MAHO BAY USVI, LLC: Construction Schedule ST JOHN, USVI

EFTA00305825 Dataset 9 6 pages Download original PDF Download as text
MAHO BAY USVI, LLC: Construction Schedule ST JOHN, USVI ID Task Name Duration Start Finish Complete 1 Pool Shade Structure & Engineering Doors 45 days Mon 6/10/19 Fri 8/9/19 0% 2 Engneering doors removal and installation 5 days Mon 6/10/19 Fri 6/14/19 0% 7 Long Lead Procurement 14 days Wed 5/29/19 Mon 6/17/19 0% 8 6" Square or 4"x6" structural steel tube 2 wks Wed 5/29/19 Tue 6/11/19 0% 9 Mobilize on Site 2 days Mon 6/10/19 Tue 6/11/19 0% 10 Delivery of Trash Bin or bins to LSJ 1 day Thu 6/6/19 Thu 6/6/19 0% 11 Delivery of doors to site location and installation 2 days Mon 6/10/19 Tue 6/11/19 0% 12 Demolition of existing Pool Shade structure 2 days Mon 6/17/19 Tue 6/18/19 0% 13 Demolition of existing conc. Slab for new footing 2 days Wed 6/19/19 Thu 6/20/19 0% 14 8 -New Column Footing 7 days Fri 6/21/19 Mon 7/1/19 0% 15 Steel Reinforcement and poured conc. Footing 3 days Fri 6/21/19 Tue 6/25/19 0% 16 Form work for( 8) 16" square concrete columns 2 days Fri 6/21/19 Mon 6/24/19 0% Task Finish-only Split External Tasks Milestone External Milestone • Summary Deadline Project Summary Critical Inactive Task Critical Split Inactive Milestone Late Page 1 of 6 Inactive Summary Baseline Manual Task Baseline Milestone O Duration-only Baseline Summary Summary Rollup Progress Manual Manual Progress Manual Summary Start-only Slack EFTA00305825 MAHO BAY USVI, LLC: Construction Schedule ST JOHN, USVI ID Task Name Duration Start Finish Complete 17 (8) Poured in place 16" square concrete columns 4 days Tue 6/25/19 Fri 6/28/19 0% 18 Saw Cut trench in conc. Slab for new light fixture locations 1 day Fri 6/21/19 Fri 6/21/19 0% 19 Roofing 20 days Mon 7/1/19 Fri 7/26/19 0% 20 Installation of Steel beams 1 day Mon 7/1/19 Mon 7/1/19 0% 21 Roof framing 10 days Mon 7/1/19 Fri 7/12/19 0% 22 Roof Decking and Weather Protection 3 days Mon 7/15/19 Wed 7/17/19 0% 23 Installation of Concrete Roofing Tiles 9 days Fri 7/19/19 Wed 7/31/19 0% 24 Building Finishes 9 days Thu 8/1/19 Tue 8/13/19 0% 25 Tiling 5 days Thu 8/1/19 Wed 8/7/19 0% 26 Electrical 1 day Thu 8/1/19 Thu 8/1/19 0% 27 Installation of light fixltures and wiring 2 days Thu 8/1/19 Fri 8/2/19 0% 28 Final Clean-up 1 day Thu 8/8/19 Thu 8/8/19 0% Task Finish-only Split External Tasks Milestone External Milestone • Summary Deadline Project Summary Critical Inactive Task Critical Split Inactive Milestone Late Page 2 of 6 Inactive Summary Baseline Manual Task Baseline Milestone O Duration Baseline Summary -only Summary Rollup Progress Manual Manual Progress Manual Summary Start-only Slack EFTA00305826 IMAHO BAY USVI, LLC: Construction Schedule ST JOHN, USVI D Task Name 29 Substantial completion date 30 Complete Final Inspections 31 Complete punch list items from all inspections Duration 1 day Thu 8/8/19 Thu 8/8/19 0% 1 day Fri 8/9/19 Fri 8/9/19 0% 1 day Fri 8/9/19 Fri 8/9/19 0% Start !Finish Complete Task Finish-only Split External Tasks ]=Im Milestone External Milestone • Summary Deadline Project Summary Critical Inactive Task Critical Split Inactive Milestone Late Page 3 of 6 Baseline Inactive Summary Manual Task Baseline Milestone Duration•only Baseline Summary Manual Summary Rollup Progress Manual Summary Manual Progress Start-only Slack EFTA00305827 MAHO BAY USVI, LLC: Construction Schedule ST JOHN, USVI Resource Names Predecessors 2019 12016 12017 12018 12019 12020 LW LSI Tricon Tricon Tricon Tricon Tricon aricon _iricon II- aricon aricon Page 4 of 6 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only I I II 11.111111 Finish-only External Tasks External Milestone Deadline Critical Critical Split Late Baseline Baseline Milestone Baseline Summary Progress Manual Progress Slack 4- EFTA00305828 MAHO BAY USVI, LLC: Construction Schedule ST JOHN, USVI Resource Names Tricon Tricon Tricon Tricon Tricon Tricon Tricon Predecessors 21 2015 12016 2017 12018 12019 12020 1Jricon aricon Tricon Tricon Tricon Tricon L Tricon Task Split Milestone Finish-only External Tasks External Milestone ■ • Summary Deadline • Project Summary ■ Critical Inactive Task Critical Split Inactive Milestone Late ■ Page 5 of 6 Inactive Summary Baseline Manual Task Baseline Milestone Duration-only Summary Baseline Manual Summary Rollup Progress Manual Summary Manual Progress Start-only Slack EFTA00305829 MAHO BAY USVI, LLC: Construction Schedule ST JOHN, USVI Resource Names Tricon LSJ,Tricon Predecessors 2018 12016 12017 12018 12019 2020 Tricon LSJ,Tricon Page 6 of 6 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Late Baseline Baseline Milestone Baseline Summary Progress Manual Progress Slack • O EFTA00305830

📷 Images in this document (6 detected)

AI-generated factual descriptions of embedded images (llava:13b). These are searchable across the corpus.

[Image 1] The image shows a document titled "MAHABAY USVI LLC: CONSTRUCTION SCHEDULE." It appears to be a schedule or timeline for various construction tasks, possibly related to a pool and a building. The tasks are listed in a table format with columns for "Task," "Start Date," "End Date," and "Percentage Complete." The visible tasks include "Pool Shade Structure," "Engineering Doors," "Long Lead Procureme [Image 2] The image shows a construction schedule document. It lists various tasks and their corresponding dates, times, and percentages of completion. The document is titled "MAHANOY USVI LLC CONSTRUCTION SCHEDULE" and includes columns for "Task," "Start Date," "End Date," "Duration," and "Completion %." The tasks listed include activities such as "Roofing," "Concrete," "Electrical," and "Landscaping," amo [Image 3] The image shows a document titled "MAHANOY BAY USVI LLC Construction Schedule." It appears to be a table or spreadsheet with columns and rows, possibly listing construction tasks, dates, and completion percentages. The visible text includes names such as "John," "USVI," and "Mahanoy Bay USVI LLC." There are also dates and completion percentages listed, but the specific details are not fully visibl [Image 4] The image shows a construction schedule document. It lists various rooms and tasks, along with dates and times. The document is titled "MAHANOY BAY USVI LLC CONSTRUCTION SCHEDULE." The visible text includes names such as "Room," "Task," "Date," and "Time." There are also columns for "Room," "Task," "Date," and "Time." The document appears to be a professional or business-related item, possibly rel [Image 5] The image shows a digital representation of a construction schedule, which appears to be a Gantt chart. The chart is titled "MAHANOY BAY USVI LLC CONSTRUCTION SCHEDULE" and lists various tasks or phases of construction with corresponding start and end dates. The chart includes columns for the task name, start date, end date, and duration. There are also color-coded bars representing the progress o [Image 6] The image shows a document titled "MAHANOY BAY USVI LLC Construction Schedule." It appears to be a table or spreadsheet with columns and rows, possibly listing dates, names, and other details related to a construction project. The visible text includes names such as "St. John USVI," "Mahanoy Bay USVI LLC," and "Construction Schedule." There are also numerical values and dates, but the specific con