water  by  pipe  to  storage  tank  or  point  of 
delivery. 

c.  Wells. — (1)  Types. — Based  on  the  method  of  construc- 
tion, wells  are  classified  as  shown  in  table  LIX. 

Table  LIX. — General  characteristics  of  wells 


Remarks 


See  fig.  85  for  de- 
velopment of  exist- 
ing well. 

Can  be  used  in  quick- 
sand if  equipped 
with  si>ccial  strain- 
er. 

Cannot  be  construct- 
ed in  solid  earth 
containing  rock 
strata  or  large 
boulders. 

Used  in  bard  material 
or  where  water 
exists  at  great 
depth. 


150 


REFERENCE  DATA 


69 


Trooyh  for  filling  water 
carts  a.  canteen  filler 


Note. — If  pump  should  require  priming,  use  purified  water  only 
for  this  purpose. 


Figure  85. — Development  of  existing  well. 

(2)  Increasing  yield  of  existing  toeUs. — One  or  more  of  the 
following  means  can  be  used  to  increase  the  flow  of  existing 
wells: 

(a)  Increase  diameter. 

<b)  Deepen  well. 

(c)  Set  off  charge  of  explosives  at  bottom  of  well. 

id)  Clean  strainer. 

(e)  Pack  pocket  around  strainer  at  bottom  of  well  with 
gravel  to  prevent  entrance  of  fine  materials. 

(/)  Construct  infiltration  galleries  (or  ditches)  across  line 
of  flow  leading  to  well. 


k 


151 


/ 


70  CORPS  OF  ENGINEERS 

■ 70.  Purification. — a.  General. — All  water,  whatever  the 
source,  should  be  considered  dangerous  until  it  is  tested  and 
designated  as  safe.  Regardless  of  apparent  absence  of  con- 
tamination, however,  water  should  always  be  disinfected  be- 
fore being  used  for  drinking  purposes.  For  a summary  of 
common  methods  of  water  purification,  see  table  LX.  An 
improvised  purification  plant  is  illustrated  in  figure  86. 


Figure  86. — Improvised  purification  plant. 


b.  Standard  purification  units. — (1)  The  M3  purification 
truck  has  a gross  weight  of  8 tons.  When  filtering  average 
water  in  the  field  this  unit  has  an  approximate  output 
capacity  of  70  gallons  per  minute.  It  is  equipped  with  con- 
nections for  2 ‘/2-inch  intake  and  2-inch  discharge  hose.  The 
truck  itself  is  a 2 Vi-ton,  6 by  6 standard  quartermaster  truck. 

(2)  The  M1940  portable  purification  unit  has  a gross  weight 
of  750  pounds.  Its  capacity  for  filtering  average  water  in  the 
field  is  approximately  10  gallons  per  minute.  Both  suction 
and  discharge  connections  are  for  1%-inch  hose.  The  unit 
may  be  transported  in  any  standard  truck  or  trailer  of  Vi -ton 
capacity  or  larger. 

c.  Water  tests. — The  purification  truck  has  facilities  for 
making  water  tests  to  determine  turbidity,  pH  value,  and 
residual  chlorine  content.  The  portable  purification  unit 
includes  facilities  for  determining  pH  value  and  residual 
chlorine  content. 


152 


Table  LX. — Methods  of  water  purification — Continued 


Method 


Agent 


Effect  on  quality 


Disinfection. 


Pure  chlorine  or  chlorino 
contained  in  the  form  of 
calcium  hypochlorite,  so- 
dium hypochlorite,  or 
chlorinated  limo  (bleach- 
ing powder). 


When  chlorine  is  employed  a sufficient  amount  must  be 
added  to  produce  a residual  chlorine  content  o f 1.0  part 
per  million.  Allow  30  minutes  boforo  water  is  used  for 
drinking,  and  before  residual  chlorine  test  is  made. 
Hypochlorite  for  Lyster  bags  is  issuod’in  sealed  glass 
tubes.  Hypochlorite  as  supplied  commercially  usu- 
ally contains  from  GO  to  70  percent  free  chlorine  by  weight. 
Chlorinated  lime  usually  contains  from  20  to  30  per- 
cent free  chlorino  when  fresh. 

Two  and  one-half  teaspoonfuls  of  standard  7 percent  tinc- 
ture of  iodine  are  used  for  one  Lyster  bag  (36  gallons); 
2 drops  are  used  per  quart  (canteen)  of  water.  Wait 
30  minutes  after  mixing  before  drinking. 

At  least  10  minutes  of  steady  boiling  is  required  to  steril- 
ize water. 


Destroys  most  bacteria 


Tincture  of  iodine 


Softening. 


Removes  or  reduces  hard- 


Reduces  carbonate  hardness.  Converts  hardness  due  to 
magnesium  compounds  to  form  which  can  bo  removed 
by  soda  ash. 

Reduces  noncarbonate  hardness,  except  when  due  to  mag- 
nesium compounds.  (For  magnesium  compounds  see 
remark  under  hydrated  lime.) 

All  types  of  hardness  may  be  removed  by  percolation  of 
water  through  zeolite  filters. 

Prolonged  boiling  will  reduce  hardness  due  to  bicar- 
bonates. 


Hydrated  lime 


Soda  ash 


Zeolite  minerals. 


Activated  carbon 


Ordinarily  applied  in  mixing  basins  prior  to  sedimenta- 
tion or  filtration,  either  separately  or  together  with 
coagulant.  Often  applied  in  form  of  black  alum  or  ac- 
tivated alum  (alums  with  activated  carbon  added  dur- 
ing manufacture).  Also  used  as  filtering  material. 
Dosage  of  carbon  ranges  from  0.5  to  50  or  more  parts 
per  million. 


Accomplished  by  passing  water  through  the  air  as  mist 
or  small  droplets.  The  finest  spray  is  the  most  effec- 
tive. Also  accomplished  by  forcing  compressed  air 
into  water,  or  by  the  introduction  of  air  through  nega- 
tive pressures  created  when  water  flows  through  a con- 
stricted passageway. 

Pouring  boiled  water  from  one  sterile  container  to  another 
will  help  to  eliminate  the  flat  taste. 


Distillation. 


Removes  impurities  having  boiling  points  greater  than 
water.  Often  employed  to  purify  excessively  contam- 
inated water.  Requires  elaborate  plant  and  large 
quantities  of  fuel.  Other  methods  of  evaporation  and 
recondensation  will  achieve  similar  results. 


* For  water  containing  bicarbonates,  or  up  to  400  parts  per  million  of  chlorides  and  sulphates,  ion  exchange  materials  such  as  zeokarb 
or  deacidite  (or  equivalent)  can  be  used  alone  or  in  combination  for  demineralization. 


Eliminates  certain  tastes 

and  odors  and  reduces 
chemical  contamination 
by  adsorbing  dissolved 
gases. 

Reduces  odors  and  tastes 

Air 

due  to  dissolved  gases;  re- 
moves objectionable  gases 
such  as  CO,;  adds  oxygen 
for  oxidation  of  ferrous  iron 
to  assist  in  its  precipita- 
tion. 

Converts  salt  water  into 

Beat* 

fresh  water. 

CORPS  OF  eng: 


71 


CORPS  OF  ENGINEERS 


■ 71.  Pipe  Flow  Computations. — a.  Manning  formula. — The 
Manning  formula  for  flow  of  water  under  pressure  in  pipes 
is  as  follows: 

0.590  (T-n  «>/* 


Formulas  (2)  and  (3)  are  convenient  forms  for  solving  for 
pipe  discharge  and  for  head  loss  due  to  pipe  friction. 


0 = 0.46 


cfM  s'/1 


Hi=  2.87 


where 

u=mean  velocity  of  water  in  feet  per  second. 
d= diameter  of  pipe  in  feet. 

r—mean  hydraulic  radius  ~ 

4 

l=length  of  pipe  in  feet. 

Hr=  loss  of  head  in  feet  in  length  l. 


s= mean  slope  of  hydraulic  gradient  in  distance  ' 


Q= discharge  of  pipe  in  cubic  feet  per  second. 
n=- Manning  coefficient  of  roughness,  varying  directly  with 
the  degree  of  roughness  of  the  pipe.  The  value  for 
cast  iron  pipe  commonly  falls  between  0.013  and 
0.015,  with  extreme  values  of  0.011  and  0.017. 
b.  Nomograph. — A straight  line  on  the  nomograph  given  in 
figure  87,  determined  by  any  two  variables  in  the  Manning 
formula,  will  pass  through  the  corresponding  values  of  the 
other  two  variables. 


72 


CORPS  OF  ENGINEERS 


72.  Water  Requirements. 


Tables  LXI. — Daily  water  consumption  in  gallons 

(These  estimates  must  be  modified  according  to  circumstances,  especially  in  hot 
climates.  The  maximum  requirements  may  exceed  those  of  the  average  month  by 
from  15  to  40  i)ercont  and  those  of  the  average  day  by  over  100  percent.] 


Unit  consumer 


sumption). 


Ilorse  or  mule,  large 
domestic  animnls 
(consumption  per 
animal). 


Motors  (consumption 
per  vehicle). 


tion  per  locomotive). 


Conditions  of  use 

Gallons 
per  unit 
per  day 

In  combat: 

Minimum-  - 

H to  M 

Normal.  

1 

In  bivouac: 

Minimum-  

1 

Normal 

2 

Temporary  camp: 

Minimum.  . ----- 

5 

Normal 

15 

Field  hospital 

25 

Semipermanent  camp 

30 

Permanent  camp 

60 

Permanent  hospital- 

200 

Minimum  - 

3 to  5 

in 

Camps  and  canton- 

30  to  50 

ments. 

Level  and  rolling 

H to  H 

country. 

Mountainous  country 

H tol 

Permanent  camps 

30  to  50 

Standard  military 

33, 000 

50,000 

Semipermanent build- 

300 

ings  (consumption 
per  fixture). 

40 

20 

40 

ing  3 days. 


only,  for  periods  not 
exceeding  3 days. 


washing  only. 


baths,  toilets,  etc. 


ing  3 days. 


using  personnel  and 
frequency  of  use. 

Do. 

Do. 

Do. 


REFERENCE  DATA 


73-74 


Section  VI 
ELECTRICITY 

■ 73.  Standard  Generator. — a.  Description. — The  standard 
set  is  a 5-kva.  portable  alternating  current  generator.  Its 
source  of  power  is  a 4-cylinder  gasoline  engine.  The  unit  is 
normally  carried  on  a l‘/2-ton  truck  and  can  be  manhandled, 
on  or  off,  by  eight  men,  although  skids  and  tackle  are  prefer- 
able. 

b.  Capacity. — It  may  be  assumed  for  purposes  of  rough  esti- 
mates that  this  unit  will  supply  from  100  to  115  40-watt  lamps 
or  their  equivalent. 

■ 74.  Military  Requirements. — When  camps  are  lighted  there 
need  not  be  more  than  four  25- watt  lights  per  barrack  (20  by 
100  feet)  and  one  40-watt  light  per  officer.  Electric  lamps 
should  be  provided  in  recreation  halls.  The  forward  eche- 
lon of  an  infantry  division  requires  about  75  lamps  of  40  to  60 
watt  rating.  One  standard  5-kva.  generator  will  supply  this 
requirement.  Requirements  for  other  units  are  about  as  fol- 
lows: 


Table  LXII. — Electric  light  requirements 


Unit 

Approximate 
number  of 
outlets  to  be 
furnished 

Power  in 
kilowatts 
required 

Corps  hoadquarters 

Army  headquarters 

76 

150 

4.5 

0.0 

GHQ 

600 

36.0 

600 

36.0 

10.000-bed  hospital * 

250 bed  hospital  > 

135.0 

4.5 

■ Power  is  for  sterilizing  apparatus,  dentist’s  tools.  X-rays,  etc.,  as  well  as  for  light. 


k\ 


159 


75 


CORPS  OF  ENGINEERS 


■ 75.  Useful  Information. — a.  Power  in  direct  current 
id.  c .)  circuits. — In  a d.  c.  circuit,  power  in  watts  (W)  Is 
equal  to  electromotive  force  (e.  m.  f.)  in  volts  ( E ) multiplied 
by  current  in  amperes  (/) : W=EI. 

b.  Power  in  alternating  current  (a.  c.)  circuits. — In  a.  c. 

circuits,  true  power  in  watts  (W)  is  equal  to  the  product  of 
the  power  factor  in  percentage  (p/)  by  the  e.  m.  f.  in  volts 
(J E)  by  the  current  in  amperes  (/) : W—(pf)  El. 

c.  Ohm’s  law  for  d.  c.  circuits. — In  d.  c.  circuits,  the 
e.  m.  f.  in  volts  (E)  is  equal  to  the  current  in  amperes  (/) 
multiplied  by  the  resistance  in  ohms  (R) : E=IR. 

d.  Units. — (1)  Kva. — The  unit  used  for  measuring  the  ap- 
parent power  of  an  a.  c.  generator  operating  on  circuits  sub- 
ject to  change  in  power  factor  is  the  kilovolt-ampere. 

. . . volt  X ampere 

kilovolt-ampere= iqqo 


(2)  Kw. — The  unit  used  for  measuring  true  power  in  an 
a.  c.  circuit  is  the  kilowatt. 

kilowatt=kilovolt-ampere  X power  factor  (p /) 

(3)  Hp. — The  unit  used  for  measuring  mechanical  work 
is  the  horsepower  (hp). 

1 hp= 746  watts 

(4)  Wire  sizes. — The  unit  used  for  measuring  wire  sizes  is 
the  mil. 

1 mil=.001  inch 


In  tables,  wire  size  is  expressed  in  circular  mils  (cross-sec- 
tional area).  The  wire  size  in  circular  mils  is  the  square  of 
the  diameter  in  mils. 


REFERENCE  DATA 


76 


76.  Form  for  Electrical  Reconnaissance  Report. 


ELECTRICAL  RECONNAISSANCE 


Reconnaissance  party: 


Area Date 

Map Photographs. 


Prime  movers 


Transmission  lines 


Type  

(Steam,  internal  com- 
bustlon,  water 
wheel.) 


(Coal,  oil,  gas.) 
(Amount  on  hand.) 


Type 

(Alternating  or  direct 
current.) 


Number  of  machines. 


Kilovolt  amperes 

Kilowatts Volts 

Amperes  . Power  factor. 


(Feed.) 

Horsepower. 


Frequency 

Revolutions  per  minute . 
Horsepower..  Maker. . 


Type 

(2-wire;  3-wire  Edison; 
1,  2,  3 phase  alter- 
nating current.) 

Current Voltage 

t Alternating  current  or 
direct  current.) 

Conductors 

(8ite  and  material.) 

Location.  ... 

(On  poles  or  below 
ground.) 

Transformers 


General  condition. 


Substation 

(Whether  transformer 
or  synchronous  con- 
verter.) 


Lubricants 

(Kind  and  amount  on 
band.) 


Water  supply 

(Character  and 
amount.) 

General  condition 


Electrical  supplier 


Recommendations 


Location 

Instruments General  kind. 

Interconnections Inventory 

Condition 


161 


77 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


77 


■ 77.  Wiring. 


Table  LXin. — Electrical  characteristics  of  copper  wire 


Brown 
A Sharj  to 
(B.*8.) 
gage 

Cross  section 

Weight,  resistance,  and 
length 

Safe  current-carry- 
ing capacity  in 
ani|>eresfor  lengths 
of  100  feet  or  less 

Diameter 
in  mils 

Area  in 
circular 
mils 

Pounds 
per  1.000 
feet 

Feet  per 
pound 

Ohms  per 
1,000  feet 

Rubber 

insulution 

Bare  or 
weather- 
proof wire 

0000.. 

400. 00 

21 1. 600 

639. 33 

1.56 

0. 04906 

225 

325 

000 

409. 04 

167,805 

507. 01 

1.97 

.061S6 

175 

275 

00 

304.80 

133,079 

402.09 

2.49 

.07831 

150 

225 

0 

324.  95 

105, 592 

319.04 

3.  14 

.09831 

125 

200 

1 

289. 30 

83,694 

252.88 

3.95 

. 12404 

100 

150 

2 

257. 63 

66, 373 

200.54 

4.99 

.15640 

90 

125 

3 

229.42 

52,634 

159.03 

6.29 

. 19723 

80 

100 

4 

204.31 

41,742 

126. 12 

7.93 

.24869 

70 

90 

5 

181.  9-1 

33, 102 

100.01 

10. 00 

.3x361 

55 

80 

6 

162. 02 

26.250 

79.32 

12.61 

50 

70 

•7 

144.28 

20, 816 

62.  IK) 

15.00 

.49871 

38 

54 

8 

128. 49 

16,509 

49.88 

20.05 

.62881 

35 

50 

•9 

114.43 

13,594 

39.56 

25.28 

.79281 

28 

38 

10  . 

101. 89 

10,381 

31. 37 

31.38 

1.0 

25 

30 

*u 

90.74 

8,234 

24.88 

40.20 

1.2007 

20 

27 

12 

80.81 

6,530 

19.73 

50.09 

1.5898 

20 

25 

•13 

71.96 

5,178 

15.65 

63.  91 

2.0047 

14 

22 

14 

64.08 

4. 107 

12.41 

80.58 

2.5908 

15 

20 

Notes. — 1.  Sizes  marked  • are  not  used  for  electrical  work. 

2.  For  aluminum  wire  the  carrying  capacity  of  any  given  size 
should  be  taken  as  84  percent  of  the  value  given  In  above  table. 

3.  If  current  exceeds  the  safe  current-carrying  capacity  of  the 
largest  wire,  two  or  more  wires  should  be  used. 


Table  LXIV. — Bill  of  electrical  material  for  one  standard  20  by  100 
foot  barrack 


Item 

Quan- 

tity 

Unit 

Size 

Weight 

in 

pounds 

Description 

210 

Feet  . 

No.  14 

5M 

Wire,  R.  C.  8.  B.  solid  copikt. 

2 

1 

Each. 

125-volt,  30- 

l 

Cut-out,  main  line,  plus  fuse. 

3 

2 

4 

Each 

ampere. 
15-ampere 

1M 

7H 

double  pole. 

Fuses,  plug. 

Socket,  pull,  brass,  S22  (PAS), 
cat.  38,  base  BP. 

Knobs,  split  porcelain,  with 

5 .. 

50 

Each... 

No.  12. 

6 

2 

Each  . 

% by  3 inches. 

nail  and  leather  washer. 
Tubes,  porcelain. 

7 

4 

Lamps,  Mar.da,  115-volt. 
Screws,  for  cul-out  and  socket, 

8 . . 

0 

4 

Each 

3 feet 

No.  8.  F.  11.  bright. 

Cord,  linen,  with  chain  and 

link  tassel. 

162 


163 


Figure  94. — Tying  square  knots. 


REFERENCE  DATA 


Cut  tail  flush  with 
rubber  insulation 


2 turns  on  rubber 


s rubber 


Figure  95. — Finishing  the  spllcet 


77-78 


CORPS  OF  ENCINEER 


REFERENCE  DATA 


78 


Figure  96 — Applying  rubber  and  friction  tape. 


before  TYING 


SOLID  CONDUCTOR 


adjacent 


SOLIO  CONDUCTOR  YYIRE 


ONTO  INSULATION 


Figure  97. — Combination  splice. 


Section  VII 
RIGGING 

■ 78  Anchorages. — Determine  the  holding  power  of  deadman 
as  follows: 

a.  For  a given  cable  pull,  the  number  of  square  feet  of  dead- 
man  bearing  surface  required  is  determined  by  dividing  the 


total  pull  to  be  placed  on  the  deadman  by  the  value  given  for 
the  depth  and  cable  inclination  selected  (see  table  LXV). 
Having  determined  the  bearing  surface  area,  select  a length 
and  section  corresponding  to  this  area. 

b.  In  order  to  insure  that  the  deadman  selected  will  not 
fail  in  bending,  test  by: 

2667bft’  for  a rectangular  timber,  or 
T L 

1600d5  for  a round  timber 

where 

7’=maximum  allowable  cable  pull  in  pounds. 

b=width  of  contact  face  of  deadman.  in  inches. 

A = depth  of  deadman  in  direction  of  pull,  in  Inches. 

d=diameter  of  round  timber,  in  inches. 

L—  length  of  deadman,  in  inches. 

c.  If  the  maximum  allowable  pull  T,  as  computed,  is  less 
than  actual  pull,  a timber  of  greater  depth  or  diameter  should 
be  used,  and  test  computation  repeated  until  a satisfactory 
section  is  determined.  If  maximum  allowable  pull  found  by 
the  formula  is  greater  than  the  required  cable  pull,  the  dead- 
man is  satisfactory  in  bending. 


Table  LXV. — Holding  power  of  deadman  in  loamy  soil 


Mean 
depth  of 
anchorage 
(feet) 

Declination  of  pull  (vertical  to  horizontal)  and  safe 
resistance  (|xmnds  per  square  foot) 

Vertical 

i/i 

1/2 

1/3 

1/4 

3 

600 

950 

1,300 

1,450 

1,500 

4 

1,050 

1,750 

2,200 

2,000 

2,700 

5 

1,700 

2.800 

3.600 

4,000 

4. 100 

6 

2,400 

3.800 

5,100 

5,800 

6,000 

7 

3,200 

5, 100 

7,000 

8,000 

8,400 

d.  Typical  forms  of  holdfasts  and  deadmen  are  shown  in 
figure  106. 


168 


169 


1*79—81 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


81 


■ 79.  Slings. — The  most  common  sling  is  made  by  splicing 
two  ends  of  a rope  together.  To  use  the  sling,  pass  it  around 
the  article  to  be  lifted.  Pass  the  bight  formed  by  one  end 
through  the  bight  formed  by  the  other  and  then  over  the 
lifting  hook.  If  the  sling  is  the  same  size  as  the  lifting  rope, 
it  should  make  a minimum  angle  of  30°  with  the  horizontal. 
At  this  angle,  the  stress  in  each  branch  of  the  sling  is  equal 
to  the  stress  in  the  lifting  rope.  If  the  angle  is  greater  than 
30°,  the  load  is  limited  by  the  strength  of  the  lifting  rope; 
if  less  than  30°,  by  the  strength  of  the  sling. 

■ 80.  Gin  Pole  or  Standing  Derrick. — To  erect  a gin  pole, 
lash  the  tackle  to  the  spar  or  suspend  it  by  a sling  run  through 
slot  in  the  head  of  the  pole.  Locate  the  foot  of  the  gin  pole. 
Lay  a line  through  the  point  to  mark  the  location  of  the  fore 
and  back  guys.  Lay  another  line  at  right  angles  to  this.  Lay 
off  on  the  four  lines  distances  equal  to  twice  the  length  of  the 
spar  for  level  ground,  plus  necessary  allowances.  Erect 
anchorages  at  these  points.  Make  the  four  guys  fast  to  the 
top  of  the  spar.  Lay  the  spar  along  one  of  the  guy  lines 
with  the  butt  nearly  in  the  footing.  Fasten  a footrope  to 
the  butt  and  to  an  anchorage  on  the  same  side  of  the  footing 
as  the  spar.  Raise  the  top  by  hauling  the  back  guy  with  a 
running  tackle.  Let  the  fore  guy  out.  Take  up  the  slack  on 
the  side  guys.  Continue  until  spar  is  in  position,  keeping 
the  slack  out  of  all  guys.  For  heavy  poles  it  may  be  necessary 
to  erect  a light  gin  pole  or  shears  first  and  use  this  to  erect 
the  heavy  pole.  In  hard  ground,  dig  a hole  about  1 foot  deep 
for  the  butt  of  the  gin  pole.  In  soft  ground,  prepare  an 
excavation  with  a wood  floor  base  to  transmit  the  ground 
pressure  over  a larger  area. 

■ 81.  Knots,  Lashings,  and  Tackle. 


170 


»m»V 


V VJHv  v 

*V«  4HP''j;  WttKm"  - m»*  >>»>"* 


,A*t  jM 


iM 


MT73P; 


?^*>V 


P?!R 

- /i 


HR 


a v*w»»iWt||lB 

'vwv^v V mvit » t , 


Timber  hitch  end  Half  hitch 


Timber  hitch 


Running  Bowlin* 


Rolling  Hitch  Shtepchenk 

Figure  100. — Miscellaneous  knots. 


Bowline  on  e Bight 
Figure  99. — Types  of  knots. 


282736'’— 41 12 


reference  data 


eiickw.n  Hitch 


Mooting  Knot 


Short  Splice, 


Long  Splice, 


Long  Splice, 


Ciown  on  Well 

Figure  101. — Miscellaneous  knots  and  hitches. 


Eye  Splice 

Figure  102. — Splices. 


81 


CORPS  OF  ENGINEERS 


Table  LXVI. — Characteristics  of  knots 


Figure 

Directions  for  tying  refer- 
ence 


1.  Overhand At  end  of  rope  to  pre- 

vent unlaying  or  to 
prevent  end  from 
slipping  through 
block. 

2.  Figure  of  eight. . Same  as  above 


See  figure 


3.  Square  or  reef  * . 


To  join  two  roi>es  of 
same  size. 


4.  Single  sheet  bend  To  join  ropes,  espe- 
or  weavers’.1  cially  of  unequal 


See  figure.  Pass  standing 
and  running  parts  of  each 
rope  through  loop  of  the 
other  in  samo  direction. 
Ends  of  each  rope  turn 
around  end  of  other, 
rather  than  standing  part. 

See  figure 


See  figure.  End  may  be 
lashed  down  or  seized  to 
standing  part  to  prevent 
slipping. 

Sec  figure 


or  weavers’.1  cially  of  unequal 

size. 

5.  Double  sheet  To  join  ropes  of  un-  do 

bend .»  equal  size,  especially 

wet  ones. 

G.  Two  half  hitches 4 To  belay  or  make  fast  See  figure.  End  may  be 
end  of  ro|>e  around  lashed  down  or  seized  to 
own  standing  part.  standing  part  to  prevent 
slipping. 

7.  Round  turn  and  Same  as  above  ...  See  figure — 

two  half 
hitches. 

8.  Fisherman’s  bend  To  fasten  a ro|>c  to  a See  figure.  Take  two  turns 

or  anchor.  ring  or  anchor.  around  the  iron,  then  a 

half  hitch  round  the  stand- 
ing part  and  between  the 
ring  and  the  turns,  then 
half  hitch  round  standing 
part. 

i Care  must  be  takon  not  to  tio  a thief  or  granny  as  these  will  slip. 

1 More  secure  than  a reef  but  more  difficult  to  untie. 

1 More  secure  than  a single  sheet  bend. 

* Must  never  be  used  for  hoisting  a spar. 


176 


$ $ 


REFERENCE  DATA 


81 


Table  LXVI. — Characteristics  of  knots — Continued 


Figure 

Directions  for  tying  refer- 

i enee 


10.  Timber  hitch ». . To  haul  or  lift  spars. 

11.  Telegraph  hitch.  To  hoist  or  haul  a spar 

12.  Hawser  bend. . . To  join  two  large  ca- 

bles. 

13.  Bowline1 To  form  a loop  that 

will  not  slip. 


9.  Clove  hitch To  fasten  a rope  at  See  figure.  If  end  of  spar  is  98 

I right  angles  to  a spar  free,  hitch  made  by  first 

or  at  beginning  of  forming  two  loops,  placing 
lashing.  right-hand  loop  over  other, 

and  slipping  the  double 
loop  over  the  end  of  the 
spar.  Otherwise,  pass  end 
of  roi>e  round  spar,  bring 
it  up  to  the  right  of  stand- 
ing part,  cross  over  latter, 
make  another  turn  around 
spar,  bring  up  the  end  be- 
tween spar,  last  turn  and 
standing  part. 

10.  Timber  hitch  . To  haul  or  lift  spars.  Sec  figure 

11.  Telegraph  hitch.  To  hoist  or  haul  a spar  .do 

12.  Hawser  bend...  To  join  two  large  ca-  See  figure.  Each  end  is  99 

Plus.  seized  to  own  standing 

part. 

13.  Bowline* To  form  a loop  that  See  figure.  Make  loop  with  ®# 

will  not  slip.  standing  part  underneath, 

pass  cud  from  below 
through  loop,  over  the 
part,  around  the  standing 
part,  then  down  through 
the  loop. 

14.  Bowline  on  a To  rnako  a comfort-  See  figure.  Make  first  part  W 

bight.  able  sling  for  a man.  as  above  with  double  part 

of  rope,  then  pull  bight 
through  sufficiently  to  al- 
low it  to  bo  bent  past  loop 
and  come  up  in  proper 
position. 

15.  Running  bow-  To  make  a slip  knot  See  figure.  Pass  end  around  99 

hoe,  that  will  not  bind.  spar.  Form  a loop  around 

the  standing  ]>art  with  the. 
running  end.  Make  a 
bowline  on  the  standing 
part  below  the  loop — on 
the  running-end  side. 

• Can  be  easily  loosened  when  strain  is  taken  oil,  but  will  not  slip  under  load. 

When  used  for  hauling  spars,  a half  hitch  is  added  near  end  of  spar. 

• Length  of  bight  depends  on  purpose  for  which  knot  is  required. 


14.  Bowline  on 
bight. 


15.  Running  bow- 
line. 


To  make  a comfort- 
able sling  for  a man. 


To  make  a slip  knot 
that  will  not  bind. 


177 


81 


CORPS  OF  ENGINEERS 


Table  LXVI. — Characteristics  of  knots — Continued 


Directions  for  tying 


16.  Cat’s  paw 


To  secure*  rope  to  the 
mouth  of  a book. 


17.  Sheepshank — 


18.  Rolling  hitch . 


19.  Blackwall  hitch 


20.  Mooring  knot.. 


21.  Carrick  bend-.. 


22.  Wall  knot  and 
crown  on  wall. 


To  shorten  a rope  or 
pass  a weak  spot. 

To  haul  a larger  rope 
or  cable. 


To  attach  a single  rope 
to  a hook  of  a block 
for  hoisting. 

To  make  fast  to  a 
mooring  or  snubbing 
post. 


To  fasten  guys  to  der- 
ricks. 

To  finish  the  end  of  a 
rope  to  prevent  un- 
1 aylng. 


See  figure.  Form  two  equal 
bights;  take  ono  in  each 
hand  and  roll  them  along 
the  standing  part  till  sur- 
rounded by  three  turns  of 
the  standing  part;  then 
bring  both  loops  (or 
bights)  together  and  pass 
over  tho  hook,  and  mouse 
the  hook. 

See  figure.  Take  a half  hitch 
with  the  standing  parts 
around  tho  bights. 

See  figure.  Take  two  turns 
around  the  burg©  rope  in 
the  direction  in  which  it  is 
to  be  hauled,  and  ono  half 
hitch  on  the  other  side  of 
the  hauling  part. 

See  figure 


See  figure.  Take  two  turns 
around  the  mooring  or 
snubbing  post,  pass  the 
free  end  under  the  stand- 
ing part,  take  a third  turn 
above  tho  other,  pass  the 
free  end  between  tho  two 
upper  turns. 

See  figure 


REFERENCE  DATA 


81 


Figure  103. — Square  lashing. 


■Si*.. 


aaawwBt 


CORPS  OF  ENGINEERS 


PH§» 


81 


81-82 


CORPS  OF  ENGINEERS 


REFERENCE  DATA 


^ P 

Figure  109. — Single  Burton  (mechanical  advantage:  6). 


IZP  |2P 

Figure  111. — Double  Burton  (mechanical  advantage:  11). 


9 


Figure  112.— Double  luff  (2-fold  tackle)  (mechanical 
advantage:  5). 


4 


Figure  113. — Luff  on  luff  (mechanical  advantage:  16). 


P 

Figure  115. — Whip  on  whip  (mechanical  advantage:  4). 

■ 82.  Rigging  Tables. 

Table  LXVII. — Working  strength  of  wire  and  manila  rope 


Diameter 

Circum- 

frreuce 

Weight  per  100  feet 

Working  strength 
(pounds) 

Steel 

Hemp 

Steel 

Manila  or 
hemp 

H 

m 

13 

5 

4,000 

400 

M 

1)4 

39 

7 

7,000 

850 

H 

2 

60 

13 

11, 100 

1,520 

H 

2H 

88 

17 

15,300 

1,900 

H 

2*4 

120 

24 

20, 700 

2,300 

1 

m 

168 

28 

28,000 

8,  LOO 

1W 

4 

260 

46 

42,000 

4,300 

m 

4*4 

305 

04 

58,700 

5,900 

1M 

5)4 

525 

84 

76,000 

7,900 

2 

6)4 

632 

115 

96,000 

10,300 

2)4 

7H 

988 

117 

110,000 

16,600 

3 

9)4 

1,421 

255 

118,  OOQ 

22,500 

182 


183 


82 


CORPS  OF  ENOIHEERS 


Table  LXVTTI. — Relation  of  sheave  and  wire  rope  diameters 


Type  of  rope 

Desirable 
sheave  and 
drum 
diameter  1 

Safe 
sheave 
and  drum 
diameter 

Minimum 
sheave  and 
drum 
diameter 

Multiply  all  fig- 
ures in  table 

6 by  7 1 

72 

42 

28 

Xrope  diameter. 

6 by  19 

45 

30 

20 

Do. 

6 by  37 

27 

18 

14 

l>o. 

8 by  19 

31 

21 

16 

Do. 

1 For  standing  ropes,  these  values  may  be  reduced  by  SO  percent. 
1 A 6 by  7 ruj>o  is  one  of  f)  strands  of  7 wires  each. 


Table  LXIX. — Lead  line  pull  factors  and  efficiencies  for  hoist  or  fall 
wire  ropes 


Number  of  parts  of  rope 

2 

3 

4 

5 

6 

7 

8 

9 

10 

Kfllciency,  percent 

Lead  line  pull  factor — 

96. 1 
.52 

92.4 

.36 

88.9 

.28 

86. 5 
.23 

82.2 

.20 

79.0 

.18 

76.0 

.165 

73.0 

.15 

70.3 

.14 

CORPS  OF  ENGINEERS 

Section  VIII 
CONCRETE 

■ 83.  Materials. — a.  Shipment  and  storage  of  cement. — Ce- 
ment is  usually  shipped  in  bags  of  94  pounds  each  (considered 
1 cubic  foot)  or  barrels  equivalent  to  four  bags  each.  It  should 
be  stored  in  a weatherproof  building  and  at  least  8 inches 
from  walls  and  ground  or  floor  to  insure  ventilation. 

b.  Fine  aggregate. — That  part  of  the  aggregate  passing  a 
%-inch  screen  is  called  fine  aggregate.  Clay  and  silt  should 
not  constitute  more  than  3 percent  of  the  sand  by  weight,  or 
together  with  coal  particles,  shale,  shell,  etc.,  not  more  than 
5 percent  by  weight.  (See  table  LXXII  for  a suitable 
gradation.) 

Table  LXXII. — Gradation  of  fine  aggregates 


83-84 


Passing— 


% inch  (standard  square  mush) 
No.  4 

No.  10 

No.  60 

No.  100 


Percent  by 
weight 


100 

05-100 

35-75 

10-26 

2-7 


c.  Coarse  aggregate. — Coarse  aggregate  will  not  pass  a %- 
inch  screen.  Broken  stone,  gravel,  slag,  and  cinders  are  com- 
monly used.  Maximum  size  of  coarse  aggregate  depends  on 
the  use  to  be  made  of  the  concrete:  for  plain  concrete  in  mass 
construction,  l‘/2  to  6 inches;  for  reinforced  work,  1 inch;  for 
thin  reinforced  members,  % inch. 

d.  Water. — Water  used  in  concrete  should  be  clean  and  free 
from  excessive  amounts  of  oil,  acid,  alkali,  or  organic  matter. 
Sea  water  is  undesirable  but  may  be  used  in  emergency. 

■ 84.  Proportioning  Concrete  Mixes. — The  following  tables 
can  be  used  to  select  trial  proportions  for  concrete  mixtures 
used  for  various  types  of  work: 


186 


REFERENCE  DATA 


84 


Table  LXXIII. — Strength  of  concrete  mixtures 


Water  con- 
tent 1 (U.  S. 
gallons  jn?r 
94-pound 

Assumed 

strength 

(pounds 

inch) 

pom  press!  ve 
at  28  days 
per  square 

cement) 

o 

0) 

ft 

1,750 

2.750 

7 

2,800 

3.300 

6 

3.000 

4,000 

5 

3. 80t) 

4,000 

' Surface  « ater  or  moisture  carried  by  aggregate  must  be  included  as  part  of  mixing 
water. 

> Data  published  at  time  water  cement  ratio  strength  law  was  announced  in  1918. 
These  values  should  be  used  in  tie  absence  of  preliminary  tests  and  careful  control. 
* Values  representative  of  present  day  cements. 


Table  LXXTV. — Approximate  quantity  of  surface  water  carried  by 
average  aggregates 


Aggregate 

Water  (gallons  per  cubic  foot) 

Very  wot  sand 

94  to  1. 

Moderately  wot  sand 

About  Vi. 

Moist  gravel  or  crushed  rock 

About  V4. 

Table  LXXV. — Suitable  slumps  for  concrete 


Slump  (inches) 

| tc  uf  jvtroctTTTB 

Minimum 

Maximum 

Massive  sections,  pavements  and  floors  laid  on  ground . . . 

1 

* 

3 

6 

Thin  walls  and  columns,  ordinary  slabs  or  beams 

4 

8 

187 


84 


CORPS  OF  ENGINEERS 


Table  LXXVI. — Trial  mixtures  for  various  water-cement  ratios 


Slump  (inches) 

Trial  mix  dry  compact  volumes  for 
maximum  si/e  of  aggregate  indicated 

1 inch 

2 inches  and  over 

Water-cement  ratio  8%  Ballons  per  sack 

M to  1 

1:2:3 

1:2:3%. 

1:194:3. 

1:1%:2%. 

3 to  4 

Irm^pWiP  ' 

MMi 

Water-cement  ratio  6 gallons  per  sack 

H to  I - 

1:2M:3  H 

1:2M:4. 

1:2:8%. 

1:194:3. 

3 to  4 

1:2,3...  

5 to  7 

1:194:2*$ 

Water-cement  ratio  6H  gallons  per  sack 

*$  to  i 

1:2*$:3*$ 

1:214:4. 

1:214:3%. 

1:2:3%. 

3 to  4 

1:2M:3M 

6 to  7 

1:2:3 

Water-cement  ratio  7*$  gallons  per  sack 

to  1 

1:3:4 

3 to  4 

1:2*$: 3 H 

5 to  7 

1:2*4:3J$ 

Notes. — 1.  Water-cement  ratios  indicated  Include  moisture  con- 
tained In  the  aggregate. 

2.  Proportions  are  given  by  volume,  aggregate  dry.  and  compact. 
Thus  1:2:3%  Indicates  1 volume  of  cement.  2 volumes  of  sand,  and 
3%  volumes  of  coarse  aggregate. 

3.  If  the  aggregates  are  to  be  measured  in  the  damp  and  loose  con- 
dition they  will  occupy  greater  volumes  than  when  dry  and  com- 
pact. Amount  should  be  determined  by  test.  Approximate  aver- 
age value  for  sand,  20  percent;  for  coarse  aggregate,  6 percent. 


188 


REFERENCE  DATA 


85 


■ 85.  Quantities  of  Materials. — Use  table  LXXVII  to  estimate 
quantities  of  materials  required  in  concrete  construction. 


Table  LXXVIIA. — Quantities  of  materials 


Mix  by  volume,  Job  damp  materials 

Materials  per  cubic  yard 
of  concrete 

Product 
of  a 
1-bag 
batch 
(cubic 
feet) 

Cement 

(sacks) 

i Sand 
(cubic 
feet) 

Stone 

(cubic 

feet) 

BH 

n 

19.1 

2.82 

3.55 

tSl&iHHa 

3.82 

1:2:3. 5 

imM 

22.7 

4. 16 

6.0 

12.0 

24.0 

4. 47 

6.8 

160 

20.4 

3. 97 

1:2.2: 3.5 

6.3 

13.9 

22.2 

4.26 

1:2.5:3. 

6.5 

16.1 

19.4 

4.18 

6.0 

160 

21.0 

4.49 

6.6 

14.0 

22.4 

4.  at 

60 

12.5 

25.0 

5.  43 

1:3:5  .. 

4.7 

14.1 

23.5 

6 76 

1:3:6- 

4.2 

12.6 

25.2 

r>.  3s 

1:314:4  

5.2 

16.2 

20.8 

5. 21 

1:314:6  

4.6 

14.5 

23.2 

6.S2 

l:394:A - 

4.3 

16.0 

21.4 

6. 32 

1:3%:  6 

3.9 

14.7 

23.5 

6.89 

1:114  

15.  5 

1:2 

12.8 

25. 6 

2. 13 

Table  LXXVIIB. — Dimensions  for  measuring  boxes 


Capacity  (cubic  (eet) 


1W 

1% 

m 

2.. 

2% 

2%. 

2% 

3... 


Inside  measure  (inches) 


Length 

Breadth 

Height 

12 

■ 

12 

15 

9% 

15 

15 

1U4 

15 

16 

13% 

18 

18 

10% 

18 

18 

12 

18 

18 

13% 

18 

18 

14% 

18 

18 

16 

282736 


•13 


189 


86 


CORPS  OF  ENGINEERS 


■ 86.  Mixing,  Placing,  and  Curing.— a.  Mixing— Batches  of 
concrete  mixed  by  hand  should  not  exceed  1 cub'cyardorb 
larger  than  can  be  placed  in  30  minutes.  Machine  mixing 
should  continue  for  at  least  1 minute  after  all  materials  are 

m b^PIacing. — The  following  precautions  should  be  observed: 

(1)  Fill  forms  from  several  points  to  prevent  segregation. 

(2)  Tamp  concrete  in  layers  1 to  2 feet  in  thickness. 

(3)  Provide  construction  joints  to  allow  for  temperature 

changes^ur  cQncrete  continuoUsly  whenever  possible.  If  im- 
possible to  pour  continuously,  remove  all  laltance,  dust  etc. 
and  roughen  the  old  surface  or  dowel  the  old  and  new  surfac 
together  bv  keyways  or  steel  bars. 

c Curing. — (1)  Concrete,  in  order  to  gain  its  full  strength, 

must  be  kept  moist  for  from  2 to  10  days  after  placing  (de- 
£5i„B  on  the  type  of  cement  need..  TO.  may  be  accom- 

''uncovering  concrete  with  wet  burlap,  canvaa,  straw,  or 

earth  and  wetting  it  down  periodically. 

(b)  Laying  water  pipe  around  green  concrete  and  allow- 
ing water  to  trickle  through  small  holes  in  pipe. 

1c)  Building  earth  or  plank  dykes  around  surface  and 
keeping  it  flooded  with  water  (for  flat  surfaces). 

id)  Wetting  forms  before  placing  concrete  to  prevent  ab 

sorption  of  mixing  water  by  wood. 

(2)  The  time  of  set  is  greatly  affected  by  the  curing  tem- 
peratures As  the  temperature  falls,  the  set  is  slowed  down, 
and  below  freezing  weather  makes  the  placing  of  concrete 
“m"  hazardmis.  The  temperature  of  setting  concrete 

-S' - »- 

pioductSjbefore  ^ place  with  insulating  material 

such  as  straw,  earth,  etc.  . , 

(c)  Providing  artificial  heat  by  canvas  enclosures  heated 

by  salamanders,  live  steam,  or  unit  heaters. 


190 


REFERENCE  DATA 


87 


■ 87.  Forms. — a.  Materials. — White  pine,  spruce,  and  the 
softer  southern  pines  are  the  best  lumber  for  forms.  All 
lumber  should  be  dressed  at  least  on  one  side  and  both  edges. 
Either  1-  or  2-inch  boards  are  suitable  for  lagging. 

(1)  One-inch  lagging  requires — 

Studding  or  joists:  2 by  4 to  2 by  6 inches. 

Distance  between  supports:  18  to  24  inches. 

(2)  Two-inch  lagging  requires — 

Studding  or  joists:  4 by  6 to  4 by  10  inches. 

Distance  between  supports:  4 to  5 feet. 

b.  Cleaning. — Remove  all  sawdust,  shavings,  dirt,  old  con- 
crete, etc.,  from  forms  and  wet  or  oil  them  before  placing 
concrete. 

c.  Removal. — Usually,  forms  should  remain  in  place  longer 
for  reinforced  than  for  plain  concrete,  and  longer  for  hori- 
zontal or  loaded  than  for  vertical  or  unstressed  members.  As 
a guide: 

Walls  in  mass  work:  1 to  3 days. 

Thin  walls:  in  summer,  2 days:  in  cold  weather,  5 days. 

Columns:  in  summer,  2 days;  in  cold  weather,  4 days. 

d.  Type  forms. — The  following  figures  illustrate  the  general 
principles  of  form  construction: 


191 


CHAPTER  3 


DEFENSIVE  MEASURES 

Paragraph 


Section  I.  Field  fortifications 88-110 

n.  Camouflage 111-128 

III.  Explosives  and  demolitions 129-138 

IV.  Barriers  and  antimechanized  defense 139-146 


Section  I 

FIELD  FORTIFICATIONS 
■ 88.  Defensive  Areas. — a.  Squad  and  platoon. 

Table  LXXVIII. — Frontages  (in.  yards) 


Size  of  unit  defense  areas 

Minimum  (heavily  wooded 
terrain) 

Maximum  (flat,  open 
terrain) 

Interval 

between 

defense 

areas 

Front- 

ape 

actually 

occupied 

Tolal 

front 

defended 

Interval 

l>ctween 

defense 

areas 

Front- 

axe 

actually 

occupied 

Total 

front 

defended 

1 squad  (12  men) 

25 

30 

55 

100 

50 

150 

Platoon,  less  1 squad  (2 

squads) 

50 

75 

125 

150 

100 

250 

Full  platoon  (3 squads)... 

100 

100 

200 

200 

200 

400 

b.  Company. — A company  can  defend  a front  of  400  to 
600  yards;  front  and  depth  actually  occupied  are  from  200 
to  400  yards  and  100  to  300  yards,  respectively. 

c.  Battalion. — A battalion  can  defend,  in  heavily  wooded 
terrain  or  with  limited  observation  and  fields  of  fire,  a front 
not  to  exceed  800  yards;  in  average  terrain,  not  to  exceed 
1,500  yards. 


193 


— 


mm 

ai 


Minimum  safe 
distance  from 
Infantry 


Arra  of  barrage 


Area  of 
concen- 
tration 


Burst 
of  1 
shell 


Emer- 

gency 


Normal 


75-mm 

105-nun 


155-nun 


CORPS  OF  ENGINEERS 


Figure  118.— Battalion  defense  area. 

Note.— Locations  and  fires  of  all  weapons  of  the  battalion  to 
include  light  machine  guns  of  rifle  companies  and  locations  of 
their  60-mm  mortars  are  shown.  Primary  target  areas *5® 
81 -mm  mortars  and  normal  barrages  of  supporting  •rtUlery 
shown.  Note  that  some  of  the  60-mm  mortars  are  attached  to 
front-line  platoons  and  that  the  caliber  .30  light  machine  guns 
are  employed  In  the  defense  in  the  same  manner  as  caliber  .30 
heavy  machine  guns. 

Table  LXXIX. — Placing  of  barrages  and.  concentrations  fired  by 
batteries  of  Field  Artillery  (dimensions  in  yards) 


Caliber 


In  open  trenches 


1 


REFERENCE  DATA 


89 


■ 89.  Effect  of  Projectiles  on  Field  Fortification. — a. 
Srjiall  arms. 

Table  LXXX. — Safe  thickness  of  material  to  protect  against  non- 
armor-piercing  bullets,  caliber  .30  ( 174  grains) 


Material 

Maximum 

penetration 

(inches) 

Least  thick- 
ness to  be 
provided  for 
protection 
(inches) 

0.3 

0.5 

2.0 

3.0 

5.0 

7.0 

8.0 

10.0 

12. 0 

14.0 

14.5 

18.0 

20.0 

JM.O 

30.0 

36.0 

60.0 

72.0 

Table  LXXXI. — Penetration  of  caliber  .30 
■piercing  bullets 

and  caliber 

.50  armor- 

Typo 


Projectile 

weight 

(groins) 


Armor  penetration 
in  inches  at— 


100  yards  300  yards 


Thickness 
of  armor 
to  provide 
protection 
(inches) 


Caliber  .30,  M6 174 

Calibe  r .50,  M6 753 


1 

2 


Table  LXXXII. — Penetration  of  special  armor -piercing  weapons 


Armor  penetration  in  inches 
at— 


Antitank  (AT)  gun 


Project  ile 
weight 
(pounds) 


Muzzle  ve- 
locity (feet 
j>er  second) 


600  yards, 
normal  im- 
pact 


1,000  yards 
20°  impact 


25-mm 
37-mm 
47- m in 


0. 72 
1.85 
3.50 


3.000 

2.000 
2.000 


1.95  1.3 

2.20  1.5 

1.90  1.2 


195 

M 


89 


CORPS  OF  ENGINEERS 


b.  Artillery  and  aircraft. — -Formula  for  maximum  penetra- 
tion of  projectiles,  impact  normal: 

r 0.23  WAK 
e D 

where 

P=penetration  of  projectile  in  feet. 

W= weight  of  projectile  in  pounds. 

D=  diameter  of  projectile  in  inches. 

A= a constant  depending  on  striking  velocity  according 
to  table  LXXXin. 

Table  LXXXIII.— Values  of  A in  penetration  formula 


Velocity 

Velocity 

(feet  per 
second) 

A 

(feet  per 
second) 

130 

0.33 

657 

197 

.72 

720 

262 

1.21 

788 

328 

1.76 

854 

394 

2. 30 

920 

460 

2.97 

985 

m 

3.58 

1,050 

592 

4.17 

1,113 

Velocity 
(feet  per 
second) 

A 

1, 180 

8.76 

1,250 

9.15 

1,320 

9.54 

1,375 

9.92 

1.445 

10.29 

1,510 

10.64 

1.675 

10.98 

1,640 



11.20 

K=&  constant,  depending  upon  the  nature  of  the  resist- 
ance, as  follows: 


0.64  for  concrete  masonry. 

0.94  for  stone. 

1.63  for  brickwork. 

2.94  for  sandy  earth. 

3.86  for  ploughed  earth. 

5.87  for  clay  soil. 

W and  D must  be  obtained  from  characteristic  tables  of 
the  projectile  under  consideration. 


196 


REFERENCE  DATA 


89 


Table  LXXXIV  — Penetration  of  field  artillery  projectiles  in 
ordinary  compact  soil 


Caliber 

Striking 
velocity 
(feet  per 
second) 

Angle  of 
impact 
(degrees) 

Penetration  (feet) 
Vertical  Horizontal 

75-ram 

730 

45 

4 

4 

105- mm 

800 

45 

5 

6 

155-nun 

770 

45 

7 

7 

8-inch 

790 

45 

9 

9 

240-ram 

806 

45 

14 

14 

Table  LXXXV. — Effect  of  angle  of  impact  on  penetration  of  artillery 
projectiles 


Angle  of  Impact 

Behavior  of  projectile 

Less  than  7° 

Ricochets. 

7°  to  25° 

Ricochets  after  traveling  short  distance  or  remains  In 
ground  at  slight  depth. 

25®  to  40° 

Tendency  for  nose  of  projectile  to  turn  toward  surface. 
Slight  penetration. 

Greater  than  40° 

Maximum  penetration. 

Table  LXXXVI. — Crater  dimensions  of  artillery  projectiles 


Caliber 

Slight  penetration 

Medium  penetration 

Diameter 

(feet) 

Depth 

(feet) 

Diameter 

(feet) 

Depth 

(feet) 

75-mm 

4 

1.5 

5 

3 

105-mni 

6.8 

2.5 

7.5 

8.78 

156-mm 

10 

4 

12 

8 

8-inch. 

11.5 

4 

13.5 

6 

240-mm 

14 

4 

15.5 

5.5 

197 


T- 


89  CORPS  OF  ENGINEERS 


c.  Aircraft  bombs. 

Table  LXXXVII.— Crater  dimensions  of  aircraft  bombs  in 
sandy  loam 


Weight  of  bomb  (pounds) 

Depth  of 
crater  (feet) 

Diameter 
at  surface 
(feet) 

Earth  dis- 
placed 
(cubic 
yards) 

With  instantaneous  fuze: 

100 

2 

0 

4 

300 

3 

13 

10 

600 

ft 

17 

17 

1,100 

0 

20 

28 

2,000  - 

7 

22 

47 

With  delay  fuze: 

100  

ft 

20 

30 

300 

7 

27 

70 

600 

10 

37 

170 

1,100 

13 

4ft 

320 

2,000 

17 

60 

600 

Table  LXXXVIII. — Typical  dimensions  of  aircraft  l>ombs 


Weight  of  bomb  (pounds) 

Over-all 
length  » 
(feet) 

Maximum 

diameter 

(inches) 

Sectional 
pressure s 
(pounds  per 
square  inch) 

14 

O) 

24 

4.4 

6 

(4) 

12 

9.7 

5 

(4) 

1ft 

3.1 

414 

(2) 

10 

2.8 

4 

(2) 

9 

1.6 

2 

(1) 

6 

1.0 



• Figures  in  parentheses  in  this  column  are  lengths  of  charge  container  only. 
, Weight  divided  by  maximum  cross-sect ional  area. 


REFERENCE  DATA  89- 


APPROXIMATE  DEPTH  OF  PENETRATION 
FOR  UNIT  SECTIONAL  PRESSURE  OF  BOMB 


Note, — Gives  approximate  depth  of  penetration  at  normal  angles 
of  impact,  for  unit  sectional  pressure.  To  obtain  total  penetration 
multiply  value  for  penetration  taken  from  the  figure  by  sectional 
pressure  given  in  Table  LXXXVIII. 

Figure  119. — Penetration  of  aircraft  bombs. 


198 


199 


89-90 


CORPS  OF  ENGINEERS 


Table  LXXXIX  — Striking  velocity  of  aircraft  bombs 
[Based  on  aircraft  speed  of  200  m.  |>.  h.  with  bombs  weighing  over  100  pounds] 


Height  of  release 
(feet) 

Angle  of 
Impact  with 
vertical 
(degrees) 

Striking 
velocity 
(feet  per 
second) 

1.000 

40 

790 

3. 000 

33 

520 

6,000 

26 

610 

7.500 

22 

710 

10. (XX) 

19 

800 

12.500 

17.8 

8S0 

15,000 

16 

950 

■ 90.  Trench  Requirements. — A deliberate  trench  must — 

a.  If  a fire  trench,  provide  a good  field  of  fire  to  permit 
maximum  use  of  defender’s  weapons  and  permit  of  flank  or 
cross 
…[truncated]