LSJ CONSTRUCTION
LSJ CONSTRUCTION
Subcontractor Payout
Project: Mechanical Desal
Trade: Water System
Subcontractor TSG Technologies, Inc
Invoice #
Phase # Requisition #05
11-200
Original Contract Sum:
Change Orders Submitted & Approved:
New Change Orders:
Total Work Contracted to Date:
Total Work Completed to Date:
Less Retainage:
Total Payments Made to Date:
Total Current Payment Due:
Balance to Finish including Retainage:
Sales Tax Liability: February 3, 2011
Requisition #05
Insurance expiration: March 1. 2011
Partial
X Final
$592.160.00
$6.905.00
$0.00
$599,065.00
95% $569,457.00
a. Subcontractor/Supplier is liable. explaii install only / tax
included in contract
b. Non-resident Subcontractor/Supplier Bond Applicable:
c. Use Tax to be paid by our company.
d. Shipping
Total Outlays for this contract incl. Sales or Use Tax: $569,457 00 I$0.00 /
$533,944.001/
$35,513.00 OF
$29,608.00
None
JEE approval attached
YES NO
Submitted Bill
Signed: jiff__
Date: February 3. 2011
Approved by: Emad
Signed.
Date )11-1 (I
I Invoice Attached
YES NO
X <
Approved by: Gary
Signed:
Date: February 3. 2011
Approved by:
Signed:
Date:
EFTA_R1_02014084
EFTA02687177
LSJ CONSTRUCTION
Project Methanicat Desat
hiboonlractor • full legal name -SG l'ecnnolLiniet lik
Phase M 1.2t!1
Trade Wale, System
Invoice d Region:Ion 405
enereeee 'Natation ,'. Mail' Payment
Partial Final
X
InvoicefReqe Dale Cf0 Amount Releinattle Due Pod Date Paid Chacke Balance I
Contract Amount I 2i22.C9 1..IC. I00 00
COitt
COS2
COs3
C044
CON.5 10.1 I; t a Watch Guard System 1.000 00
tOt 131 IJ Slotar / Insurance 1.000 00
01.08111Lost lime 4 905 00
Requisition PI 02/2210 Dottie') Phase • 8% 47.800 00 1100 47,800 00 47.800 %QV 000
Requisition a2 03e3w iti Procurement. 42% 248.280 00 C. (X) 24828000 248 280 Otiv,C, 000
Reqtrsition a3 08515+10 Ready to Snip 30% 171.548 0C 0 00 177,648 00 177.548 CUV 0.00
Requisition 44 tztat.ii 0 Equip on Ste - 10% 50.216 00 000 60.21800 60 215 On 0 01
Requisition 05 02/03/11 Substantial Cumpetion • .5% 20.604 00 U 00 2940600 29.808 00
02/03/11 CO's NZ 13 5.90500 000 5.905.00 590500
Requisition 46 Final COMPlObOn • 5%
Total 569,45700 000 569.457.00 533.944.00 _ 35.51300 Data Revised r ate,
C011eaCI AriltatiN • PeaSe
Contract
Co.,
Co.?
C004
C015 Plant 592.160.00
1:0
escn Guard i .000 00 Desorption
Swage i Insurance 1.00000 Div:mono
Lost limo 4.505 00 Description
Oesonpuon
Descupoon
Contracted To Date
Natant:* Cr Contract uaRetainatge L599.065.00,1
29.608 00
EFTA_R1_02014085
EFTA02687178
:11: SIG
WirjrliKartagitibleWee - .;
Name I Me St James. LID
Uo 4inancol Trust Company. Inc
Address 6100 Red Hook Ouaner B-3
City St Thomas
Slate USVI Zip 00802
Phone (340) 779-8054
All:, Gary Kerney 1
TInvoice Number 40-204-02-PRIM
Dale 2/3/7011
Order No.
SG Called Bob Petoisen
Michael Maio
Phone (340) 778-7766
Fax (340)774-9489
7tavywantmt . .44. .Z. 7ralliffliititi . Wit Prb0 Eit04550r9040
1 Pay Request 45 529608 00
t Change Order 112 51.00000
I Change Order 1/3 54.905 00
Payment Schedule:
a Task Percentage Payment
I Design Phase- NIP -t 8% 54/.80000
2 Begin Procurement - NTP 2 42% 5248.780 00
3 Ready to Ship 30% 5177648.00
Charge Order al 51.000.00
1 kquipment on Site 10% 559.21600
Cnartge Order rt2 51900 00
Change Order 43 54.905 40
5 Substanbal Completion 5% 529.608 00
6 Final Completion 5% 529.608 00
Total 100% 5599.065.00
Total per Contract 5599.065.00
Less Previously Invoiced: 5533.944.00
Total this Invoice: 535.513 00
Remaining Contract Value $29.608.00
Subtotal
Shipping and Handling
Taxes
Total invoice amount
Wire information.
TSG Technologies. Inc
Darby Bank and Trust
Routing number 061211168
Account number 133442 635.513 00
$0.00
535.513.00
EFTA_R1_02014086
EFTA02687179
task TSG MAXIK I VIRY DROP COulil
TO: DATE: October 13, 2010
FROM: TSG Technologies
CONTRACTOR CHANGE ORDER REQUEST
PROJECT NAME: Little St. James RO
PROJECT NUMBER:
ORIGINAL CONTRACT SUM $ 592.160 00
(Contract Dated - February 11. 2010)
PREVIOUSLY APPROVED CHANGE ORDERS $ 1 000 00
(Total Number of Approved Change Orders- 1)
REQUESTED CHANGE ORDER NO. 2 S 1 000 00
TOTAL $ 594 160 00
Description of Request (include time. schedule. authorizing associate)
Item1: Storage/insurance for RO equipment through December 2010 $1.000
TSG TECHNOLOGIES L.S.J., LLC
IbtLL-464L
Page 1 of
EFTA_R1_02014087
EFTA02687180
TS •••••• MAKING G (WRY DROP COW
TO • K rn
FROM- TSG Tecbnolo ies
CONTRACTOR CHANGE ORDER REQUEST
PROJECT NAME. Little St. James RO
PROJECT NUMBER: 40.204.02 DATE January 18. 2011
ORIGINAL CONTRACT SUM. $ 592 160,00
(Contract Dated - February 11. 2010)
PREVIOUSLY APPROVED CHANGE ORDERS $ 2 000 00
(Total Number of Approved Change Orders- 2)
REQUESTED CHANGE ORDER NO. 3 $ 4 905 00
TOTAL $ 599.065.00
Description of Request /include time, schedule, authorizing associate)
Item 1: Time lost due to power nol being available to TSG staff as of 1/19/11. Newest information
conveyed to TSG has power available at end of day 1/21/11. for a loss of 3 days.
Installers: 2 people x 9 hrs/day x $50/hr x 3 days $2.700
Project Manager: 1 person x 9 hrs/day x $65/hr x 3 days $1,755
Per Diem: 3 people x $50/day x 3 days $450
If work cannot be completed by 1/28/11. TSG's original finish date, then extra charges will be incurred for
housing and change ticket fees.
TSG TECHNOLOGIES LLC
Page 1 of I
EFTA_R1_02014086
EFTA02687181
Emad Hanna
From: Monique Har
Sent: Friday, February 04, 2011 10:42 AM
To: Emad Hanna
Subject: TSG
Attachments: TSG Req 5.pdf
Emad,
Attached for payment TSG Technologies, Inc Req 5 in the amount of $35,513.00. Project 1010 Code 11-200.
Monique
EFTA_R1_02014089
EFTA02687182
📷 Images in this document (6 detected)
AI-generated factual descriptions of embedded images (llava:13b). These are searchable across the corpus.
[Image 1] The image shows a document that appears to be a financial statement or invoice. It includes sections for "Vendor Name," "Invoice Number," "Date," "Amount," and "Payment Method." There are also checkboxes for "Paid," "Unpaid," and "Pending." The document is signed by two individuals, one on the bottom left and one on the bottom right. The visible text includes names, dates, and numerical figures, b
[Image 2] The image is a scanned document, specifically a financial statement or report. It contains tables with numerical data, including columns for dates, descriptions, and amounts. The document appears to be a record of financial transactions, possibly for a business or organization. There are no visible names, dates, places, or logos that can be described confidently. The text is too small to read the
[Image 3] The image shows a document that appears to be a financial statement or invoice. It contains various sections with headings such as "Invoice Number," "Date," "Bill To," "From," and "To." There are tables with columns for "Description," "Qty," "Unit Price," and "Total." The document includes numerical figures and a signature at the bottom. The visible text includes names, dates, and financial detail
[Image 4] The image shows a document that appears to be a contract or agreement. It includes sections with headings such as "Contractor Information," "Project Information," and "Payment Information." There are fields for the contractor's name, address, and contact information, as well as details about the project, including the project name, description, and start and end dates. The payment section lists th
[Image 5] The image shows a document that appears to be a construction payment request form. It includes fields for the project name, project number, date, and various details such as the contractor's name, the amount requested, and the description of the work performed. There is a logo at the top left corner that reads "TGS," which could be the name of the company or organization associated with the form.
[Image 6] The image appears to be a scanned document, possibly a letter or an invoice, with a header that includes the sender's name and contact information. The body of the document contains text, but the content is not fully visible due to the angle and resolution of the scan. The visible text includes a date and a reference number, but the specific details are not clear. The document is addressed to a re